E.L. Hamm & Associates, Inc. v. Gordon R. England, Secretary of Navy

379 F.3d 1334, 2004 U.S. App. LEXIS 17021, 2004 WL 1832803
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 17, 2004
Docket03-1527
StatusPublished
Cited by89 cases

This text of 379 F.3d 1334 (E.L. Hamm & Associates, Inc. v. Gordon R. England, Secretary of Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E.L. Hamm & Associates, Inc. v. Gordon R. England, Secretary of Navy, 379 F.3d 1334, 2004 U.S. App. LEXIS 17021, 2004 WL 1832803 (Fed. Cir. 2004).

Opinion

PROST, Circuit Judge.

E.L. Hamm & Associates, Inc. (Hamm) appeals the decision of the Armed Services Board of Contract Appeals (Board) upholding the contracting officer’s (CO’s) decision denying Hamm’s claim for an equitable adjustment. In re E.L. Hamm & Assocs., Inc., ASBCA No. 51838, 2003 WL 1795675 (Apr. 1, 2003). At the Board, Hamm claimed, among other things, it was entitled to $135,930.18 for additional policing work because of a defect in the specification whereby the government understated the policing acreage. Although the Board found that the contract between the Navy and Hamm was defective as to the policing acreage, it denied Hamm’s claim for an equitable adjustment based on its finding that Hamm was not misled by the defect. We conclude that this finding was not supported by substantial evidence because Hamm relied on the understated policing acreage and the defect was not patent. We therefore reverse and remand for a quantum hearing.

BACKGROUND

On October 14, 1993, the Department of the Navy (Navy) awarded Hamm a combination fixed-price and indefinite-quantity contract. The fixed-price portion of the contract included management and maintenance of family housing units and other real property at seven housing areas in or near Norfolk, Virginia. The contract provided for a base year and four option years. The base year as awarded covered a ten-month period, but a General Accounting Office award protest caused the Navy to suspend contract performance from November 4, 1993, to April 1, 1994. Upon resolution of the protest, the Navy adjusted the base-year term to cover a six-month period beginning on April 1, 1994. Thereafter, the Navy exercised two options, the first for twelve months and the second for nine months. Consequently, the contract lasted a total of twenty-seven months.

Particularly relevant to this appeal, the contract required seasonal grass mowing and daily policing of the housing area grounds. To that end, the contract contained three specific line items, as follows:

*1337 [[Image here]]

Section C.ll required general and prestige mowing thirty-two weeks per year, from April through October. It also required daily policing of grounds for which lawn maintenance was required, in addition to all streets, sidewalks, playground areas, parking lots, gutters, and alleys. On April 14, 1994, Hamm subcontracted with Trident Services for general and prestige mowing. Over the course of the contract, both Hamm and Trident Services employees performed the required policing work.

The Board found that Hamm discovered a discrepancy between the mowing and policing acreages in early 1995 after receiving a draft contract modification from the Navy. After analyzing the contract information in more detail, Hamm claims to have found that the acreages for both policing and mowing were essentially the same. Noting that the policing acreage included both the mowing acreage plus the acreage for streets, sidewalks, playground areas, parking lots, gutters, and alleys, Hamm concluded that the acreage for policing must have been understated.

On April 10, 1995, Hamm requested a price modification from the CO because of the understated policing acreage. The CO denied the request. Hamm then submitted a certified claim for $112,031.39 on July 30, 1996, for 48.04 additional acres of policing. Thereafter, Hamm hired a professional engineer to review the Public Works Center (PWC) drawings attached to the contract — drawings 12,628 through 12,628R — -to determine the actual mowing and policing acreages. Hamm’s expert calculated a total mowing area of 164.82 acres and a total policing area of 244.7 acres. Comparing those results to the acreages listed in the contract, Hamm’s expert found that both the mowing and policing acreages were understated. Hamm therefore submitted a revised claim to the Navy for $135,930.18 for additional policing and $23,088.49 for additional mowing on June 12,1997, concurrently requesting a Final Contracting Officer’s Decision (FCOD). Hamm later incorporated this claim into its Consolidated Request for Equitable Adjustment, submitted April 14, 1998, to address several contract issues. Subsequently, Hamm certified this request and submitted it for a FCOD on August 31, 1998. The CO issued a Final Decision on October 29,1998, denying Hamm’s Consolidated Request, including the claim for additional policing and mowing.

Hamm timely appealed to the Board on January 15, 1999. The consolidated appeals were docketed as ASBCA No. 51970, with ASBCA No. 51085, 2003 WL 21054377 as the central appeal file. An administrative judge conducted hearings on the consolidated appeals on January 15-16, 2002. On April 1, 2003, the Board issued a separate opinion addressing the mowing and policing appeals, identifying the opinion by the original docket number, ASBCA No. 51388. In its opinion, the Board upheld Hamm’s claim for an equita *1338 ble adjustment for additional mowing because the mowing acreages provided in the solicitation were understated by 9.656 acres weeldy and Hamm was misled by this defect. E.L. Hamm, ASBCA No. 51388, slip op. at 12. The Board also found that the policing acreage in the contract specification was erroneous. Id. But the Board denied Hamm’s claim for the value of additional policing work, finding that Hamm failed to show that it was misled by the understated policing acreage. In particular, the Board found that Hamm used the single mowing acreage of 166.77 1 acres to propose conducting policing 236 days per year. Id. Thus, because Hamm’s policing proposal included only the mowing acres, 2 id. at 9, the Board found that Hamm failed to include any additional acreage for the streets, sidewalks, playground areas, parking lots, gutters, and alleys, id. at 13. Having relied on the single mowing acreage to calculate its policing bid, the Board found that Hamm was not actually misled by the defective policing acreage. Id.

Hamm timely filed an appeal on July 30, 2003. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).

DISCUSSION

I. STANDARD OF REVIEW

We review a Board decision by applying the standards of review set out in the Contract Disputes Act of 1978(CDA), 41 U.S.C. §§ 601-613. Under the CDA, the Board’s conclusions of law are reviewed without deference. 41 U.S.C. § 609(b) (2000). The Board’s findings of fact, however, shall not be set aside unless fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence. Id. Substantial evidence means such relevant evidence as a reasonable mind might accept as adequate to support a conclusion. Wickham Contracting Co., Inc. v. Fischer,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2025
Govwave, LLC v. United States
Federal Claims, 2025
Sauer Construction, LLC
Armed Services Board of Contract Appeals, 2025
Mvl USA, Inc. v. United States
Federal Claims, 2025
H&L Contracting LLC
Armed Services Board of Contract Appeals, 2024
Philips Lighting North American Corporation
Armed Services Board of Contract Appeals, 2024
Hahnenkamm, LLC v. United States
104 F.4th 1333 (Federal Circuit, 2024)
Korte Construction Company
Armed Services Board of Contract Appeals, 2024
DLT Solutions, LLC
Armed Services Board of Contract Appeals, 2024
Marine Hydraulics International, LLC
Armed Services Board of Contract Appeals, 2024
ECC International Constructors/Metag(JV)
Armed Services Board of Contract Appeals, 2023
David Boland, Inc.
Armed Services Board of Contract Appeals, 2022
Sekri, Inc. v. United States
Federal Claims, 2021
The Boeing Company v. United States
968 F.3d 1371 (Federal Circuit, 2020)
CKY, Inc.
Armed Services Board of Contract Appeals, 2020

Cite This Page — Counsel Stack

Bluebook (online)
379 F.3d 1334, 2004 U.S. App. LEXIS 17021, 2004 WL 1832803, Counsel Stack Legal Research, https://law.counselstack.com/opinion/el-hamm-associates-inc-v-gordon-r-england-secretary-of-navy-cafc-2004.