Langdon Engineering & Mgt

CourtArmed Services Board of Contract Appeals
DecidedJune 3, 2025
Docket61959, 63501
StatusPublished

This text of Langdon Engineering & Mgt (Langdon Engineering & Mgt) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Langdon Engineering & Mgt, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Langdon Engineering & Mgt ) ASBCA Nos. 61959, 63501 ) Under Contract No. N00244-15-P-0294 )

APPEARANCE FOR THE APPELLANT: Mr. Albert L. Swank, Jr. President

APPEARANCES FOR THE GOVERNMENT: Allison M. McDade, Esq. Navy Chief Trial Attorney Elizabeth C. Tosh, Esq. Jerry Kim, Esq. Russell A. Shultis, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE WOODROW

This appeal involves the Navy’s termination for default of a firm fixed-price contract with Langdon Engineering & Management (Langdon) to refurbish and deliver eight bow thruster nozzles used to propel a type of hovercraft known as Landing Craft Air Cushion (LCAC). The Navy terminated Langdon’s contract for cause because Langdon failed to refurbish or deliver any of the bow thruster nozzles. Langdon appealed that termination (ASBCA No. 61959) and also submitted a monetary claim seeking $730,000 (ASBCA No. 63501).

Langdon’s owner, Mr. Albert L. Swank, Jr., who is not an attorney, represented appellant on a pro se basis. Despite his lack of any formal training, Mr. Swank ably and thoroughly made arguments and presented evidence throughout the hearing.

On March 2, 2021, the Board denied the Navy’s motion for summary judgment on the grounds that there was a material dispute of fact concerning whether the bow thrusters provided by the Navy differed materially from the OEM drawings and therefore could not be refurbished as required by the contract. Langdon Eng’g & Mgt., ASBCA No. 61959, 21-1 BCA ¶ 37,810 at 183,623.

On March 9, 2023, the Board conducted a hearing via videoconference on both entitlement and quantum. The hearing took place over four days, with the first two days being held on March 9-10, 2023, and the final two days on March 29-30, 2023. Following the hearing, both parties filed post-hearing briefs and reply briefs. With its post-hearing brief, Langdon submitted additional documents purporting to support its quantum claim. However, Langdon did not previously include these documents in its Rule 4 file, nor did it proffer the documents during the hearing.

As set forth below, we uphold the government’s termination for cause and deny the appeal (ASBCA No. 61959). We also deny Langdon’s appeal seeking monetary damages (ASBCA No. 63501).

FINDINGS OF FACT

I. The Contract

1. On May 22, 2015, the Navy (though the Naval Supply Systems Command, Fleet Logistics Center, San Diego), awarded Contract No. N00244-15-P-0294 to Langdon for the complete refurbishment of eight bow thruster nozzles used on air cushion landing craft (ASBCA No. 61959 (61959) R4, tab 1 at 1-3). In exchange for a firm-fixed-price of $77,295.28, Langdon agreed to refurbish the bow thruster nozzles as well as install eight new bow thruster bearings which the Navy had provided as Government Furnished Material (id. at 3).

2. On May 26, 2015, shortly after the contracting officer (CO) awarded the contract to Langdon, Mr. Swank emailed a representative of L-3 Unidyne, Inc. seeking a quote for the refurbishment of the eight bow thruster nozzles under the contract. The representative for L-3 Unidyne replied on the same date that he would respond to Mr. Swank’s request and that L-3 Unidyne had performed repairs and upgrades on an LCAC craft, including the refurbishment of the bow thruster nozzles. (App. supp. R4, tab 19.038)

3. The LCAC landing crafts are amphibious vehicles used to transport Marine personnel and equipment from ship to shore (tr. 2/7-8). The eight craft at issue here were manufactured in the 1980’s and 1990’s and were approximately 20-25 years old when the contract was awarded (tr. 2/7-8; 3/135).

4. Bow thrusters nozzles are used to steer the landing craft by directing high velocity air out of the nozzle. A bow thruster nozzle is a “fiberglass duct mounted vertically on the bow thruster bearing” (61959 R4, tab 254 at 1338). It rotates on the bearing and pushes “high-velocity air produced by the lift fans out through an elliptical exhaust nozzle that creates a venturi effect on the high-velocity air leaving the thruster” (id. at 1321. By directing air, the bow thruster controls the bow of the craft and steers the landing craft (tr. 2/10). Each landing craft has two bow thruster nozzles—referred to as a ship set—which can be rotated 360 degrees by the craft controller (tr. 2/13, 19, 135).

2 5. There are two fiberglass turning vanes connected horizontally to the inner walls of the bow thruster as well as three vertically mounted structural fiberglass reinforcements called “splitters” bisecting the turning vanes. The vanes channel the air flow through the thruster while the splitters strengthen and reinforce the thruster walls and turning vanes. (61959 R4, tabs 18 at 96, 254 at 1338)

6. The contract included a statement of work, dated February 20, 2015, that described the performance requirements. It was divided into seven sections, including 1.0 Introduction, 2.0 Background, 3.0 General Requirements, 4.0 Performance Requirements, 5.0 Deliverables, 6.0 Special Requirements, and 7.0 Point of Contact (61959 R4, tab 1 at 3-4).

7. Section 2.0 Background of the statement of work stated:

Due to the cumulative effects of saltwater/ultraviolet/sandblast exposure, the Bow Thruster Nozzles have reached/exceeded the intended service-life. These Bow Thruster Nozzles require complete refurbishment to provide an addition 10-20yrs of service- life. The Bow Thruster Nozzle (BTN) is made up of a painted fiberglass structure with mechanically fastened drive and attachment components; the compositions of all parts are detailed in the reference drawings and technical manual listed in section 4.0.

(61959 R4, tab 1 at 3)

8. Section 3.0 General Requirements provided that:

3.1 Each shipset of BTNs will be completely disassembled with all mechanically fastened components removed and glass bead blasted clean then visually inspected for damage. 3.2 Any damaged components will be repaired or replaced. All fasteners (nuts, bolts, washers, screws, etc..) will be replaced with new. 3.3 All existing paint on the fiberglass structure will be removed. Any damaged, deteriorated or missing fiberglass will be repaired/renewed/installed ensuring all reference [drawing] dimensions are maintained.

3 3.4 All new paint and marking will be applied after repairs are complete.

9. Section 4.0 Performance Requirements provided that “[a]ll repair material and physical, dimensional, and functional requirements are to be IAW the following reference drawings unless specifically addressed in section 6.0.” The drawings referenced in Section 4.0 were from the original equipment manufacturer (OEM):

4.1 Drawing. 5749810 Rev. R LCAC Mechanical Installation Bow Thruster 4.2 Drawing. 5749544 Rev. V LCAC Bow Thruster 4.3 Drawing. 5749793 Rev. N LCAC Bearing Bow Thruster 4.4 Drawing. 7616123 Rev. B SLEP Mod Bow Thruster 4.5 Drawing. 6800343 Rev. N LCAC Painting and Marking 4.6 Drawing. 5749811 Rev. L LCAC Bracket Support Bow Thruster Installation 4.7 Technical Manual S9568-AL-SLP-010 Rev. 02 Bow Thruster Assembly

(61959 R4, tab 1 at 4).

10. Section 5.0 Deliverables stated the following: “Four shipsets (8 each) BTNs will be picked up from Assault Craft Unit Five, fully refurbished IAW sections 4.0 and 6.0 and returned to Assault Craft Unit Five. Period of performance will not exceed 180 days from pickup. No work will be done at Assault Craft Unit Five” (id.).

11. Section 6.0 Special Requirements stated:

6.1 After refurbishment of the BTN is complete; install new GFM Bow Thruster Bearing in accordance with the reference technical manual listed in item 4.6 and mechanical installation [drawing] in item 4.1. The old bearing will be disposed of.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
McCready, Sheila v. Nicholson, R. James
465 F.3d 1 (D.C. Circuit, 2006)
Helene Curtis Industries, Inc. v. The United States
312 F.2d 774 (Court of Claims, 1963)
Edward R. Marden Corporation v. United States
803 F.2d 701 (Federal Circuit, 1986)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Hercules Incorporated v. United States
292 F.3d 1378 (Federal Circuit, 2002)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Century Exploration New Orleans, LLC v. United States
745 F.3d 1168 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Langdon Engineering & Mgt, Counsel Stack Legal Research, https://law.counselstack.com/opinion/langdon-engineering-mgt-asbca-2025.