Linan-Faye Construction Co., Inc. v. Housing Authority of the City of Camden

49 F.3d 915, 1995 U.S. App. LEXIS 5078, 1995 WL 55661
CourtCourt of Appeals for the Third Circuit
DecidedMarch 13, 1995
Docket94-5193
StatusPublished
Cited by101 cases

This text of 49 F.3d 915 (Linan-Faye Construction Co., Inc. v. Housing Authority of the City of Camden) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Linan-Faye Construction Co., Inc. v. Housing Authority of the City of Camden, 49 F.3d 915, 1995 U.S. App. LEXIS 5078, 1995 WL 55661 (3d Cir. 1995).

Opinions

[917]*917OPINION OF THE COURT

COWEN, Circuit Judge.

Linan-Faye Construction Company Co., Inc. (“Linan-Faye”), a public housing contractor, appeals from orders of the district court that granted summary judgment for the Housing Authority of the City of Camden (“HACC”) on Linan-Faye’s claims under public contract law and 42 U.S.C. § 1983. Because the district court erred in applying federal common law rather than state law to resolve this dispute, we will reverse and remand to the district court for further proceedings. Nevertheless, since we conclude that in the absence of New Jersey law which specifically interprets “termination for convenience” clauses New Jersey courts would look to federal common law for guidance, we will limit the triable issues on remand to a determination of: (1) the definition of “work performed” for purposes of paragraph 17 of Linan-Faye’s contract with HACC; (2) the pre-termination expenses incurred by Linan-Faye that may be compensable as “work performed” under paragraph 17 of the contract; and (3) HACC’s liability, if any, for damages resulting from HACC’s withholding of Linan-Faye’s performance bond after termination. Finally, because the district court did not err in determining that Linan-Faye failed to demonstrate a protectible property or liberty interest sufficient to support its § 1983 claim, we will affirm the district court’s grant of summary judgment on this claim.

I. FACTS & PROCEDURAL HISTORY

On August 11, 1988, HACC advertised for bids on a housing modernization project. The project involved the renovation and rehabilitation of 244 housing units and was to be funded in substantial part by a grant from the United States Department of Housing and Urban Development pursuant to the Public and Indian Housing Comprehensive Improvement Assistance Program (“CIAP”). Plaintiff, Linan-Faye, attended all required pre-bid meetings and submitted a bid of $4,264,000, together with supporting documentation which included a bid bond, performance bond, qualification statement, and required affidavits. Linan-Faye was the lowest responsible bidder for the job, underbidding its nearest competitor by $600,000. Accordingly, HACC informed Linan-Faye that the contract was to be forthcoming.

Linan-Faye engaged in preparatory activities in connection with the contract, including meeting with prospective subcontractors, job planning and pricing, talking with relevant inspectors, and seeming insurance. Also, on several occasions, representatives of Linan-Faye met with HACC and its architect to discuss specifications and make preparations for the commencement of physical construction. Linan-Faye, however, never began physical construction because numerous disputes broke out between the parties over interpretation of the specifications.

Linan-Faye contends that HACC demanded concessions before permitting work to begin. HACC maintains that the parties arrived at different interpretations of the project plans and specifications, and this conflict became evident at pre-construction meetings. On November 29, 1988, as the result of these disputes, HACC advised Li-nan-Faye that it was going to rebid the project. Linan-Faye filed suit to enjoin this rebidding and allow it to complete the project as bid.

The district court entered a temporary restraining order to prevent HACC from accepting further bids. Subsequently, the court approved a Stipulation of Settlement and Order of Dismissal with Prejudice, under which the parties agreed to execute the contract and proceed with the project as originally. planned. Nevertheless, disputes soon broke out again.

On November 22, 1989, HACC issued a Notice to Proceed. Linan-Faye contends that the notice was limited to an order to correct certain plumbing problems that were a portion of the original contract. Linan-Faye refused to proceed in a piecemeal fashion, and insisted that it would not begin work until a certain number of vacant buildings were available at the same time so that it could achieve economies of scale. HACC responded that it had scattered vacant units available, but not rows of units.

[918]*918Subsequently, HACC attempted first to extract the plumbing segment from the contract and, when that failed, proposed a complete buy-out of Linan-Faye’s contract. The parties entertained the possibility of a buyout until July of 1990, at which time HUD informed HACC that it would not approve a buy-out. HACC reinstated the previous Notice to Proceed by letter dated July 23, 1990.

At a preconstruction meeting on September 6, 1990, Linan-Faye informed HACC that it would not start work until the contract price was increased to reflect the costs incurred by the delay in commencing construction. HACC responded that Linan-Faye had to begin work before it would address the issue of the price increase.

HACC elected to terminate Linan-Faye’s contract by letter dated September 25, 1990. In that letter, Gregory Kern, the Interim Executive Director of HACC, stated that HACC would instruct the Modernization Office to assist Linan-Faye in reclaiming its performance bond. While the letter did not mention the terms “breach” or “default,” it did state that Linan-Faye “had continually failed to demonstrate its intent to perform under the public contract.” Letter from Kern to Norman Faye (September 25, 1990); App.Vol. I at 114 — 115. HACC confirmed its decision to terminate by letter dated October 23, 1990.

Linan-Faye objected to the termination and filed the instant action on October 26, 1990, setting forth theories of recovery under New Jersey public contracts law and 42 U.S.C. § 1983. Linan-Faye served HACC with a complaint in December of 1990 seeking specific performance and damages. HACC did not surrender Linan-Faye’s performance bond until July of 1991, after the district court determined that specific performance was not available to Linan-Faye.

In April of 1992, HACC filed a motion for summary judgment on Linan-Faye’s civil rights claim and for the first time argued, in that same motion, that the “termination for convenience” clause set forth in paragraph 17 of the General Conditions of their contract limited Linan-Faye’s damages under the contract.1 The district court granted HACC’s motion for summary judgment on the § 1983 claim, but deferred decision on the effect of the termination of convenience clause pending further discovery.

Upon a renewed motion for summary judgment, the district court held for HACC, determining that Linan-Faye’s damages would be limited to those compensable under the contract’s termination for convenience clause. The district court left open, however, the possibility of recovery for damages accruing from HACC’s initial failure to identify specifically the termination as one of convenience.

HACC filed its third motion for summary judgment on October 27, 1993. In that motion, HACC contended that since Linan-Faye never began work under the contract, it could not recover any damages under the termination for convenience clause. Linan-Faye responded that it could recover damages for: (1) preparatory costs such as soliciting subcontractors, pricing, and pre-construction meetings; (2) improper notice of termination; (3) pre-termination delay by HACC; and (4) HACC’s refusal to relinquish Linan-Faye’s performance bond. Determin[919]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A.L. Prime Energy Consultant, Inc. v. Mass. Bay Transportation Authority
95 N.E.3d 547 (Massachusetts Supreme Judicial Court, 2018)
A.L. Prime Energy Consultant, Inc. v. Massachusetts Bay Transportation Authority
34 Mass. L. Rptr. 164 (Massachusetts Superior Court, Suffolk County, 2017)
Masso-Torrellas v. Municipality of Toa Alta
845 F.3d 461 (First Circuit, 2017)
Garcia-Gonzalez v. Puig-Morales
761 F.3d 81 (First Circuit, 2014)
Freebery v. Coons
589 F. Supp. 2d 409 (D. Delaware, 2008)
Ferrone v. Onorato
298 F. App'x 138 (Third Circuit, 2008)
Hughes v. City of Bethlehem
294 F. App'x 701 (Third Circuit, 2008)
Benn v. County of Los Angeles
58 Cal. Rptr. 3d 563 (California Court of Appeal, 2007)
No. 05-2361
481 F.3d 187 (Third Circuit, 2007)
Carton v. Choice Point & Choice Point Services, Inc.
450 F. Supp. 2d 489 (D. New Jersey, 2006)
Solomon v. Philadelphia Housing Authority
143 F. App'x 447 (Third Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
49 F.3d 915, 1995 U.S. App. LEXIS 5078, 1995 WL 55661, Counsel Stack Legal Research, https://law.counselstack.com/opinion/linan-faye-construction-co-inc-v-housing-authority-of-the-city-of-ca3-1995.