Nolan Brothers, Incorporated v. The United States

405 F.2d 1250, 186 Ct. Cl. 602, 1969 U.S. Ct. Cl. LEXIS 109
CourtUnited States Court of Claims
DecidedJanuary 24, 1969
Docket371-67
StatusPublished
Cited by44 cases

This text of 405 F.2d 1250 (Nolan Brothers, Incorporated v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nolan Brothers, Incorporated v. The United States, 405 F.2d 1250, 186 Ct. Cl. 602, 1969 U.S. Ct. Cl. LEXIS 109 (cc 1969).

Opinion

ON DEFENDANT’S REQUEST FOR REVIEW OF THE TRIAL COMMISSIONER’S ORDER

DAVIS, Judge.

The claimant, Nolan Brothers, Incorporated, undertook in August 1962 to construct for the Corps of Engineers two rock jetties out into the Gulf of Mexico from Matagorda Peninsula in Texas. The contract price ultimately amounted to some nine million dollars. In March 1964, when about one-third of the work was done, the defendant exercised its contract right to terminate performance for the Government’s convenience. The contractor did not contest this action but submitted, under the convenience-termination article, its termination claims on the total-cost basis, and efforts were made to settle the demands by negotiation. These were unsuccessful and, as the termination clause contemplated, the contracting officer then issued a unilateral determination in which he allowed the plaintiff $5,386,183 out of the $8,153,902 sought. Nolan Brothers appealed to the Corps of Engineers Board of Contract Appeals which granted only $101,315 more.

This action followed. In the second count of the petition plaintiff avers that the Board erred in several ways in refusing to increase the termination award. There is no dispute as to the method of handling this count in court. It is agreed that that part of the case will be reviewed on the basis of the administrative record under the standards of the Wunderlich Act. The parties’ arguments on that phase are not now before us; they will be presented initially to the trial commissioner for his recommendation.

It is the first count of the petition which concerns us at this time. There the plaintiff alleges that the Government breached the contract by furnishing an inadequate design and defective specifications for the jetties, and also by negligently failing to apprise the contractor of certain facts. The gist of the complaint is that the design and specifications envisaged a land-based operation, to which plaintiff was accustomed, but that, after completion by another contractor of a channel through Matagorda Peninsula near the location of plaintiff’s jetties, strong currents developed which made it impossible to place the jetty material by land-based equipment. The petition also says that defendant misrepresented the rise and fall of the tide, which seriously interfered with construction.

These contentions had not been presented to the Engineers Board of Contract Appeals and that body did not consider or determine the factual issues of whether the Government gave plaintiff an inadequate design or defective specifications, or withheld material facts. The trial commissioner, ruling that this first cause of action “contains allegations respecting a breach of contract by the defendant”, ordered a separate de novo trial on that claim. Defendant has requested review by the judges of that order. We set the matter for oral argument and asked the parties to brief, in addition to the points they desired to present, the legal issues of “(1) whether it is necessary, in view of the relief plaintiff has requested under the termination-for-convenience clause, for the court to consider or decide at all the issues of inadequate design, etc., raised by the first cause of action, and (2) if a trial on these issues is necessary, whether adequate relief could be granted administratively under the Changes, Changed Conditions, Suspension of Work, Damage to Work, and Termination-for-Convenience articles of the contract (separately or together).”

We think that the answer to the first query disposes of the problem and that no trial, either judicial or administrative, need be held on. the assertions of inadequate design, defective specifications, breach of warranty, misrepresenta *1253 tion, and withholding, of information. The reason, as we shall show, is that all the plaintiff is now entitled to is a proper award under the convenience-termination article — the claim covered by the second cause of action — and a separate claim of the kind set forth in the first cause of action no longer exists for plaintiff.

The crucial factor is the termination for the Government’s convenience. That was an action the defendant had a full right to take under the contract which lodged in the contracting officer the fullest of discretion to end the work “in the best interests of the Government.” See John Reiner & Co. v. United States, 325 F.2d 438, 442-443, 163 Ct.Cl. 381, 390 (1963), cert. denied, 377 U.S. 931, 84 S.Ct. 1332, 12 L.Ed.2d 295 (1964); Commercial Cable Co. v. United States, 170 Ct.Cl. 813, 821 (1965); Schlesinger v. United States, 390 F.2d 702, 707, 182 Ct.Cl. 571, 581 (1968). If, as plaintiff now seems to maintain, the spiir to invocation of this right of termination was the defendant’s realization that its plans and specifications were faulty, reliance on that motive would not be improper or an abuse of discretion. 1 The mere existence of a default by the Government would not bar convenience-termination (College Point Boat Corp. v. United States, 267 U.S. 12, 16, 45 S.Ct. 199, 69 L.Ed. 490 (1925)) and plaintiff had not treated the alleged breach as ending the entire agreement. Among the “host of variable and unspecified situations” calling for closing of the work under a still-existing contract (John Reiner & Co. v. United States, supra, 325 F.2d at 442, 163 Ct.Cl. at 390) it is entirely reasonable to include a post-contract recognition that the job is impossible or too difficult to perform or too costly for the Government if pushed through to its conclusion. That would be a characteristic case for a convenience-termination. The defendant could properly wish to cut unnecessary losses as early as possible and to consider what drastic changes might be needed in its plans. 2 Certainly the Government would not be compelled to see the contract work through to the bitter end, no matter what the cost or the trouble or the waste in resources. Rather, in that situation it would be as much in the Government’s “best interests” to use the termination clause as we have held it to be to avoid a conflict with the Comptroller General (e. g. John Reiner & Co. v. United States, supra) or with Congress (Schlesinger v. United States, supra) or in order to employ a contractor with greater production facilities (Nesbitt v. United States, 345 F.2d 583, 170 Ct.Cl. 666 (1965), cert. denied, 383 U.S. 926, 86 S.Ct. 931, 15 L.Ed.2d 846 (1966)).

The contractor’s protection on a convenience-termination is that he gets full reimbursement of his costs, together with a measure of profit. He becomes entitled to the “cost of the work performe.d and the cost of settling subcontract claims — plus 2% of the cost of materials and articles delivered to the site but not incorporated in the work and 8% of the balance of the cost (with the total profit not to exceed 61% of the whole cost of the work), unless the contractor would have sustained a loss on the entire contract in which event no profit is to be allowed.” G. L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Armour of America v. United States
69 Fed. Cl. 587 (Federal Claims, 2006)
Advanced Materials, Inc. v. United States
46 Fed. Cl. 697 (Federal Claims, 2000)
Cincinnati Electronics Corp. v. United States
39 Cont. Cas. Fed. 76,724 (Federal Claims, 1994)
Boeing Co. v. United States
39 Cont. Cas. Fed. 76,663 (Federal Claims, 1994)
Linan-Faye Construction Co. v. Housing Authority
847 F. Supp. 1191 (D. New Jersey, 1994)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Rhen v. United States
35 Cont. Cas. Fed. 75,672 (Court of Claims, 1989)
PBI Electric Corp. v. United States
35 Cont. Cas. Fed. 75,669 (Court of Claims, 1989)
Salsbury Industries v. United States
35 Cont. Cas. Fed. 75,661 (Court of Claims, 1989)
Maxima Corporation v. The United States
847 F.2d 1549 (Federal Circuit, 1988)
Skip Kirchdorfer, Inc. v. United States
34 Cont. Cas. Fed. 75,481 (Court of Claims, 1988)
Ralcon, Inc. v. United States
34 Cont. Cas. Fed. 75,377 (Court of Claims, 1987)
American Science & Engineering, Inc. v. United States
8 Cl. Ct. 129 (Court of Claims, 1985)
Descon System Ltd. v. United States
32 Cont. Cas. Fed. 72,989 (Court of Claims, 1984)
Miracle Contractors, Inc. v. United States
32 Cont. Cas. Fed. 72,682 (Court of Claims, 1984)
Golden Eagle Refining Co. v. United States
31 Cont. Cas. Fed. 72,190 (Court of Claims, 1984)
J & L Janitorial Services, Inc. v. United States
30 Cont. Cas. Fed. 70,185 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
405 F.2d 1250, 186 Ct. Cl. 602, 1969 U.S. Ct. Cl. LEXIS 109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nolan-brothers-incorporated-v-the-united-states-cc-1969.