Aleutian Constructors v. United States

37 Cont. Cas. Fed. 76,203, 24 Cl. Ct. 372, 1991 U.S. Claims LEXIS 486, 1991 WL 211506
CourtUnited States Court of Claims
DecidedOctober 18, 1991
DocketNo. 22-89C
StatusPublished
Cited by20 cases

This text of 37 Cont. Cas. Fed. 76,203 (Aleutian Constructors v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aleutian Constructors v. United States, 37 Cont. Cas. Fed. 76,203, 24 Cl. Ct. 372, 1991 U.S. Claims LEXIS 486, 1991 WL 211506 (cc 1991).

Opinion

ORDER

TIDWELL, Judge:

This case is before the court on the parties’ cross-motions for summary judgment on plaintiff’s claim for an equitable adjustment under a government construction contract. For the reasons set forth below, the court grants defendant’s motion and denies Aleutian’s cross-motion.

FACTS

This dispute arose out of a contract between plaintiff, Aleutian Constructors, and defendant, acting through the Army Corps of Engineers (Corps), to construct an airplane hangar and dormitory building for the Air Force’s Optical Aircraft Measurement Program (OAMP) at Shemya Air Force Base, Alaska. Shemya AFB occupies all of Shemya Island and is situated approximately 1,500 miles west of the Alaskan mainland, near the far western end of the Aleutian Chain. The island is known for its extreme weather conditions, including high winds and humidity. The Corps awarded the contract on February 18,1983, with a projected completion date of May 15, 1985.

Construction of the $12.8 million project proceeded normally. However, on November 12, 1984, at some time between 9:00 a.m. and 10:45 a.m., high winds partially destroyed a portion the roof of the OAMP hangar before completion of the project, and acceptance by the Corps. Aleutian rebuilt the roof at its own expense. The portion of the roof that was destroyed was the ethyl propylene diene monomer (EPDM) membrane, a watertight, rubber-like plastic sheet stretched over and attached to the barrel-shaped roof deck by round, metal fasteners. The membrane tore loose from the fasteners, and exposed a forty-by-fifty-foot section of the roof system substructure. Queen City Sheet Metal and Roofing of Seattle (Queen City) was the roofing subcontractor that constructed the roof; DiversiTech General, Inc., a subsidiary of General Tire and Rubber Corporation (General Tire), manufactured the membrane. Wescon Materials (Wescon), General Tire’s EPDM membrane system representative in the Pacific Northwest provided the necessary detailed information to install the membrane.

When the contract required shop drawings, Aleutian was to “coordinate all such drawings, and review them for accuracy, completeness, and compliance with contract [375]*375requirements____” Approval by the contracting officer did not relieve the Contractor from responsibility for errors or omissions in shop drawings, nor from responsibility for meeting the requirements of the contract. The contracting officer’s approval meant only that “the general method of construction and detailing [was] satisfactory,” and that the Corps would “rely upon the Contractor’s certification on the shop drawing that a complete check has been made and conformance with the contract has been met.”

Among the written specifications for the roof was one entitled “ELASTOMERIC ROOFING (EPDM).” This specification provided that “[m]embrane, flashing, and adhesives shall be the standard products of a single manufacturer.” Likewise, “fasteners shall be of the types and sizes best suited for the purpose and shall comply with roofing manufacturer’s approved instructions.” Wood to which the membrane was to be attached was to be preservative-treated. Under “INSTALLATION,” the contract specified that “[fasteners fastening membrane to treated grid nailer shall be covered with 6-inch wide strips of elastomeric [membrane] flashing.” Aleutian was to submit the installation details for attachment of the membrane in a shop drawing to the Corps for approval. Among other matters, Aleutian was to establish and maintain a quality control program to insure that: (1) the membrane was applied as designed, (2) tests were performed on materials, and (3) test reports were produced to verify that the materials conformed to the specifications. The test reports were to contain a certification that the materials met the specifications.

Architectural Contract Drawing A-5 showed the dimensions of the roof, the locations of vents, and bore a note that Aleutian was to install mechanical fasteners “PER MNFR. RECOMMENDATION.” Also, on drawing A-5 was a handwritten statement, “NOTE ON HANGAR ROOFING: CONTRACTOR TO PROVIDE CAU CULATIONS TO VERIFY THAT ROOFING FASTENING SYSTEM CAN WITHSTAND AN UPLIFT FORCE OF 80 p.s.f.” (Emphasis in original.)1

The contract further specified that the layers of membrane were to be cemented together, and to the insulation, at every point with contact cement, and held in place by one-inch, membrane-covered, continuous metal battens anchored to the roof frame. The contract also contained a sheet listing climatic variations, which included yearly rainfall and snowfall, and noted that the highest wind speed ever recorded at Shemya was 139 m.p.h.

Manufacturers of roof systems advised Aleutian that the combination of high winds and humidity dictated against the use of an adhered membrane because of the length of time required to apply contact cement, and for the cement to set. Moreover, the use of contact cement would not allow the air bubbles in the membrane to be rolled out. General Tire stated, without qualification, that installation of an adhered membrane would be impossible, and would “insure disastrous results.” On February 1, 1984, Queen City recommended that Aleutian use General Tire’s alternative membrane system which employed “metal fastening disks” to secure a single layer of membrane to the roof substructure with adhesive only at the perimeter.2

Aleutian submitted Queen City’s February 1, 1984 letter to the Corps on February 16, 1984 as part of a shop drawing request for a no-cost change from the fully-adhered membrane system, fastened with continuous metal battens, to a non-adhered mem[376]*376brane system, fastened with eight-inch round disks. Also enclosed with the February 16,1984 shop drawing were installation instructions, samples, catalog data, shop drawings, and calculations addressing the strength of the membrane and fasteners. The calculations verifying compliance with the 80 p.s.f. requirement, and detailed installation instructions, were contained in a letter from Wescon to Queen City dated February 4, 1984. The Corps rejected the proposed change, in part, because of its expressed concern that the non-adhered membrane would billow upwards and tear in high winds. To satisfy some of the Corps’ concerns with the alternative membrane system, General Tire’s representative explained at a meeting that the disk edges would be turned upwards to negate any “cutting edge” so that the membrane would not tear in high winds. The representative also stated that the General Tire disk-anchored system had been used successfully in Dade County, Florida, an area prone to hurricanes and having one of the strictest building codes in the country.

On April 6, 1984, Aleutian resubmitted the proposed General Tire alternative membrane system to the Corps, incorporating by reference the enclosures in the February 4, 1984 shop drawing. Both shop drawings contained a statement signed by a representative of Aleutian which said, “I certify that the above submitted items have been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.” No exception was stated. In the latter submittal Aleutian also noted that “WIND TUNNEL TEST REPORTS WILL BE FORWARDED THE WEEK OF 4/9/84”—the following week.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flink/Vulcan v. United States
63 Fed. Cl. 292 (Federal Claims, 2004)
First Commerce Corp. v. United States
60 Fed. Cl. 570 (Federal Claims, 2004)
Ferguson Propeller, Inc. v. United States
59 Fed. Cl. 51 (Federal Claims, 2003)
Kiewit Construction Co. v. United States
56 Fed. Cl. 414 (Federal Claims, 2003)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Boozell v. United States
979 F. Supp. 670 (N.D. Illinois, 1997)
Aircraft Gear Corp. v. Kaman Aerospace Corp.
856 F. Supp. 446 (N.D. Illinois, 1994)
Martin v. United States
30 Fed. Cl. 542 (Federal Claims, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
National Medical Enterprises, Inc. v. United States
28 Fed. Cl. 540 (Federal Claims, 1993)
Westerhold v. United States
38 Cont. Cas. Fed. 76,509 (Federal Claims, 1993)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
Hawaiian Bitumuls & Paving v. United States
38 Cont. Cas. Fed. 76,402 (Court of Claims, 1992)
Sterling Millwrights, Inc. v. United States
38 Cont. Cas. Fed. 76,316 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,203, 24 Cl. Ct. 372, 1991 U.S. Claims LEXIS 486, 1991 WL 211506, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aleutian-constructors-v-united-states-cc-1991.