Martin K. Eby Construction Co. v. Jacksonville Transportation Authority

436 F. Supp. 2d 1276, 2005 U.S. Dist. LEXIS 42793
CourtDistrict Court, M.D. Florida
DecidedMarch 21, 2005
Docket2:03-cv-00041
StatusPublished
Cited by1 cases

This text of 436 F. Supp. 2d 1276 (Martin K. Eby Construction Co. v. Jacksonville Transportation Authority) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin K. Eby Construction Co. v. Jacksonville Transportation Authority, 436 F. Supp. 2d 1276, 2005 U.S. Dist. LEXIS 42793 (M.D. Fla. 2005).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

CORRIGAN, District Judge.

This case involves a dispute between Martin K. Eby Construction Co., Inc. (“Eby”), and the Jacksonville Transportation Authority (“JTA”) arising from Eby’s construction of highways and bridges forming part of the new Wonderwood Connector in Jacksonville, Florida. Although Eby’s end product won awards for smooth concrete, the construction project was anything but smooth, resulting in two separate multimillion dollar lawsuits by Eby against JTA. 1

In this case, Eby seeks over $10 million in damages relating to the difficulty it had in accessing areas of the construction site located in and over water and marshes. Eby asserts that JTA misled bidders into believing that the areas could be accessed using relatively inexpensive and uncomplicated temporary dirt haul roads and working platforms. Eby asserts that JTA is liable under breach of contract, differing site conditions, constructability, and superior knowledge claims.

The Court conducted a nine-day bench trial 2 in December 2004 and heard closing *1278 ■arguments in January 2005. Having reviewed the pleadings, examined the evidence, observed the witnesses, read the parties’ proposed findings and conclusions, and considered the arguments, the Court makes the following findings of fact and conclusions of law as required by Federal Rule of Civil Procedure 52(a).

I. Findings of Fact 3

A. The Parties

JTA is an independent state agency that provides transportation services for Duval County, Florida. The services include highway and bridge design and construction. 4

Eby is a Kansas-based private contractor that has been involved in many large and well-known public construction projects in its 68-year history. Although Eby has had experience with bridge construction, it is not known in the industry as a “marine contractor,” i.e., a contractor specializing in projects that involve construction over water. During the relevant time period, Eby had a significant Florida presence. 5

B. The Project

In the 1990s, federal funds and bond proceeds were earmarked for Jacksonville’s Wonderwood Connector, a four-phased project involving the design and construction of new highways and bridges. The four phases, in chronological order from the earliest to the latest start dates, were Wonderwood Connector Segment 2A (“Wonderwood 2A”), Wonderwood Connector Segment 2 (‘Wonderwood 2”), Wonder-wood Connector Segment 1 (“Wonderwood 1”), and Wonderwood Connector Segment 3 (Wonderwood 3”).

This case involves Eby’s construction of Wonderwood 2. Wonderwood 2 consists of approximately 2.1 miles of recently constructed four-lane highways and bridges connecting Sandcastle Lane and Girvin Road. One bridge is approximately 1,400 feet long and spans Greenfield Creek. Another bridge is approximately 3,585 feet long and spans the Intracoastal Waterway and Pablo Creek.

JTA retained Sverdrup Civil, Inc. (“Jacobs-Sverdrup”), 6 to design Wonderwood 2. Theodore Finch, originally employed by Jacobs-Sverdrup, was designated as the “Engineer of Record.” 7 JTA also relied on its general consultant, Reynolds, Smith & Hills, Inc. (“RS & H”), to provide advice on various engineering aspects of Wonder-wood 2, and Reynolds, Smith & Hills CS (“RS & H CS”) to provide advice on various construction aspects of Wonderwood 2. George Mayforth of RS & H CS, later *1279 replaced by Shane Rixom of RS & H CS, was designated as the “Engineer” 8 responsible for ensuring that Wonderwood 2 was constructed as designed.

C. The Planning

JTA and Jacobs-Sverdrup spent many years planning Wonderwood 2. The planning included the development of progressive bridge development reports (“BDRs”). Both RS & H, as a general consultant, and the Florida Department of Transportation (“FDOT”), as a courtesy, reviewed the BDRs and provided JTA and Jacobs-Sverdrup with feedback based on their significant experience with large highway and bridge projects.

In addition to addressing design details for the permanent highways and bridges, the BDRs addressed how the contractor would access the portions of the highways and bridges to be built over water and marshes. An aerial photograph of the Wonderwood 2 area before construction showed the Intracoastal Waterway and Pablo Creek as wide bodies of water deep enough for boating (at least at high tide), separated by a small island, and surrounded by small tributaries and marshes. The only ground that appeared relatively “high and dry” was an old railroad embankment upon or over which the permanent structures were to be built.

Generally, contractors use either barges or “temporary access structures” to access construction sites that are inaccessible by other means. As evident from the name, temporary access structures are temporary and used solely by the contractor for construction access. They are removed after project completion and the land upon which they were placed is returned to its original or near-original condition. Because of their temporary nature and limited use, they usually are not the central focus of a construction project.

Temporary access structures can take many forms, including dirt embankments, trestles, Bailey bridges, 9 and any combination of these structures. The type of temporary access structure selected for a particular project depends on, among other factors, the availability of environmental permitting, the type and weight of the construction equipment, the manner in which the construction equipment will be used, the type and weight of the building materials for the permanent structure, when access will be needed for construction of the permanent structure, the foundation upon which the temporary access structure will be placed, and the expediency with which the project must be completed. Because many of these factors implicate the means and methods used by the contractor, the contractor usually is responsible for selecting and designing the temporary access structure. This is in contrast to the permanent structure which, unless contracted as a design-build project, usually is fully designed with exact plans and specifications for the contractor to follow, is not dependent on the contractor’s means and methods, and is not constructed for the sole direct benefit of the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Electric Corp. v. Utilities Board of Foley
643 F. Supp. 2d 1302 (S.D. Alabama, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
436 F. Supp. 2d 1276, 2005 U.S. Dist. LEXIS 42793, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-k-eby-construction-co-v-jacksonville-transportation-authority-flmd-2005.