Philips Lighting North American Corporation

CourtArmed Services Board of Contract Appeals
DecidedNovember 15, 2024
Docket61769, 61873, 62391
StatusPublished

This text of Philips Lighting North American Corporation (Philips Lighting North American Corporation) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philips Lighting North American Corporation, (asbca 2024).

Opinion

DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) Philips Lighting North American ) ASBCA Nos. 61769, 61873, 62391 Corporation ) ) Under Contract No. CQ-12077 )

APPEARANCES FOR THE APPELLANT: Franklin C. Turner, Esq. Ethan Brown, Esq. Cara A. Wulf, Esq. Alexander W. Major, Esq. Matthew Wright, Esq. McCarter & English, LLP Washington, DC

APPEARANCES FOR THE AUTHORITY: Jeffrey Weinstein, Esq. Chief Counsel Washington Metropolitan Area Transit Authority Washington, DC

Tracye Winfrey Howard Esq. George E. Petel, Esq. Wiley Rein LLP Washington, DC

OPINION BY ADMINISTRATIVE JUDGE WOODROW

This appeal involves a contract to upgrade and replace the lighting systems at 25 parking garages owned by the Washington Metro Area Transit Authority (WMATA). Conformed Contract No. CQ-12077, Parking Garage Lighting Efficiency (the contract), required Philips Lighting North American Corporation (Philips) to upgrade and replace the lighting fixtures with energy-efficient LED technologies and install state-of-the art electricity metering equipment in all of WMATA’s parking garages.

The contract established two phases of performance: the construction phase, during which Philips agreed to design and install the upgraded lighting and metering systems at each garage; followed by the maintenance phase, during which Philips would maintain the system for a period of 10 years. The contract required WMATA to pay Philips in 20 semi-annual installments over the ten-year maintenance phase based DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. on the energy savings achieved from the project. The contract did not require payment during the construction phase.

Philips contends that WMATA breached the contract by failing to pay Philips’ invoices for installment payments and also breached the duty of good faith and fair dealing by causing delays during the construction phase of the contract. On July 30, 2020, we granted partial summary judgment to Philips as to the payment obligations but denied summary judgment as to Philips’ allegations of the breach of the duty of good faith and fair dealing. Philips Lighting North American Corp., ASBCA No. 61769 et al., 20-1 BCA ¶ 37,679 at 182,929.

On September 3, 2020, WMATA filed a motion for reconsideration requesting that the Board reconsider two aspects of its opinion: (1) the Board’s grant of partial summary judgment under Count II of Philips’ complaint with respect to the payment provision in the Lighting Contract, and (2) the Board’s grant of Philips’ motion to strike WMATA’s affirmative defense of setoff associated with Philips’ alleged performance delay. In addition to opposing WMATA’s motion, Philips filed a motion requesting that we order WMATA to make immediate payment under the Lighting Contract and that we impose sanctions against WMATA for the alleged bad faith in its motion. On March 11, 2021, we denied both parties’ motions. Philips Lighting North American Corp., ASBCA No. 61769 et al., 21-1 BCA ¶ 37,821 at 183,652-53.

Starting on March 22, 2021, we held a seven-day hearing to determine quantum and to resolve Philips’ allegations of bad faith and the breach of the duty of good faith and fair dealing. Due to the ongoing COVID-19 pandemic, we conducted the hearing virtually.

Philips contends that WMATA’s breaches entitle Philips to be excused from further performance and to be compensated at the full value of the contract (app. br. at 45). Philips advances several alternative theories of breach, including bad faith, breaches of the duty of good faith and fair dealing, and material breach based upon nonpayment (app. br. at 10-20). Philips also contends that the Board could view WMATA’s conduct as a de facto default termination and judicially impose a termination for convenience remedy (app. br. at 22-24).

In response, WMATA argues that the testimony does not support a finding of either bad faith or a breach of the duty of good faith and fair dealing (resp’t br. at 24-30). WMATA further argues that it was justified in refusing to pay Philips’ invoices, because the invoices demonstrated that Philips never met the energy savings guarantee using the baseline measurement specified by the contract (resp’t br. at 25-29). With respect to Philips’ theory that WMATA’s conduct amounts to a de facto default termination, WMATA contends that the contract is ongoing and has not

2 DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. been terminated and that the Board does not possess jurisdiction to order the WMATA contracting officer to issue a termination (resp’t reply br. at 27-28).

As we explain below, we hold that WMATA’s non-payment constitutes a material breach of the lighting contract. Because Philips continues to maintain the lighting system pursuant to the contract and has not elected to cease performance, we award damages based on Philips past performance through February 29, 2024, the last date for which we have complete information. If Philips continues performance going forward, WMATA must pay any future invoices pursuant to the terms of the contract and consistent with this decision.

We further hold that WMATA did not act in bad faith or breach the implied duty of good faith and fair dealing when it refused to pay Philips’ invoices. We also hold that Philips is entitled to additional damages for infrastructure repairs, but that Philips has not met its burden of demonstrating that it is entitled to additional damages for the cost of installing additional meters. Finally, we hold that Philips is not entitled to payment for energy savings accrued during the enlarged installation period.

FINDINGS OF FACT

I. The Solicitation and Philips’ Proposal

1. On October 31, 2011, WMATA issued a request for proposal (RFP) to obtain a lighting system at its parking garages to produce “total cost and energy savings.” (App. supp R4, tab 3 at 3 1 answer at ¶ 6)

2. The purpose of the lighting project was to, among other things, improve lighting for customer comfort and safety and reduce WMATA’s energy consumption and operating costs (R4, tab 1 at 113).

3. The RFP – which later was incorporated into the Contract – provided that the costs for the project would be financed through operating cost savings (R4, tab 1 at 18; answer at ¶¶ 7, 18).

4. Philips had an opportunity to tour and photograph the garages before bidding (tr. 2/119; 5/200).

1 The bates-labeling contained in the both the government’s Rule 4 file and appellant’s supplemental Rule 4 file has leading zeros and the prefixes. We have removed the prefixes and leading zeros from our citations for clarity.

3 DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below is subject to an ASBCA Protective Order. This version has been approved for public release. 5. Paragraph 13 of the RFP stated that it was Philips’ responsibility to understand the conditions of the garages and the extent of work required (ex. G-84 at 87; R4, tab 1 at 87; tr. 2/202).

6. On August 15, 2013, Philips submitted its proposal to WMATA (ex. G-5 - 12). In its proposal, Philips agreed to “finance 100 percent of all Project costs” and required no upfront capital outlay from WMATA. (Ex. G-6 at 13313).

7. Philips’ proposal also included “Philips Energy Guarantee,” which Philips provided WMATA with its energy consumption calculations as part of its proposal, the final version of which was dated August 30, 2013 (app. supp. R4, tab 492 at 8715-18).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Turner Construction Co., Inc. v. United States
367 F.3d 1319 (Federal Circuit, 2004)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Shell Oil Company v. United States
896 F.3d 1299 (Federal Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Philips Lighting North American Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philips-lighting-north-american-corporation-asbca-2024.