Jet Construction Co. v. United States

531 F.2d 538, 22 Cont. Cas. Fed. 80,144, 209 Ct. Cl. 200, 1976 U.S. Ct. Cl. LEXIS 74
CourtUnited States Court of Claims
DecidedMarch 17, 1976
DocketNo. 402-74
StatusPublished
Cited by13 cases

This text of 531 F.2d 538 (Jet Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jet Construction Co. v. United States, 531 F.2d 538, 22 Cont. Cas. Fed. 80,144, 209 Ct. Cl. 200, 1976 U.S. Ct. Cl. LEXIS 74 (cc 1976).

Opinion

Durfee, Senior Judge,

delivered the opinion of the court:

In this contract suit plaintiff seeks Wunderlich Act (41 U.S.C. §§ 321, 322 (1910)) review of a decision of the General Services Administration Board of Contract Appeals (Board) denying its claim for additional compensation on a building renovation contract between plaintiff and the General Services Administration (GSA). The parties’ respective motions for summary judgment brings the case before this court without challenge to the bulk of the underlying facts. As neither party contests the majority of the Board’s factual determinations, as stated in its opinion, they will be restated here only in abbreviated form. A fuller factual picture appears in the Board’s reported decision, Jet [202]*202Construction Co., Inc., GSBCA No. 3348, 74-1 BCA ¶10,560, affirmed on reconsideration, 74-1 BCA ¶10,'641. Tihe Board decisions are affirmed for the reasons stated below.

In March 1970, plaintiff contracted with the GSA on a firm-fixed price basis to furnish and install air conditioning and lighting in an existing Government building in Trenton, New Jersey. Plaintiff subcontracted the air conditioning part of its contract to Hudik-Ross, Inc., on whose behalf it brings this appeal. The air conditioning part of plaintiff’s contract called for the supply and installation of wall mounted packaged terminal air conditioning and heating units meeting specific contract requirements. The contract stated detailed mechanical, installation, performance and other specifications required of the units to be supplied under the contract without any designation as to a particular brand name or manufacturer. To insure that the supplied units complied with the stated contract specifications, defendant as part of the contract provisions, required plaintiff to submit a list of proposed materials for approval.

The parties’ contract provided:

21-03. Approval of Material
a. Within 60 days after the receipt of notice to proceed, the contractor shall submit to the Architect a complete list, hereinafter called the “Materials List,” showing for each item in Material Schedule set forth below the name of the manufacturer of the product that he proposes to use in the project. Consideration will not be given to partial lists submitted from time to time. The Architect will forward the above list with his recommendations to the Contracting Officer for final action.

Failing the contractor’s compliance with the above contract provision, defendant reserved the right to select materials for use in the renovation work at no additional cost to the Government:

21-03. * * *
h. Should the Contractor fail to comply with any of the requirements of the preceding subparagraphs, i.e.:
1. Fail to submit the “Material List” in accordance with the above schedule to the Architect or the Public Buildings Service for approval within 60 days after the date of receipt of notice to proceed;
[203]*2032. Fail to name items in accordance with. Specification requirements and of the best quality and grade;
then the right is reserved by the Public Buildings Service to select any or all items in the above Material Schedule, which selection shall he final and binding upon the Contractor. The materials selected or approved, as the case may be, by the Public Buildings Service shall be used in the work at no additional cost to the Government.

Plaintiff received its notice to proceed on April 15, 1970 and on April 27, 1970, submitted data on ‘Climate Master’ air conditioning units manufactured by Cool-Heat Corp. for approval. Defendant disapproved these units on May 5,1970 because they failed to comply with the mechanical, installation, performance and other requirements of the contract. On June 3, 1970, plaintiff again submitted the Cool-Heat Corp. ‘Climate Master’ units for defendant’s approval and again on June 12,1970 they were disapproved because, as defendant advised the contractor in a June 26,1970 letter, of the number of unresolved deviations from plans and specifications. On June 30,1970, defendant learned that plaintiff again intended to resubmit the twice-disapproved Cool-Heat Corp. ‘Climate Master’ units and on that date advised plaintiff by telegram that this was unacceptable and directed plaintiff, under its contract Para. 21-03h reserved power, cited above, to furnish and install Remington or Nesbitt brand air conditioning units. Plaintiff furnished and installed the Remington units under protest and pursued this claim for the additional cost of those units over plaintiff’s proposed and thrice-rejected Cool-Heat units.

After the Contracting Officer’s denial of plaintiff’s claim, the Board, on timely appeal, found that plaintiff’s submitted units did not conform to the contract specifications; that defendant properly and neither arbitrarily nor capriciously exercised its contractual rights under contract para. 21-03h; and that defendant’s contract specifications did not restrict plaintiff to a sole source for the units. Plaintiff moved for reconsideration of this latter Board finding which, on reconsideration, the Board affirmed. 74-1 BCA ¶ 10,641.

Plaintiff’s four-page petition and five-page brief in support of its summary judgment motion in this case amounts to no more than a general declaration of protest and does not [204]*204rise to the pointed specification of Board error required of a party seeking to overturn a Board decision. In a Wunder-lich Act review case the “* * * plaintiff has the burden to specify the facts and circumstances contained in the Board’s record which make the Board’s decision lacking in substantial evidence. Valentine & Littleton v. United States, 136 Ct. Cl. 638, 643, 145 F. Supp. 952, 954 (1956); River Constr. Corp v. United States, 159 Ct. Cl. 254, 269 (1962). * * *" Jefferson Constr. Co. v. United States, 177 Ct. Cl. 581, 589, 368 F. 2d 247, 252 (1966). Plaintiff, in this case, has done little more than place the Board record before the court, and challenged the court to find error in the record rather than properly taking up the challenge itself of establishing factual or legal error in the Board’s decision. “* * * It is not the court’s function to supply this deficiency by an independent excursion along the administrative trail. * * Sundstrand Turbo v. United States, 182 Ct. Cl. 31, 60, 389 F. 2d 406, 423 (1968).

More deadening to plaintiff’s claim than its own failure to specifically demonstrate Board error is defendant’s mustering of evidence from the Board record augmented with authoritatively supported legal arguments in defendant’s brief in support of the Board decision. Defendant’s effort convincingly demonstrates the error-free validity of the Board’s decision to which plaintiff elected not to respond.

In its petition, plaintiff succinctly asserts its contentions of error in the Board’s decision:

5. Plaintiff contends that the Board erred in denying the Appeal when it failed to find: (i) that Plaintiff offered a product which in effect met the requirements of the Specifications; (ii) that Plaintiff was improperly subjected to pre-qualification testing; (iii) that the specifications as

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pi Electronics Corp. v. United States
54 Fed. Cl. 56 (Federal Claims, 2002)
Davies Precision Machining, Inc. v. United States
35 Fed. Cl. 651 (Federal Claims, 1996)
Dillingham Construction, N.A. v. United States
40 Cont. Cas. Fed. 76,827 (Federal Claims, 1995)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Mega Construction Co. v. United States
37 Cont. Cas. Fed. 76,305 (Court of Claims, 1992)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,080 (Court of Claims, 1991)
Blount Brothers Corporation v. The United States
878 F.2d 1446 (Federal Circuit, 1989)
Quality Environment Systems, Inc. v. United States
32 Cont. Cas. Fed. 73,267 (Court of Claims, 1985)
Roflan Co. v. United States
32 Cont. Cas. Fed. 73,207 (Court of Claims, 1985)
Mark A. Carroll & Son, Inc. v. United States
29 Cont. Cas. Fed. 82,684 (Court of Claims, 1982)
Churchill Chemical Corp. v. United States
602 F.2d 358 (Court of Claims, 1979)
Wickham Contracting Co. v. United States
546 F.2d 395 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
531 F.2d 538, 22 Cont. Cas. Fed. 80,144, 209 Ct. Cl. 200, 1976 U.S. Ct. Cl. LEXIS 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jet-construction-co-v-united-states-cc-1976.