Salem Engineering & Construction Corp. v. United States

31 Cont. Cas. Fed. 71,312, 2 Cl. Ct. 803, 1983 U.S. Claims LEXIS 1687
CourtUnited States Court of Claims
DecidedJuly 7, 1983
DocketNo. 345-80C
StatusPublished
Cited by27 cases

This text of 31 Cont. Cas. Fed. 71,312 (Salem Engineering & Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salem Engineering & Construction Corp. v. United States, 31 Cont. Cas. Fed. 71,312, 2 Cl. Ct. 803, 1983 U.S. Claims LEXIS 1687 (cc 1983).

Opinion

OPINION

MAYER, Judge.

Plaintiff Salem Engineering and Construction Corporation (Salem) brought this suit under the Contract Disputes Act of 1978, 41 U.S.C. § 609(a)(1) (Supp. IV 1980), for an equitable adjustment of a construction contract price for work performed on instructions of defendant allegedly exceeding the requirements of the contract. The government defended on the basis that Salem’s interpretation of the contract is unreasonable and it had a duty to request clarification if the contract specifications and drawings were unclear or ambiguous. Trial was held in Boston, Massachusetts.

FACTS AND CONTENTIONS

Salem was awarded a contract for the extension and remodeling of the Social Security Administration District Office Building in Haverhill, Massachusetts. In the course of performance, a dispute arose over the scope of roofing work required. When Salem was asked by defendant’s Clerk of the Works how it intended to protect the existing occupied building from damage during reroofing, Salem responded that the contract required it to remove and install only so much of the existing roof as was necessary to join it to the roof installed on the new addition. The Clerk replied that under the contract Salem was required to also remove and replace the roof on the existing building. At Salem’s request, a written directive to that effect was issued by the General Services Administration (GSA) and, under protest, Salem performed the reroofing work.

After completion of the project, Salem submitted a written claim to GSA on March 5, 1979, with a breakdown of costs for removing and replacing the existing roof and met with GSA representatives to discuss the matter. Three months later, by letter of June 14, 1979, Salem requested a final decision from the contracting officer pursuant to the disputes clause of the contract. Salem’s claim for an adjustment was denied and this suit followed.

[805]*805The disagreement centers around the interpretation of paragraph 2.2 of contract section 0211 on demolition, and general note No. 4 of drawing 27-A-301. Paragraph 2.2 provides:

Remove existing east wall shown to top of foundation walls. Remove all interior partitions as indicated on drawings. Remove exterior grade mounted lighting fixtures. Remove all existing carpet. Remove existing drinking fountain and wheelchair toilet stalls and wall rails. Remove existing B.U. [built up] Roof, Roof insulation and gravel stop. (Emphasis added.)

Note No. 4 on the drawing states:

Remove existing B.U. [built up] roof, insulation and gravel stop. Install new tapered urethane insulation, B.U. roof and gravel stop. Add additional blocking and base flashing as required.

Defendant argues that these provisions clearly require Salem to remove and replace the entire existing roof.

Salem, on the other hand, says that when these provisions are read together with the contract drawings and other specifications, and in light of the primary purpose of the contract, construction of an addition to the office building, it is reasonable to interpret them as requiring removal and replacement of the existing roof only to the extent necessary to join it to the roof on the new addition.

As support for this interpretation, Salem points to the following three paragraphs of contract section 01000 on special conditions:

2.1 Existing structures shown shall remain in place except as otherwise noted on drawings and specified under Section [0211], Demolition.
22.1 Unless otherwise noted on drawings or specified, new work in extension of existing conditions shall correspond in all respects with that to which it connects, or to similar existing conditions, in materials, workmanship and finish.
23.1 Existing work shall be cut, drilled[,] altered, removed, or temporarily removed and replaced as necessary for performance of work under the contract. Work that is replaced shall match similar existing work. Structural members shall not be cut or altered, except where noted on drawings, without authorization of the Contracting Officer. Work remaining in place which is damaged or defaced during this contract shall be restored to the condition existing at time of award of contract.

In addition, it cites drawings 27-A-301 and 27-A-303. The principal diagram on drawing 27-A-301 represents an aerial view of the building as it would appear after completion of the addition and contains arrows delineating the existing roof in contrast to the roof on the new structure. It shows the location for a “new” roof scuttle on the “existing” roof, “new” roof drains on the addition, and “new” blacktop and curbing along the side of the building. The north, south, east, and west elevation diagrams on the drawing are shaded to represent the new addition, but not the roof on the existing building. The detail schematic of the gravel stop in the north elevation is shown in the new addition and shows only one layer of insulation as required by the contract for the new roof. In drawing 27-A-303, however, the detail at the air conditioning unit on the existing roof is shown with two layers of insulation, which was the construction of that roof. Salem argues that if it was required to remove and replace the entire existing roof the air conditioning unit detail should show only one layer of insulation as required for the new roof under the contract, just as the one for the gravel stop did.

Defendant counters that paragraph 2 of the general provisions section says that “[i]n case of difference between drawings and specifications, the specifications shall govern,” and “[i]n case of discrepancy either in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing.” Defendant further contends that Salem’s reliance on the absence of shading on the existing roof in the elevation details of drawing 27-A-301 is mis[806]*806placed because the diagrams do not indicate the scope of the work to be performed. No significance should be attached to the fact that the detail at the gravel stop is shown on the new addition because it is merely an example which could have been shown anywhere on the roof, new or existing, and defendant notes that the steel deck in that detail is labeled “new and existing.”

Defendant also points out that the typical duct opening diagram on drawing 27-A-303 contains the phrase, “existing roof deck and structure to remain,” along with “(new) 4-ply built-up roofing.” These phrases indicate that a new roof was to be placed on the existing structure. Finally, defendant asserts that Salem’s interpretation of the contract must be rejected because it gives no meaning to the directive in the specification and drawing note to “[rjemove existing B.U. Roof, insulation and gravel stop.”

CONTRACT INTERPRETATION

The initial inquiry is whether the contract specifications and drawings with respect to removal and replacement of the existing roof are ambiguous. The contract is ambiguous if it sustains the interpretations advanced by both parties, Max Drill, Inc. v. United States, 192 Ct.Cl. 608, 627, 427 F.2d 1233

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Suburban Maintenance & Constr. v. Ohio Dept. of Transp.
2016 Ohio 7060 (Ohio Court of Claims, 2016)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
North American Construction Corp. v. United States
56 Fed. Cl. 73 (Federal Claims, 2003)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
P.R. Burke Corp. v. United States
47 Fed. Cl. 340 (Federal Claims, 2000)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Nicholson v. United States
29 Fed. Cl. 180 (Federal Claims, 1993)
Delcon Construction Corp. v. United States
38 Cont. Cas. Fed. 76,476 (Federal Claims, 1993)
Reliance Insurance v. United States
36 Cont. Cas. Fed. 75,892 (Court of Claims, 1990)
Seaboard Lumber Co. v. United States
19 Cl. Ct. 310 (Court of Claims, 1990)
Dawco Construction, Inc. v. United States
35 Cont. Cas. Fed. 75,755 (Court of Claims, 1989)
Design & Production, Inc. v. United States
35 Cont. Cas. Fed. 75,718 (Court of Claims, 1989)
Dynamics Corp. of America v. United States
35 Cont. Cas. Fed. 75,663 (Court of Claims, 1989)
Ralph Larsen & Son, Inc. v. United States
35 Cont. Cas. Fed. 75,662 (Court of Claims, 1989)
XXX Construction Co. v. United States
35 Cont. Cas. Fed. 75,631 (Court of Claims, 1989)
Avedon Corp. v. United States
35 Cont. Cas. Fed. 75,592 (Court of Claims, 1988)
Tilley Constructors & Engineers, Inc. v. United States
35 Cont. Cas. Fed. 75,567 (Court of Claims, 1988)
Randallstown Plaza Associates v. United States
13 Cl. Ct. 703 (Court of Claims, 1987)
Shank-Artukovich v. United States
34 Cont. Cas. Fed. 75,372 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,312, 2 Cl. Ct. 803, 1983 U.S. Claims LEXIS 1687, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salem-engineering-construction-corp-v-united-states-cc-1983.