Corbetta Construction Co. v. United States

461 F.2d 1330, 198 Ct. Cl. 712, 1972 U.S. Ct. Cl. LEXIS 85
CourtUnited States Court of Claims
DecidedJune 16, 1972
DocketNo. 369-65
StatusPublished
Cited by11 cases

This text of 461 F.2d 1330 (Corbetta Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corbetta Construction Co. v. United States, 461 F.2d 1330, 198 Ct. Cl. 712, 1972 U.S. Ct. Cl. LEXIS 85 (cc 1972).

Opinion

Per Curiam::

This case was referred to Trial Commissioner Harry E. Wood with directions to prepare and file bis opinion on tbe issues of plaintiff’s motion and defendant’s cross-motion for summary judgment as to Claim 3 of tbe petition under the order of reference and Rule 166(c). Tbe commissioner has done so in an opinion and report filed on December 30, 1971, wherein such facts as are necessary to the opinion are set forth. Defendant filed a request for review by the court of the commissioner’s opinion, plaintiff urged its adoption by the court and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the opinion and recommended conclusion of the trial commissioner, it hereby adopts the same, as hereinafter set forth, as the basis for its judgment in this case. Therefore, plaintiff’s motion for summary judgment on Claim 3 is granted, defendant’s cross-motion for summary judgment is denied and further proceedings on Claim 3 are stayed pursuant to (and subject to the terms of) Rule 167, for 90 days to afford plaintiff an opportunity to obtain administrative consideration of the amount due it in accordance with this opinion.

OPINION OE COMMISSIONER

Wood, Commissioner: The amended petition in this case, stating three separate claims, pertains to a 1953 contract between plaintiff and the Department of the Navy for the construction of a dry dock at the Brooklyn, New York, Naval Shipyard.1 In Claim 3, presently before the court on cross-[715]*715motions for summary judgment, plaintiff seeks review, under familiar standards,2 of a decision of tlie Armed Services Board of Contract Appeals3 denying plaintiff’s claim to an equitable adjustment for certain subgrade repairs required of it, on the ground that plaintiff was contractually obligated to perform them.

For reasons which follow, it is concluded that plaintiff is entitled to recover on Claim 3.

Perhaps because the question administratively considered was so clearly one of law, the Board opinion is factually rather sparse. As an aid to understanding of this claim, the indisputable, if not essentially undisputed, factual background of the controversy will briefly be sketched. Foster Constr. C. A. v. United States, 193 Ct. Cl. 587, 600, 435 F. 2d 873, 879 (1970); Bay D. Bolander Co. v. United States, 186 Ct. Cl. 398, 409 (1968).

The contract in suit (NOy-74770), dated August 4, 1953, was a lump-sum, fixed-price, contract requiring plaintiff to furnish the materials and perform the work necessary to reconstruct “Dry Dock No. 3” at the Brooklyn Naval Shipyard, “complete and ready for use.” In general terms, plaintiff was to demolish an ancient timber dry dock, and to replace it with a substantially larger one of modern design.4

The contract contained standard Disputes, Changes and Extras, and Changed Conditions clauses, as well as voluminous specifications, schedules and drawings designated Specification 35705 (with Addenda 1 through 5). Because of funding limitations, the original contract called for construction of only a portion of the dry dock ultimately intended, at a lump-sum price of $8,662,000. Subsequently, change orders {inter alia) increased the scope of the work, and raised the contract price to more than $12,775,000. The dry dock was finally accepted by the Navy as complete on February 3, 1960. Corbetta Constr. Co. v. United States, 187 Ct. Cl. 409, 413, 408 F. 2d 450, 452 (1969).

[716]*716The contract specifications broadly delineated the scope of the work to be performed as follows:

1-01 General intention. * * * to provide and secure a dry dock and its appurtenances * * * complete and ready for use.
1-02 General deseription. Tbe dry dock of reinforced concrete construction, founded on piles, having inside dimensions approximately 770 feet long and 116 feet wide with a 41 foot depth, will be constructed on the site of the existing timber constructed, relieving type Dry Dock No. 3. The new dock consists of a relieved section of approximately 642 feet in length and a gravity section of approximately 128 feet in length * * *. Dock construction will include: a perimeter cofferdam and cellular cofferdam of the Contractor’s design; the sheeting for the perimeter cofferdam shall remain in place complete; temporary dewatering facilities, to permit all construction to be done in the dry; the demolition of existing dry dock * * * ; sand-gravel back fill with embedded under-drains for the new dock floor slab of the relieved section; reinforced concrete floor with embedded inserts; reinforced concrete walls providing pipe and service galleries * * *; pump well together with its flooding and dewatering appurtenances * * *.

The new dry dock was to be a “graving” one, i.e., essentially a rectangular lined excavation located at the edge of the shore of a harbor or other body of water, with an entrance, and a pumping plant for removing inside water. There are several subclassifications of graving dry docks, two of which were combined in the overall design of Dry Dock No. 3. The shorter outboard section of the dry dock was of “gravity” design, incorporating a massively constructed floor and walls to ensure that the section would remain firmly in place in the mud and water bearing soil at the water’s edge. The larger inboard section of the dock was of “relieved” design.5

[717]*717Prior to commencement of excavation for the dry dock,6 plaintiff was to drive into the ground, and surround the entire work area with, a kind of subsurface fence or wall composed of interlocking steel sheet piling. The Claim 3 dispute concerns the sheet piling, or “perimeter cofferdam”, surrounding the relieved section of the dry dock at the inboard end and on the two sides.7

In essence, plaintiff contends that it (a) rightly, or (b) in any event, actually and reasonably, construed defendant’s specifications as requiring a “perimeter cofferdam” having only the function of permitting construction “work in the dry”, and (on either theory) that, after completion of the work, plaintiff was not contractually responsible for maintaining the cofferdam’s integrity its watertight character) below subgrade. Defendant asserts, however, that its specifications required, in clear and unambiguous terms, that the cofferdam serve not only to permit construction “in the dry”, but also as a permanent water cut-off wall below sub-grade, and that plaintiff was therefore contractually obligated to perform the repairs required at no additional cost to defendant.

Those additional specification provisions8 relevant to decision on these conflicting interpretations are as follows:

SECTION 2 DEMOLITION AND EXCAVATION 2-05 Order of Procedure. The construction methods shall be such as to accomplish the work in the dry. The methods used by the Contractor shall be approved by the Ofiicer-in-Charge.
2-06 Cofferdam
a. The contractor shall provide a perimeter cofferdam of the type and in location shown on the drawings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CJP Contractors, Inc. v. United States
45 Fed. Cl. 343 (Federal Claims, 1999)
Westinghouse Electric Corp. v. United States
42 Cont. Cas. Fed. 77,332 (Federal Claims, 1998)
Darwin Construction Co. v. United States
39 Cont. Cas. Fed. 76,673 (Federal Claims, 1994)
Nicholson v. United States
29 Fed. Cl. 180 (Federal Claims, 1993)
Olympic Marine Services, Inc. v. United States
792 F. Supp. 461 (E.D. Virginia, 1992)
Hoppmann Corp. v. United States
35 Cont. Cas. Fed. 75,720 (Court of Claims, 1989)
XXX Construction Co. v. United States
35 Cont. Cas. Fed. 75,631 (Court of Claims, 1989)
Salem Engineering & Construction Corp. v. United States
31 Cont. Cas. Fed. 71,312 (Court of Claims, 1983)
Folk Construction Co. v. United States
31 Cont. Cas. Fed. 71,247 (Court of Claims, 1983)
Northwestern Industrial Piping, Inc. v. United States
467 F.2d 1308 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
461 F.2d 1330, 198 Ct. Cl. 712, 1972 U.S. Ct. Cl. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corbetta-construction-co-v-united-states-cc-1972.