Jamsar, Inc. v. The United States

442 F.2d 930, 194 Ct. Cl. 819, 1971 U.S. Ct. Cl. LEXIS 125
CourtUnited States Court of Claims
DecidedMay 14, 1971
Docket205-68
StatusPublished
Cited by37 cases

This text of 442 F.2d 930 (Jamsar, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jamsar, Inc. v. The United States, 442 F.2d 930, 194 Ct. Cl. 819, 1971 U.S. Ct. Cl. LEXIS 125 (cc 1971).

Opinion

LARAMORE, Judge.

This is a Wunderlich Act 1 review casé that comes before the court on cross-motions for summary judgment. As one would expect from the notation of the Wunderlich Act this is a government contract case and it involves a sum of approximately $18,500, plus interest. It comes to us following a full hearing by the General Services Contract Board of Appeals (GSBCA) and, therefore, we are first concerned with the scope of our review. Consequently, the opinion will initially discuss the applicability of the Wunderlich principles (and the cases decided pursuant thereto). This will follow a thorough presentation of the facts and will precede the discussion of plaintiff’s claims. In conclusion we shall find that the defendant is clearly entitled to have its motion granted and the plaintiff’s petition will be dismissed.

The pertinent facts are actually quite simple; it is the interjection of the human element that makes things complicated. It all began when the defendant, through the General Services Administration, invited several small business concerns to submit bids for the painting of Federal Building No. 1, Third & C Streets, SW., Washington, D.C. These bids were to contain estimates for painting the exterior as well as the interior of the second and third stories. However, the dispute to be discussed herein arises only as to the interior painting and, therefore, no further references will be made to exterior painting.

Along with the invitation to bid, the defendant furnished specifications for the work to be done. Included was an “Estimated Cost Range” which provided for a cost limit of “less than $25,000.” Pursuant to these specifications and costs limitation, the plaintiff submitted its bid of $15,400 and on May 31, 1967 plaintiff was awarded the contract.

Subsequent to awarding the contract and during a preconstruction conference on June 14, 1967, a dispute arose between the parties to the contract. This dispute, which forms the basis for the present action, centered around just how much of the second and third stories plaintiff was to paint. It appears that the building in question was designed so that it consisted of corridors and wings. At the end of the wings are located office space in which can be found the ordinary office furniture, bookcases, etc. Also found in these wings are filing cabinets which are used by the occupants of Building No. 1 in their normal course of business activity. The corridors do not contain any furniture, nor are they used as work spaces, but they do have benches located therein. Moreover, restrooms can be found adjoining the corridors as well as two cleaning closets. These facts, insignificant as they may appear, form the background for the dispute that first arose on June 14,1967.

*932 Plaintiff contended at the conference, and continues to contend, that the specifications required the contractor to paint only the corridors and the adjoining restrooms. Defendant differed with this contention at the initial confrontation and has continuously advocated the proposition that the specifications clearly and concisely notify the contractor that the area to be painted includes not only the corridors but the work spaces and rooms found within the building". This was the position of the contracting officer and it was supported by the GSBCA (Appeal of Jamsar, Inc., GSBCA-2417). It is now our task to decide whether the GSBCA reached a conclusion which is not arbitrary, capricious, fraudulent or “so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence” (41 U.S.C. § 321); or, conversely, we must decide whether this is the type of case that involves simply a question of law. If we are concerned with the latter in that case the decision of the Board would not be binding on this court and we must then pass on the merits of plaintiff’s claim. Beacon Construction Company of Massachusetts v. United States, 314 F.2d 501, 161 Ct.Cl. 1 (1965); Gorn Corp. v. United States, 424 F.2d 588, 191 Ct.Cl. 560 (1970). To decide the above-noted question requires an understanding of the contentions made by plaintiff.

First and foremost plaintiff contends that the specifications as to the work to be performed were ambiguous. And that since they were ambiguous, the burden of that ambiguity should fall on the party who drew the specifications. Therefore, plaintiff alleges it should recover the additional $18,500 of expenses incurred in painting an area greater than was contemplated in the original bid.

Secondly, and as an alternative assertion, plaintiff asks for reformation of the contract due to a mistake in the bid. As for the merits of this claim, a thorough discussion will follow; however, at this point the mistake allegation, along with the ambiguity contention, is mentioned only in reference to the scope of our review.

As for the decision of the Board concerning the first claim of plaintiff, it is unquestionably a matter of interpretation of the specifications and thus a question of law. Consequently, neither this court nor the plaintiff is bound by the determination of the ASBCA 2 . Bishop Engineering Co., Inc. v. United States, 180 Ct.Cl. 411 (1967); Maxwell Dynamometer Co. v. United States, 386 F.2d 855, 181 Ct.Cl. 607 (1967); Vann v. United States, 420 F.2d 968, 190 Ct.Cl. 546 (1970). However, in reference to the alternative assertion of mistake, it is not quite as easily classified. Our problem here was aptly stated by Judge Durfee in Bromion, Incorporated v. United States, 411 F.2d 1020, 1023, 188 Ct.Cl. 31, 36 (1969), when he said “[t]he determination as to whether an issue is one of fact or of law is one of the most complex and perplexing questions facing a court.”

To resolve this question, we again find the Bromion ease helpful. Citing Professor Corbin, 3 Corbin on Contracts, section 614, at page 725, Judge Durfee points out that for this type of case “a court will not decree reformation unless it has convincing evidence that the parties expressed agreement and an intention to be bound in accordance with the terms that the court is asked to establish and enforce.” (411 F.2d 1020, 1023, 188 Ct.Cl. 31, 36) In our opinion this quotation applied purely to the scope of review issue now at hand indicates that the reformation for mistake issue is a *933 difficult one to classify. It is filled with issues of interpretation and also requires considering questions of fact; it is truly one of those areas that makes application of the Wunderlich standards quite difficult. See Bromion, Inc., supra. In any event, a final decision on this partiular point is not crucial to our case. Likewise for the ambiguity issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
P.R. Burke Corp. v. United States
47 Fed. Cl. 340 (Federal Claims, 2000)
Patel v. Harless
926 P.2d 963 (Wyoming Supreme Court, 1996)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Hydro Group, Inc. v. United States
35 Cont. Cas. Fed. 75,723 (Court of Claims, 1989)
Yaist v. United States
17 Cl. Ct. 246 (Court of Claims, 1989)
Beck v. United States
16 Cl. Ct. 655 (Court of Claims, 1989)
Bromley Contracting Co. v. United States
34 Cont. Cas. Fed. 75,415 (Court of Claims, 1987)
Edward R. Marden Corporation v. United States
803 F.2d 701 (Federal Circuit, 1986)
Dynamics Corp. of America v. United States
33 Cont. Cas. Fed. 74,498 (Court of Claims, 1986)
Sperry Corp. v. United States
33 Cont. Cas. Fed. 74,234 (Court of Claims, 1986)
Raytheon Co. v. United States
31 Cont. Cas. Fed. 71,309 (Court of Claims, 1983)
Howard v. United States
31 Cont. Cas. Fed. 71,104 (Court of Claims, 1983)
A & K Plumbing & Mechanical, Inc. v. United States
30 Cont. Cas. Fed. 70,877 (Court of Claims, 1983)
Mark A. Carroll & Son, Inc. v. United States
29 Cont. Cas. Fed. 82,684 (Court of Claims, 1982)
Summit Timber Co. v. United States
677 F.2d 852 (Court of Claims, 1982)
SCM Corp. v. United States
675 F.2d 280 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
442 F.2d 930, 194 Ct. Cl. 819, 1971 U.S. Ct. Cl. LEXIS 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jamsar-inc-v-the-united-states-cc-1971.