Wickham Contracting Co. v. United States

546 F.2d 395, 23 Cont. Cas. Fed. 80,899, 212 Ct. Cl. 318, 1976 U.S. Ct. Cl. LEXIS 219
CourtUnited States Court of Claims
DecidedDecember 15, 1976
DocketNo. 327-75
StatusPublished
Cited by21 cases

This text of 546 F.2d 395 (Wickham Contracting Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wickham Contracting Co. v. United States, 546 F.2d 395, 23 Cont. Cas. Fed. 80,899, 212 Ct. Cl. 318, 1976 U.S. Ct. Cl. LEXIS 219 (cc 1976).

Opinion

Pee Curiam :

This case comes before the court on defendant’s motion, filed September 14, 1976, pursuant to Rule 54(b) (3) (iii), requesting that the court adopt, as the basis for its judgment in the case, the recommended decision of Trial Judge Thomas J. Lydon, filed July 22,1976, pursuant to Rule 166(c) on plaintiff’s motion and defendant’s cross-motion for summary judgment, since plaintiff has failed to [321]*321file a request for review by the court thereof and the time for so filing pursuant to the Rules of the court has expired. Upon consideration thereof, without oral argument, since the court agrees with the recommended decision, as hereinafter set forth, it hereby grants defendant’s motion and adopts the decision as the basis for its judgment in this case. Therefore, plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted and plaintiff’s petition is dismissed.

OPINION OP TRIAL JUDGE

Lydon, Trial Judge:

This government contract case involves a review, under standards of the Wunderlich Act (68 Stat. 81, 41 U.S.C. §§ 321-22 (1970)), of a decision by the Armed Services Board of Contract Appeals (Board), denying plaintiff’s claims for (1) additional costs by way of a contract price adjustment, and (2) a 2-month time extension. Both claims were premised on a scale error contained on a contract drawing. (Wickham Contracting Co., ASBCA No. 19069, 75-1 BCA ¶11,248.)1 On review, it is concluded that the Board decision denying plaintiff’s claims is correct in fact and in law.2

[322]*322On July 23, 1973, plaintiff was awarded a construction contract by tbe Corps of Engineers, U.S. Army Engineer District, New York, for Replacement of Primary Underground Cable at tbe Military Ocean Terminal, Bayonne, New Jersey. Tbe contract price was $44,000. In essence, tbe contract required tbe furnishing and installation of four manholes, underground electrical cable, a concrete duct bank within which to run the cable, and certain accessories for the overall system. The contract documents contained only a single drawing and it provided the setting for the dispute which resulted in the Board decision here under review.

The contract drawing contained two different scales. To the left of the title 'block, in the lower right-hand corner of the drawing, was a calibrated graphic or bar scale 3 inches long with marked footage designations. Immediately to the left of this graphic or bar scale were the figures; 1" — 200'.3 In the middle section of the drawing under the heading “Plan” appeared the following figures: Scale l'=200'. It is undisputed that the 1' —200' scale was a drafter’s error and should have read 1"=200'. The Board found that plaintiff based his bid on the Plan scale of l'=200'. The issue is whether plaintiff is entitled to recover additional costs of performance because of its reliance on the erroneous scale set out on the contract drawing which caused it to underbid.

Initially, it must foe observed that plaintiff’s petition and moving brief lack the substantive particularity, supported by appropriate record references, necessary to overcome the finality that otherwise attaches to findings made by a Board whose decision is subject to Wunderlich Act review. It is not the court’s function to remedy this deficiency by an independent and/or de novo review of the record. Jet Constr. Co. v. United States, 209 Ct. Cl. 200, 203-04, 531 F. 2d 538, 540-41 (1976). Hicks Corp. v. United States, 203 Ct. Cl. 65, 68, 487 F. 2d 520, 521 (1973). A review of the record, however, discloses the existence of substantial evidence supportive of the Board findings. Under these circumstances, the court is bound by such findings even though the record would support [323]*323contrary and/or modified findings in some respects. Allied Contractors, Inc. v. United States, 176 Ct. Cl. 1095, 1098-99 (1966).

The Board found that the possibility of an error relative to the scale 1' — 200' on the drawing was manifest. Parenthetically, plaintiff challenges this Board finding on the sole ground that it is irrelevant. Such a challenge, under the circumstances, is without merit. The Board noted that use of a V scale was unusual. Moreover, the presence on the drawing of another scale figure 1'=200// created a patent discrepancy.4 The Board concluded that plaintiff should have recognized the possibility of a drawing error when bidding.5 It is established that plaintiff was under an obligation to study all aspects of the contract drawing before submitting its bid, see Richardson Camera Co. v. United States, 199 Ct. Cl. 657, 665, 467 F. 2d 491, 496 (1972), and its failure to note the discrepancy in the scale data on the drawing rightly impinges on the reasonableness of its bid submission. See Martin Lane Co. v. United States, 193 Ct. Cl. 203, 217, 432 F. 2d 1013, 1020 (1970).

Under circumstances where a patent and glaring discrepancy exists in a contract drawing, and such a discrepancy [324]*324would be recognized by a reasonable bidder, there is a burden imposed on such a bidder to seek clarification of said discrepancy from an appropriate government official before submitting a bid, if the bidder, subsequent to an award to it, hopes to rely on its unilateral resolution of the discrepancy issue as a basis for a subsequent contract price adjustment claim. Merando, Inc. v. United States, 201 Ct. Cl. 23, 475 F. 2d 601 (1973); Space Corp. v. United States, 200 Ct. Cl. 1, 5-6, 470 F. 2d 536, 539 (1972); Beacon Constr. Co. v. United States, 161 Ct. Cl. 1, 7, 314 F. 2d 501, 504 (1963). This proposition is for application in situations where a bidder knew, as well as in situations where a bidder should have known, of the discrepancy. The latter situation is present in this case. Allied Contractors, Inc. v. United States, 180 Ct. Cl. 1057, 1064-65, 381 F. 2d 995, 1000 (1967). Indeed it has been said that whether a bidder knew or did not know of the discrepancy prior to submitting its bid is not a governing factor. “It is the existence and type of the discrepancy, not necessarily the contractor’s actual knowledge of it that imposes a burden of inquiry on the contractor * * HRH Constr. Corp. v. United States, 192 Ct. Cl. 912, 920-21, 428 F. 2d 1267, 1272 (1970).6

The Board recognized the applicability of the above legal proposition to the instant situation, although it did not cite any of the above cases, but was dissuaded from basing its decision thereon because of its finding that the government had knowledge of the drawing error prior to contract award.7 [325]*325See Helene Curtis Indus., Inc. v. United States, 160 Ct. Cl. 437, 443-44, 312 F. 2d 774, 777-78 (1963). The Board also alluded to the well established principle that the government impliedly warrants the suitability of its drawings for their intended use. See Thompson Ramo Wooldridge, Inc. v. United States, 175 Ct. Cl. 527, 538, 542, 361 F. 2d 222, 230, 232 (1966). At this stage, the Board in essence, viewed both parties as being at fault.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dynamic Systems Technology, Inc.
Armed Services Board of Contract Appeals, 2023
Clearwater Constructors, Inc. v. United States
71 Fed. Cl. 25 (Federal Claims, 2006)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Robins Maintenance, Inc. v. United States
265 F.3d 1254 (Federal Circuit, 2001)
Metric Constructors, Inc. v. United States
44 Fed. Cl. 513 (Federal Claims, 1999)
International Transducer Corp. v. United States
39 Cont. Cas. Fed. 76,630 (Federal Claims, 1994)
Crown Laundry & Dry Cleaners, Inc. v. United States
39 Cont. Cas. Fed. 76,575 (Federal Claims, 1993)
Gresham, Smith & Partners v. United States
37 Cont. Cas. Fed. 76,247 (Court of Claims, 1991)
Bayou Land & Marine Contractors, Inc. v. United States
37 Cont. Cas. Fed. 76,153 (Court of Claims, 1991)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,080 (Court of Claims, 1991)
Maintenance Engineers, Inc. v. United States
36 Cont. Cas. Fed. 75,950 (Court of Claims, 1990)
Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
Zinger Construction Co. v. United States
34 Cont. Cas. Fed. 75,411 (Court of Claims, 1987)
Brutoco Engineering & Construction, Inc. v. United States
34 Cont. Cas. Fed. 75,249 (Court of Claims, 1987)
Flexible Metal Hose Manufacturing Co. v. United States
31 Cont. Cas. Fed. 72,120 (Court of Claims, 1984)
Johnson Controls, Inc. v. United States
671 F.2d 1312 (Court of Claims, 1982)
Pleasant Excavating Co. v. United States
229 Ct. Cl. 654 (Court of Claims, 1981)
FFR Building Specialties Corp. v. United States
29 Cont. Cas. Fed. 81,999 (Court of Claims, 1981)
Bromley Contracting Co. v. United States
652 F.2d 70 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
546 F.2d 395, 23 Cont. Cas. Fed. 80,899, 212 Ct. Cl. 318, 1976 U.S. Ct. Cl. LEXIS 219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wickham-contracting-co-v-united-states-cc-1976.