R.E.D.M. Corporation v. The United States

428 F.2d 1304, 192 Ct. Cl. 891, 1970 U.S. Ct. Cl. LEXIS 159
CourtUnited States Court of Claims
DecidedJuly 15, 1970
Docket408-67
StatusPublished
Cited by22 cases

This text of 428 F.2d 1304 (R.E.D.M. Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R.E.D.M. Corporation v. The United States, 428 F.2d 1304, 192 Ct. Cl. 891, 1970 U.S. Ct. Cl. LEXIS 159 (cc 1970).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

PER CURIAM.

This case was referred to Trial Commissioner George Willi with directions to prepare and file his opinion on the issues of plaintiff’s motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 166(c). The commissioner has done so in an opinion and report filed on February 24, 1970, wherein such facts as are necessary to the opinion are set forth. Defendant filed a request for review by the court of the commissioner’s opinion, plaintiff urged its adoption and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the opinion and recommended conclusion of the trial commissioner, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this ease. Therefore, as to the claim under the first contract (No. DA 30-069-ORD-3063), plaintiff’s motion for summary judgment is granted and defendant’s cross-motion is denied with further proceedings stayed pursuant to Rule 167 for a period of 90 days to afford the parties an opportunity to obtain an administrative resolution of the amount of equitable adjustment to which plaintiff is entitled. Further, as to the claim under the second contract (No. DA 30-069-ORD-3416), plaintiff’s motion for summary judgment is denied, defendant’s cross-motion is granted and the petition is dismissed.

OPINION OF COMMISSIONER

WILLI, Commissioner: Plaintiff sues here to reverse the Armed Services Board of Contract Appeals’ denial of its claim for an equitable adjustment under each of two consecutive 1 Army contracts for the manufacture of artillery fuzes used to ignite the explosive charge in anti-tank projectiles. The two contracts contained identical drawings and specifications and were otherwise the same in all respects relevant here.

Though plaintiff’s theory of recovery is based on the contention that defective specifications and drawings caused it extra expense in performing the contracts, *1306 it proceeds here, as it did before the Board, on the premise that its grievance is fully redressable under the standard Changes clause of the contracts. See L.W. Foster Sportswear Co. v. United States, 405 F.2d 1285, 1290, 186 Ct.Cl. 499, 507-508 (1969), and cases cited. There being no dispute as to the availability of complete relief under the contract, 2 the review here is limited to the issue of liability 3 and accords all relevant Board factual determinations the finality imparted by the standard Disputes clause of the contracts, since it is found, and not really contested by the parties, that such determinations pass muster under the standards of the Wunderlich Act, 68 Stat. 81, 41 U.S.C. § 321 (1964). Thus, to the extent that the Board is reversed here, it is not because of a rejection of its view of the facts but a difference of opinion as to the legal consequences that flow from them.

Plaintiff’s first contract (No. DA 30-069-ORD-3063), entered into May 24, 1960, called for production of 320,000 M509E6 fuzes at a fixed price. The fuze consisted principally of a rotor, detonator, and release mechanism. In order for the fuze to arm, the rotor had to so rotate that the detonator contained within the rotor cavity was positioned to ignite two booster charges which, in turn, set off the main explosive charge of the projectile. Movement of the rotor was controlled by an attached rotor pin which was restrained by a release mechanism consisting of three aluminum leaves, stacked one atop another, positioned between two bearing plates. The release mechanism was constructed so that the bottom leaf (Leaf No. 3) could not rotate until the middle leaf (Leaf No. 2) had rotated, and the middle leaf could not rotate until the top leaf (Leaf No. 1) had rotated. Leaf No. 1 was held in position by a leaf spring. When sufficient centrifugal force was exerted to overcome the restraining force of the leaf spring, Leaf No. 1 would rotate, thereby releasing Leaves No. 2 and No. 3 to rotate also. This movement of the leaves removed the restraint on the rotor pin, allowing the rotor to turn approximately 90 degrees into the armed position.

To function acceptably, the fuze had to arm before the projectile reached the target, but not until after the round had been fired. Thus, the contract specified that the fuze must not. arm when a centrifugal force up to 2,500 G’s was applied. Each fuze produced had to be tested to ensure compliance with this “non-arming” requirement. Further, the contract required that the fuze arm when subjected to a centrifugal acceleration of 4,000 G’s. Testing of this “arming” requirement was to be conducted on a sample basis only, with an acceptable quality level (“AQL”) of 0.10 percent required.

Plaintiff experienced no difficulties with the non-arming test, but almost immediately encountered problems in meeting the arming requirement. As early as the initial stage of production in August 1960, it was unable to obtain consistent results on in-plant centrifuging tests established to check the arming capability of the fuzes manufactured. Fuzes would sometimes arm within a given G range and sometimes not. When the first pilot lot failed ballistic firing tests in September 1960, plaintiff began conducting the in-plant testing at levels more stringent (initially 3700 G’s and eventually 3500 G’s) than the contract required, in an effort to ensure that the fuzes would meet the arming requirement for the AQL specified. Twice in conducting the arming tests, plaintiff screened the units on a 100-percent basis. Nevertheless, the number of failures remained excessive. The rejection rate ranged from 10 to 30 percent, with an average of 18 to 20 percent of the assemblies tested failing to meet the arming requirement. Moreover, production costs began to mount.

*1307 During the remainder of 1960 and the first 10 months of 1961, plaintiff took numerous steps in an effort to isolate the cause of the arming problem. A production check was made to ensure that the fuze was being assembled properly. The leaf spring was adjusted to a tighter arming range and, at one point, removed entirely. An alternate method of assembly, utilizing loose rather than rigid leaf pins, was tried. Tests were conducted to ascertain whether the anti-reset spring was causing Leaf No. 3 to bind. The shape of Leaf No. 3 was modified to determine if the leaf was preventing the rotor pin from revolving. None of these measures suggested a solution and the rejection rate remained high. In February 1961, plaintiff requested that the arming test requirement be raised from a maximum 4,000 G’s to 4,300 G’s. Although the request was approved in March, the arming difficulties continued.

Sometime during the spring of 1961, plaintiff conducted a centrifuge test of the release mechanism without the rotor and rotor spring, and for the first time fewer rejects were encountered. A similar reduction was noted when the screws holding down the front bearing plate of the release mechanism were loosened.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rick's Mishroom Service, Inc. v. United States
521 F.3d 1338 (Federal Circuit, 2008)
AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)
Robins Maintenance, Inc. v. United States
265 F.3d 1254 (Federal Circuit, 2001)
United Technologies Corp. v. United States
39 Cont. Cas. Fed. 76,696 (Federal Claims, 1994)
Big Chief Drilling Co. v. United States
38 Cont. Cas. Fed. 76,418 (Court of Claims, 1992)
Hawaiian Bitumuls & Paving v. United States
38 Cont. Cas. Fed. 76,402 (Court of Claims, 1992)
Aleutian Constructors v. United States
37 Cont. Cas. Fed. 76,203 (Court of Claims, 1991)
R.J. Crowley, Inc. v. The United States
923 F.2d 871 (Federal Circuit, 1990)
Transtechnology Corp. v. United States
36 Cont. Cas. Fed. 75,953 (Court of Claims, 1990)
Neal & Co. v. United States
36 Cont. Cas. Fed. 75,802 (Court of Claims, 1990)
Kordick & Son, Inc. v. United States
34 Cont. Cas. Fed. 75,328 (Court of Claims, 1987)
Utility Contractors, Inc. v. United States
32 Cont. Cas. Fed. 73,446 (Court of Claims, 1985)
Toombs & Co. v. United States
31 Cont. Cas. Fed. 72,149 (Court of Claims, 1984)
Johnson Controls, Inc. v. United States
671 F.2d 1312 (Court of Claims, 1982)
Ordnance Research, Inc. v. United States
609 F.2d 462 (Court of Claims, 1979)
Manufacturers Hanover Trust Co. v. United States
590 F.2d 893 (Court of Claims, 1978)
Switlik Parachute Co. v. United States
573 F.2d 1228 (Court of Claims, 1978)
Firestone Tire & Rubber Co. v. United States
558 F.2d 577 (Court of Claims, 1977)
Wickham Contracting Co. v. United States
546 F.2d 395 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
428 F.2d 1304, 192 Ct. Cl. 891, 1970 U.S. Ct. Cl. LEXIS 159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/redm-corporation-v-the-united-states-cc-1970.