Mark A. Carroll & Son, Inc. v. United States

29 Cont. Cas. Fed. 82,684, 231 Ct. Cl. 722, 1982 U.S. Ct. Cl. LEXIS 309, 1982 WL 25206
CourtUnited States Court of Claims
DecidedJune 11, 1982
DocketNo. 19-81C
StatusPublished

This text of 29 Cont. Cas. Fed. 82,684 (Mark A. Carroll & Son, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mark A. Carroll & Son, Inc. v. United States, 29 Cont. Cas. Fed. 82,684, 231 Ct. Cl. 722, 1982 U.S. Ct. Cl. LEXIS 309, 1982 WL 25206 (cc 1982).

Opinion

This Wunderlich Act1 case comes before us on cross-motions for summary judgment. The sole issue is whether a contract entered into between plaintiff and the U. S. Postal Service for alterations to a post office included the installation of an air conditioning (ac) system. The Postal Service Board of Contract Appeal ( psbca or board) upheld the decision of the contracting officer that the contract required such installation. Plaintiff timely appealed to this court. For the reasons stated below, we affirm the decision of the board.

On September 9, 1975, defendant issued Invitation for Bid (Construction Contract) (hereafer ifb), No. 249955-76-A-0004 for alterations to the U.S. Post Office in Franklin, New Hampshire.2 On the front page of the ifb was the following description: "The work includes demolition of a loading platform, construction of a new loading platform, new electrical lighting and related electrical work, lobby and screenline renovations and installation of an air conditioning system.” Estimated cost of the project was between $25,000 and $100,000. The ifb contained the statement that any request for explanations of the ifb, drawings, specifications, etc., must be submitted in writing. Bidders with technical questions relating to plans or specifications were directed to contact two individuals, one [723]*723of whom was followed by the designation "(Air Conditioning Work only).” Apparently defendant’s architect-engineer designed all of the project except for the AC system, whose drawings and specifications were supplied by an outside engineering firm.

Plaintiff, a Massachusetts corporation, was not originally sent the ifb. After procuring the ifb on its own, plaintiff, on September 15, 1975, requested a set of plans and specifications for the project. The specifications sent to plaintiff on September 17, 1975 consisted of two parts, both numbered "ifb No. 249955-76-A-0001.” One part of these technical provisions dealt with components which in the aggregate constituted an ac system, while the other part dealt with the general construction aspects of the alterations to the building. Plaintiff was also sent 12 drawings to which a bidder’s work was to conform: 7 drawings related to construction work, 2 to electrical work, and 3 drawings for the ac system. The designer of the AC drawings apparently considered the work shown to be the subject of a separate contract for ac work only.3 This premise is evidenced by two facts: (1) on the drawings were the notations "n.i.c.” (not in contract) at the point where the ac system connected to the existing electrical system; and (2) the statement in the drawings that the ac contractor would have to coordinate his work with that of the general construction contractor.

Before the close of the date for bids, three bid amendments were issued, and the original closing date of October 9, 1975, was ultimately extended to October 30, 1975. After receipt of the drawings (on or around September 17, 1975), plaintiff began to prepare its bid. On October 26, 1975, or October 28,1975, plaintiffs president telephoned the designated contract specialist to inquire about certain matters relating to the contract, one of which was "the extent of the coordination on the air conditioning.” Plaintiffs president was transferred to a member of the technical staff, who advised him that he believed that the ac work would be part of the plaintiffs contractual duties. Plaintiffs president then asked if he "could rely on this belief as binding” [724]*724and was told it was up to him to interpret the contract and referred him to the ifb section regarding explanations to bidders.4 After this conversation, plaintiff’s president examined the specifications and drawings and apparently concluded that the installation of the ac system was not required (for reasons discussed later). He later tried to reach the ac system’s designer, but failed to contact him. Plaintiffs president made no further attempts (before submitting the bid) to get an interpretation of the contract and never contacted the contracting officer, although it is conceded he could have done so.

Plaintiff submitted a bid of $82,764, presumably based upon its conviction that the installation of the ac system was not part of the work mandated by the contract. Plaintiff was low bidder by $1,111 and was awarded the contract, No. 249955-76-V-0088-00, on November 7, 1975. The contract, by its terms, incorporated the specifications (and amendments thereto) and drawings contained in ifb No. 249955-76-A-0004. Work was to be completed by late spring 1976.

Even before work on the project began, a dispute broke out on whether plaintiff was required to install an ac system providing cool air as well as heat. Pursuant to the disputes clause of the contract, plaintiff sought the contracting officer’s opinion on whether the contract required plaintiff to install an ac system. On February 10, 1976, the contracting officer issued a final decision informing plaintiff that the ac work was required by the contract. Plaintiff timely appealed this decision to the psbca. On June 20, 1977, the psbca issued its decision denying plaintiffs appeal of the contracting officer’s decision. On January 15, 1981, plaintiff filed its petition in this court.

Plaintiffs basic argument is that at the time of the signing of the construction contract, it was never intended that plaintiff was responsible for installation of the ac equipment. Rather, defendant tried to "inject” this requirement by "insinuating” it into the contract after the bid award. Defendant, plaintiff contends, originally intended the ac work be the subject of a wholly separate contract. [725]*725Evidence of this intent is seen through the disparity in the numbering of the technical provisions (numbered, in pertinent part, "0001” instead of "0004,” the number of the ifb) and the notations "n.i.c.” and statement of coordination with the "other” contractor contained in the ac drawings. As a consequence, plaintiff believed that the ac technical specifications and drawings included in the bid package were only there so that the general construction contractor could coordinate its work with the separate ac contract. Plaintiff therefore states that the psbca’s decision to the contrary is arbitrary, capricious and lacking in substantial evidence, and seeks damages of $60,000.

As an initial matter, defendant argues that we should dismiss the petition because plaintiff has failed to comply with the Rules of this court. Specifically, defendant states that plaintiff has failed to comply with Rule 163(b)(3), applicable to Wunderlich Act reviews, by omitting citations to the board’s decision and references to the administrative record in its brief in support of summary judgment. Defendant cites Jet Constr. Co. v. United States, 209 Ct. Cl. 200, 204, 531 F.2d 538, 540 (1976), in which this court stated:

In a Wunderlich Act review case the * * * plaintiff has the burden to specify the facts and circumstances contained in the Board’s record which make the Board’s decision lacking in substantial evidence.” [Citations omitted.] Plaintiff, in this case, has done little more than place the Board record before the court, and challenged the court to find error in the record rather than properly taking up the challenge itself of establishing factual or legal error in the Board’s decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Carlo Bianchi & Co.
373 U.S. 709 (Supreme Court, 1963)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Koppers Company, Inc. v. The United States
405 F.2d 554 (Court of Claims, 1968)
Jamsar, Inc. v. The United States
442 F.2d 930 (Court of Claims, 1971)
Maxwell Dynamometer Co. v. United States
386 F.2d 855 (Court of Claims, 1967)
Arundel Corp. v. United States
515 F.2d 1116 (Court of Claims, 1975)
Jet Construction Co. v. United States
531 F.2d 538 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
29 Cont. Cas. Fed. 82,684, 231 Ct. Cl. 722, 1982 U.S. Ct. Cl. LEXIS 309, 1982 WL 25206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mark-a-carroll-son-inc-v-united-states-cc-1982.