Inland Container, Inc. v. United States

512 F.2d 1073, 21 Cont. Cas. Fed. 83,804, 206 Ct. Cl. 478, 1975 U.S. Ct. Cl. LEXIS 16
CourtUnited States Court of Claims
DecidedMarch 19, 1975
DocketNo. 350-70
StatusPublished
Cited by16 cases

This text of 512 F.2d 1073 (Inland Container, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Inland Container, Inc. v. United States, 512 F.2d 1073, 21 Cont. Cas. Fed. 83,804, 206 Ct. Cl. 478, 1975 U.S. Ct. Cl. LEXIS 16 (cc 1975).

Opinion

Per Curiam : This case comes before the court on exceptions by the parties to the recommended decision filed March 4, 1974, by Trial Judge David Schwartz, pursuant to Rule 134(h), having been submitted to the court on the briefs and oral argument of counsel. Upon consideration thereof, since the court agrees with the trial judge’s recommended decision, as hereinafter set forth, it hereby affirms and adopts the same as the basis for its judgment in this case. Therefore, it is concluded that plaintiff is entitled to recover and judgment is entered for plaintiff and against defendant in the sum of $34,831.72,

[482]*482OPINION OP TRIAL «JUDGE

Schwartz, Trial Judge:

This is an action for $92,570 as damages for breach by the Defense Depot at Ogden, Utah, of three contracts with plaintiff for the Depot’s requirements of fiberboard shipping boxes. The claim is here found valid. Damages, held assessable under the convenience-termination clauses in the contracts, are found to be proven under the third contract only, in the amount of $84,831.72.

The Defense Depot, a facility of the Defense Supply Agency, Department of Defense, stocks and, as needed, packs and ships electronic equipment, clothing and other supplies to military installations throughout the world, primarily, at the times involved, to installations in Southeast Asia. Plaintiff is a manufacturer of corrugated fiberboard boxes, with its principal place of business in Ontario, California. Beginning in 1967 the Depot awarded to plaintiff three consecutive, annual contracts for boxes. The first contract covered only Schedules VI and VII of the invitation, the second contract only Schedule VII. In the third contract, which extended from September 1969 to September 1970, plaintiff was awarded Schedules III through VI, a substantial portion of the total invitation and a significant increase over the previous contracts.

The contracts were what is known as requirements-type contracts. The first contract obligated the Depot “to order from the contractor all of its requirements” of the designated boxes “that may in the judgement [sic] of the contracting officer be required during the contract term.”1 The second and third contracts provided that “the Government shall [483]*483order from the Contractor all the * * * [boxes] which are required to be purchased by the” Depot.2

Prior to the award to the third contract, Depot officers, including the contracting officer — the Depot’s procurement officer for boxes — had solicited plaintiff, and other box manufacturers, to locate a branch plant near the Depot. The officers did this in the interest of promoting competition and facilitating Government orders of boxes. Plaintiff was willing, if it could get enough business from the Depot to warrant a branch plant. Accordingly, on receipt of the substantial award of the third contract, plaintiff established a second plant at Clearfield, Utah, not far from the Depot in Ogden, with the expectation that the Depot’s business would carry the plant for a year and the hope that meanwhile other business would be developed.

The alleged breach resides in the practice of the Depot, throughout the three contracts, of ordering the boxes it needed from the General Services Administration, under a system to be described, before placing an order with plaintiff pursuant to the contract in force. The Depot’s orders for plaintiff’s boxes during the third contract amounted to $146,099; during the same period orders placed with GSA for the type of boxes covered by the contract amounted to $446,720.

The Depot-GSA relationship was unknown to plaintiff until well into the third contract, when plaintiff had already established the branch plant and saw that it was practically idle for insufficient orders. The branch plant, opened in mid-November 1969, did a gross business of $54,000, of which $35,000 was for boxes for the Depot, before it closed in March 1970, with a loss of $35,000.

It appears that GSA, and particularly GSA Denver, with which the Depot dealt, stocked not only boxes but other supplies as well for requisition by federal agencies. Specifically, GSA regularly stocked most of the boxes on the [484]*484schedules of the contracts with plaintiff. Operating under requirements contracts, with box manufacturers other than plaintiff, providing for 70-day delivery, OSA ordered boxes in advance of the Depot’s needs, to meet those needs. The Depot paid GSA for the boxes; the payments went into a revolving fund which financed the system, and the price was fixed so that OSA would “break even” on the operation.

OSA and the Depot had a close working relationship involving forecasts of need by the Depot, periodically updated, a computerized system at GSA which would automatically reorder boxes when stocks fell below a pre-set level and the storage of boxes in GSA warehouses until the Depot called for them. Telephone orders were placed by the Depot for boxes needed urgently and deliveries or pick-ups could be arranged by telephone on GSA or Depot trucks. In consequence, GSA could deliver boxes to the Depot with great promptness, often on the same day, from stocks kept by GSA suppliers or warehouses as near to the Depot as Clear-field. If GSA Denver was unable to meet the Depot’s needs from its own stocks, it would draw on other GSA warehouses, in Texas or elsewhere.

The net result was that GSA stocked or was able promptly to provide a ready supply of most of the kinds of boxes used by the Depot. Plaintiff got the leavings, including, prominently, all of the Depot’s need for special boxes, called full-flap, difficult and time-consuming to make. Almost 85 percent of the boxes ordered from plaintiff under its third contract were these full-flap boxes. GSA did not stock these boxes.

The Depot was not without some doubts over its treatment of plaintiff, though, as will appear, its officers believed they were doing the correct thing under “regulations.” The contracting officer testified that at about the time of the award of the third contract it occurred to him that in the light of the Depot’s practice of ordering boxes from GSA, the requirements clauses in the outstanding contracts might be confusing or misunderstood. A clause was thereupon drafted, to be added to solicitations for such contracts, stating that “boxes available from Government Agencies will not be ordered under this contract” [emphasis in the original].

[485]*485What the effect of such a clause might have been — whether it gives sufficient notice of the practice described here — - need not be decided, for the clause was not added to any of the contracts now in suit. The episode is important as tending to show some awareness by the Depot that the contract words “required to be purchased” and “required,” might (as is now held) be taken to include the boxes ordered from GSA and purchased by it to meet the Depot’s requirements.

As a defense to the claim of breach, the Government says, first, that the boxes were not “purchased” (a word found only in the clause in the second and third contracts, see note 2, supra), but requisitioned. Except for this, there is apparently no contest of the basic proposition that the language used was clear enough to create an obligation to order from plaintiff all of the Depot’s requirements of boxes to be purchased. Goldwasser v. United States, 163 Ct. Cl. 450, 325 F. 2d 122 (1963); Locke v. United States, 151 Ct. Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott Timber Co. v. United States
65 Fed. Cl. 131 (Federal Claims, 2005)
AR Sales Co. v. United States
49 Fed. Cl. 621 (Federal Claims, 2001)
Datalect Computer Services, Ltd. v. United States
42 Cont. Cas. Fed. 77,243 (Federal Claims, 1997)
Design & Production, Inc. v. United States
35 Cont. Cas. Fed. 75,718 (Court of Claims, 1989)
Maxima Corporation v. The United States
847 F.2d 1549 (Federal Circuit, 1988)
Western Pioneer, Inc. v. United States
32 Cont. Cas. Fed. 73,617 (Court of Claims, 1985)
Hemet Valley Flying Service Co. v. United States
32 Cont. Cas. Fed. 73,278 (Court of Claims, 1985)
Ralph Construction, Inc. v. United States
32 Cont. Cas. Fed. 72,430 (Court of Claims, 1984)
Salem Engineering & Construction Corp. v. United States
31 Cont. Cas. Fed. 71,312 (Court of Claims, 1983)
Systems Architects, Inc. v. United States
31 Cont. Cas. Fed. 71,105 (Court of Claims, 1983)
R-D Mounts, Inc. v. United States
30 Cont. Cas. Fed. 71,059 (Court of Claims, 1983)
Kisco Co. v. United States
610 F.2d 742 (Court of Claims, 1979)
Media Press, Inc.
566 F.2d 1192 (Court of Claims, 1977)
Kalvar Corp. v. United States
543 F.2d 1298 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
512 F.2d 1073, 21 Cont. Cas. Fed. 83,804, 206 Ct. Cl. 478, 1975 U.S. Ct. Cl. LEXIS 16, Counsel Stack Legal Research, https://law.counselstack.com/opinion/inland-container-inc-v-united-states-cc-1975.