Triax Pacific, Inc. v. Togo D. West, Jr., Secretary of the Army

130 F.3d 1469
CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 30, 1998
Docket97-1067
StatusPublished
Cited by115 cases

This text of 130 F.3d 1469 (Triax Pacific, Inc. v. Togo D. West, Jr., Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triax Pacific, Inc. v. Togo D. West, Jr., Secretary of the Army, 130 F.3d 1469 (Fed. Cir. 1998).

Opinion

BRYSON, Circuit Judge.

Triax Pacific, Inc., appeals a decision of the Armed Services Board of Contract Appeals denying its request for an equitable adjustment of a contract to renovate military housing. Because the contract contained ambiguities on its face sufficient to place a reasonable contractor on notice, we apply the “patent ambiguity” doctrine and uphold the decision of the Board of Contract Appeals.

I

In 1990, the Army issued a bid solicitation to renovate 21 military housing units at Fort Shatter, Hawaii. The solicitation called for the construction of new lanais (covered, screened patios) attached to the back of each unit, along with minor interior renovations, such as the installation of new dishwashers and new door locks. As described in the bid packet, each lanai was to be constructed on a new concrete slab poured at the back of each housing unit. The lanais were intended to be fully enclosed areas, with low concrete masonry walls and screens extending up to a wood-frame roof. The Army estimated that the entire project would cost approximately $1.9 million.

Triax was the low bidder on the project, with a bid of $1,593,500. Before awarding the contract to Triax, the Army asked for confirmation of its bid because the figure was lower than the Army’s estimated project cost and substantially lower than the bid of the second-lowest bidder. Triax subsequently reconfirmed its bid “[i]n accordance with [Triax’s] understanding of the plans and specifications.” The Army gave Triax notice to proceed on December 17, 1990, and the contract completion date was established as April 20,1992.

Triax and the Army first met to discuss the contract at a preconstruction meeting on January 22, 1991. During the course of that meeting, Triax and the Army discovered that they had completely different views as to the painting requirements of the contract. The Army believed the contract required all the newly constructed lanai surfaces to be painted, except for the concrete floor slab. Triax maintained that the contract required only small amounts of painting associated with the interior renovations, and that the lanai surfaces did not have to be painted.

The contract plans and specifications address painting at some length. The General Notes of the contract specify that when a new lock is installed, the door and frame must be painted. Several drawings detailing the kitchen renovation work expressly direct that touchup paint is to be applied to specific surfaces to match existing finishes. The most extensive provisions on painting appear in section 9900 of the specifications, entitled “Painting, General.” Because the language of that section is central to the dispute between the parties, the relevant portions are reproduced here:

Section 9900

Painting, General

Part 3 —Execution

13. SURFACES TO BE PAINTED: Surfaces listed in the PAINTING SCHEDULE, other than those listed in paragraphs SURFACES NOT REQUIRING *1472 PAINTING and SURFACES FOR WHICH PAINTING IS PROHIBITED, will receive the surface preparation, paints, and number of coats prescribed in the schedule.

14. SURFACES NOT REQUIRING PAINTING: The following listed items will not require painting: Existing surfaces in good condition, unless otherwise noted or required.

15. SURFACES FOR WHICH PAINTING IS PROHIBITED: The following items shall not be painted: Copper, anodized aluminum, plated surfaces, mineral surfaced built-up roofing, stainless steel.

18. PAINTING SCHEDULE: The PAINTING SCHEDULE prescribes the surfaces to be painted, and the number and types of coats of paint.

The Painting Schedule referenced in the above provisions appears at the end of Part 3 of section 9900, and lists seven surfaces and the painting treatment associated with each. The seven surfaces are:

1. Exterior and interior concrete masonry units
2. Exterior concrete surfaces
3. Exterior and interior wood surfaces not otherwise specified
4. Exterior ferrous surfaces, exposed, unless otherwise specified
5. Exterior and interior galvanized surfaces
6. Exterior aluminum and aluminum-alloy surfaces
7. Wood cabinets and existing interior wood doors

Of the seven listed items, the first three are applicable to components of the new lanais to be constructed by Triax. None of the drawings pertaining to the construction of the lanais contain any instructions on painting.

Triax and the Army were unable to resolve their differences over the scope of the painting provisions. Ultimately, Triax chose to do the painting requested by the Army and seek an equitable adjustment. The contracting officer denied the request, and Triax appealed to the Armed Services Board of Contract Appeals.

Before the Board, Triax argued that the information contained in the Painting Schedule governs how to paint the seven listed surfaces when those surfaces are identified elsewhere in the contract as requiring paint. To bolster its interpretation, Triax pointed to two other provisions to demonstrate that the contract does not envision that the lanai surfaces would be painted. Paragraph 8.4.3 of section 1900 of the specifications required that Triax complete all work in an individual dwelling unit within 14 working days after gaining access to the unit. Paragraph 10.2 of section 9900 of the specifications directed that concrete masonry units must be allowed to dry (or “cure”) for at least 30 days before painting. Therefore, Triax reasoned, an interpretation of section 9900 requiring the lanai surfaces to be painted would be unreasonable, because the requirement of a 30-day curing period before painting would render timely performance of the contract impossible.

Triax also claimed that the Army’s interpretation would produce results at odds with customary commercial practice. According to Triax, concrete masonry units such as those to be used on the lanais are frequently left unpainted. Triax also noted that the wood specified for the lanai roof beams is a rough, structural grade that is ill-suited for painting but that has a “rustic” attractiveness in its unpainted state. Triax claimed that if the Army wanted the lanai beams to be painted, the only commercially reasonable course of action would have been to specify a better grade of wood requiring less surface preparation before painting. Finally, Triax argued that because paint degrades over time, the Army’s insistence that the lanais be painted would eventually result in a less attractive finished product.

The Board of Contract Appeals rejected Triax’s arguments and held that section 9900 *1473 of the contract constituted a clear direction to Triax to paint all the surfaces listed in the Painting Schedule, including the surfaces of the lanais. The Board found that the absence of specific directions on the drawings to paint the lanais was not a flaw in the contract, because the plans and specifications were intended to be read together in defining the scope of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sofitc3, LLC v. United States
Federal Claims, 2025
Langdon Engineering & Mgt
Armed Services Board of Contract Appeals, 2025
Govwave, LLC v. United States
Federal Claims, 2025
Philips Lighting North American Corporation
Armed Services Board of Contract Appeals, 2024
Korte Construction Company
Armed Services Board of Contract Appeals, 2023
The Boeing Company v. United States
968 F.3d 1371 (Federal Circuit, 2020)
CKY, Inc.
Armed Services Board of Contract Appeals, 2020
DynCorp International LLC
Armed Services Board of Contract Appeals, 2019
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2019
R.L. Persons Construction, Inc.
Armed Services Board of Contract Appeals, 2018
Zebel LLC v. United States
Federal Claims, 2017
Premier Office Complex of Parma, LLC v. United States
134 Fed. Cl. 83 (Federal Claims, 2017)
Veterans Evaluation Services, Inc. v. United States
132 Fed. Cl. 610 (Federal Claims, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
130 F.3d 1469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triax-pacific-inc-v-togo-d-west-jr-secretary-of-the-army-cafc-1998.