J. D. Hedin Construction Company, Inc. v. The United States

408 F.2d 424, 187 Ct. Cl. 45, 1969 U.S. Ct. Cl. LEXIS 128
CourtUnited States Court of Claims
DecidedMarch 14, 1969
Docket121-60
StatusPublished
Cited by89 cases

This text of 408 F.2d 424 (J. D. Hedin Construction Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. D. Hedin Construction Company, Inc. v. The United States, 408 F.2d 424, 187 Ct. Cl. 45, 1969 U.S. Ct. Cl. LEXIS 128 (cc 1969).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR. . SUMMARY JUDGMENT

DAVIS, Judge.

Early in 1955 plaintiff agreed with the Veterans Administration to construct additional buildings at the Administration’s hospital in Marion, Indiana, for a price of almost $2,000,000. Notice to proceed was given on February 14, 1955, and the work was to be completed within 500 days, i. e. June 28, 1956. On November 29, 1956 — 154 days beyond the completion date — the contracting officer terminated plaintiff’s right to proceed. 1 He invoked Clause 5(a) (“Termination for Default — Damages for Delay — Time Extensions”) which authorized a default termination “[i]f the Contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time * The notice of termination also called upon Clause 9(a) (“Inspection”) which gave the contracting officer authority to reject defective material and workmanship or require its correction, and to direct the contractor to correct and replace the rejected work and material; “[i]f the Contractor fails to proceed at once with the replacement of rejected material and/or the correction of defective workmanship the Government may * * * terminate the right of the Contractor to proceed as provided in Clause 5 * * *.”

*426 Plaintiff’s position was that it was not in default, either on the score of delay or because of defective workmanship or materials. As for the former, it contended that it was entitled to time-extensions under Clause 5(c) which specified that the “right of the Contractor to proceed shall not be terminated * * because of any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor * * The claim was that, if the contracting .officer properly extended the contract completion date under this provision, the job would have been current on November 29, 1956, the date of the termination, and certainly would not then have been in default.

Plaintiff’s appeal was heard in 1958 by the Veterans Administration Construction Contract Appeals Board, under an antiquated procedure which we shall describe later. Meanwhile, a successor contractor was hired to continue with the work; notice to proceed was given this firm on January 9, 1957, and it completed the project on February 10, 1958 (over a year later).

In September 1959, the Board recommended to the V.A.’s Assistant Administrator for Construction — the official designated to determine building contract disputes — that the default termination be upheld. The Assistant Administrator (in November 1959) approved and adopted this recommendation, as well as the Board’s opinion. The result of this ruling, together with subsidiary determinations later made by the Board, was that plaintiff was assessed (i) with liquidated damages of $155,400 (at $300 per day) for 518 days (from the original completion date to the day the successor contractor actually finished the job, less short extensions administratively granted plaintiff in connection with two of the disputed items), and (ii) with the sum of $8,769.33 for V.A.’s expenses of protecting the work in place immediately after termination and before the successor contractor came on the site. 2

In its suit here Hedin challenges the Board’s findings and determinations, and asks damages for the breach it says occurred when the Government improperly defaulted it on November 29, 1956 (as well as for other lesser breaches). Both parties have moved for summary judgment on the administrative record, the trial commissioner having denied plaintiff’s demand for a de novo trial. 3

Faced with 1059 pages of motions and briefs from the parties, 4 and a Board opinion mounting to 277 pages, Commissioner Gamer has evaluated the record in,a detailed, careful, thorough and perceptive opinion (of 212 pages), with which we generally agree (except for the matter dealt with in Part V, infra). He has treated with each ground upon which the Board sustained the default termination and with each argument raised by the defendant, concluding that the default termination was improper. 5 Though for the largest part we agree with the commissioner’s discussion— without stopping to decide whether we approve every word, every sentence, or every nuance — and base our judgment on it, we do not adopt it in extenso as our own opinion because it is unavoidably long, detailed, and tied to the particular circumstances of this individual case. *427 However, the underpinning of our conclusions is found in that opinion, and our failure to adopt it as our own does not mean that we reject or differ significantly from it (except to the extent indicated in Part V, infra). It has been indispensable to our review and forms the essential foundation for our holdings.

I.

Under the Veterans Administration’s then procedures (38 CFR §§ 1.750-1.755 (1956)), appeals were heard in a way now happily considered obsolete. For one thing, the contracting officer’s findings of fact with respect to the termination were prepared subsequent to the plaintiff’s notice of appeal, and in piecemeal stages. Then, the plaintiff put on its case ex parte in informal proceedings before the Board, at which the contracting officer and the procurement officials were not represented officially; such cross-examination as there was came from the Board members. After plaintiff’s case was put on and the transcript made available to the procurement officials, the Board collected materials for the Government’s side, including written comments on the testimony of plaintiff’s witnesses, solicited statements, affidavits, etc. 6 There was no oral testimony by witnesses for the Government and they were not subject to cross-examination by anyone. The contracting officer’s case was put in wholly ex parte, via written statements, documents, and photographs.

The contractor first had its opportunity to see and comment on the materials collected by the Board for the Government’s side when the Board submitted a draft of its proposed determinations and findings. The plaintiff then had a period “to submit such further pertinent written evidence, data, and arguments as he may desire in support of his contentions” (38 CFR § 1.754(a) (1956) (emphasis added)). These additional materials were to be considered by the Board “before rendition of its final report to the Assistant Administrator for his decision” (38 CFR § 1.754(b) (1956)). As already indicated, the Assistant Administrator made the ultimate determination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paragon Defense Solutions, Inc.
Armed Services Board of Contract Appeals, 2025
Langdon Engineering & Mgt
Armed Services Board of Contract Appeals, 2025
Pinewood Inc. fka PNI Incorporation
Armed Services Board of Contract Appeals, 2025
Gulf Extreme Engineering & Construction
Armed Services Board of Contract Appeals, 2023
SBA Contracting, LLC
Armed Services Board of Contract Appeals, 2023
Trident Engineering & Procurement, P.C.
Armed Services Board of Contract Appeals, 2023
Safaa Al-Rawaby Company
Armed Services Board of Contract Appeals, 2023
Assist Consultants Inc.
Armed Services Board of Contract Appeals, 2021
John's Tile and Carpet Service
Armed Services Board of Contract Appeals, 2020
Axxon International, LLC
Armed Services Board of Contract Appeals, 2020
Grow Life General Trading, LLC
Armed Services Board of Contract Appeals, 2019
Stobil Enterprise
Armed Services Board of Contract Appeals, 2019
Ballistic Recovery Systems, Inc.
Armed Services Board of Contract Appeals, 2018
LKJ Crabbe Inc.
Armed Services Board of Contract Appeals, 2018
Pyrotechnic Specialties, Inc.
Armed Services Board of Contract Appeals, 2017
Baistar Mechanical, Inc. v. United States
128 Fed. Cl. 504 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
408 F.2d 424, 187 Ct. Cl. 45, 1969 U.S. Ct. Cl. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-d-hedin-construction-company-inc-v-the-united-states-cc-1969.