Masso-Torrellas v. Municipality of Toa Alta

845 F.3d 461, 2017 WL 74706
CourtCourt of Appeals for the First Circuit
DecidedJanuary 9, 2017
Docket16-1319P
StatusPublished
Cited by35 cases

This text of 845 F.3d 461 (Masso-Torrellas v. Municipality of Toa Alta) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Masso-Torrellas v. Municipality of Toa Alta, 845 F.3d 461, 2017 WL 74706 (1st Cir. 2017).

Opinion

DYK, Circuit Judge.

Plaintiffs appeal from a district court order dismissing their 42 U.S.C. § 1983 claim for lack of subject matter jurisdiction, and declining to exercise supplemental jurisdiction over related state law claims. We affirm the district court’s dismissal. The district court found that it lacked subject matter jurisdiction because *464 the parties had failed to comply with the mediation/arbitration clause in their contract. Although we conclude that the district court erred by holding that the mediation/arbitration clause applied to the § 1983 claim, we conclude that the § 1983 claim should be dismissed pursuant to Fed. R. Civ. P. 12(b)(6) for failure to state a claim. Accordingly, there is also no supplemental jurisdiction over the state law claims.

I.

This dispute relates to contracts for the construction of a municipal transportation terminal. On May 7, 2010, defendant, the Municipality of Toa Alta (“Municipality”), awarded a construction project to plaintiff, OSSAM Construction Inc. (“OSSAM”), to build the terminal on land owned by the Municipality. The parties contemplated that the construction project would be undertaken in two phases, with two separately executed contracts. The Phase I contract was executed on September 10, 2010, and the work was apparently completed without incident within the 120 days provided in the contract. The Phase II contract was executed on September 4, 2012. From September of 2014 and continuing through December of 2014, disputes arose regarding payments for the work performed in connection with the Phase II contract. On January 20, 2016, OSSAM issued a notice of default against the Municipality due to its alleged nonpayment for the completed construction work. On February 4, 2016, the Municipality notified OSSAM by letter that the contract between OSSAM and the Municipality was being terminated effective immediately “[d]ue to reasons of public policy in connection with the sound administration of [municipal] funds.” JA 122. This letter was signed by Mayor Clemente Agosto-Lugar-do (“Agosto”) on behalf of the Municipality. On the same day, municipal officials and police officers took control of the construction site, which was on municipal property.

After taking control of the site, the Municipality initially barred OSSAM from removing any property from the construction site. The Municipality alleges that this was necessary to fully inventory the on-site property and determine the correct ownership pursuant to the contract. On February 5th and 14th, OSSAM was permitted to retrieve some of its property from the site. And on February 18th, OSSAM was finally permitted access to the site to retrieve “most” of its property. Appellants allege that at the time of filing the Complaint, the Municipality still retained security barriers and fences belonging to OS-SAM.

On May 4, 2015, OSSAM, its president José Francisco Massó-Torrellas and his wife Sarina Maldonado-Alfandari, and OS-SAM’s vice-president Francisco José Mas-só-Torrellas and his wife Rosa Julia Esté-vez-Datiz, filed a complaint in the District Court of Puerto Rico, against the Municipality, Agosto in his official capacity as mayor, Agosto and his wife Yaritza Rosario-Soto in their personal capacities, an indeterminate number of unnamed Municipality police officers and officials in them official and personal capacities, along with their spouses, and any “insurance companies] that may be responsible to [the] Plaintiffs.” JA 12. The plaintiffs claimed that the defendants violated 42 U.S.C. § 1983 when the defendants acted under color of law to interfere with the plaintiffs’ Fourth, Fifth, and Fourteenth Amendment rights during the construction site takeover in February of 2014. The plaintiffs also claimed that these actions constituted a breach of contract and “a violation of the Constitution and laws of the Commonwealth of Puerto Rico.” JA 23.

*465 The defendants moved to dismiss the § 1983 claim for failure to state a claim, and also argued that “OSSAM has not complied with the mandatory arbitration clause in the contract.” JA 41.

The Phase II construction contract between OSSAM and the Municipality included clause 35, which we refer to as the mediation/arbitration clause. It provided that

[i]n the event that any controversy arises from the interpretation or of any other class among the parties with respect to any matter related to this contract, it shall be previously be [sic] required that before resorting to a judicial forum for the adjudication of their rights, that the parties exhaust a mediation procedure. The ■ Municipality and [OSSAM] will at all times attempt to resolve their claims and disputes among themselves in [good] faith and if unable to arrive at an agreement^] they bind themselves to resolving the controversy or dispute through mediation.

JA 117-18 (emphases added). The Phase I contract included the same clause with an additional final sentence stating that “[t]he mediator’s decision will be final and firm.” Add. 2. This sentence was not included in the Phase II contract. 1

The usual meaning of arbitration is that the dispute resolution is binding and final. See Fit Tech, Inc, v. Bally Total Fitness Holding Corp., 374 F.3d 1, 7 (1st Cir. 2004). Conversely, the usual meaning of mediation is that the dispute resolution is non-binding. See In re Atlantic Pipe Corp., 304 F.3d 135, 141 (1st Cir. 2002). For purposes of resolving this case, we need not decide whether clause 35 provides for nonbinding mediation or binding arbitration.

Interpreting clause 35 as an arbitration clause, the district court held that “the parties must comply with the obligation to mediate their claims before pursuing claims in a judicial forum,” and “dismissed for lack of subject matter jurisdiction.” Add. 4, 6.

The plaintiffs appeal. We have jurisdiction under 28 U.S.C. § 1291. We review the district court’s dismissal for lack of subject matter jurisdiction de novo. Viqueira v. First Bank, 140 F.3d 12,16 (1st Cir. 1998). We review the district court’s decision not to exercise supplemental jurisdiction over state law claims for abuse of discretion. González-De-Blasini v. Family Dept., 377 F.3d 81, 89 (1st Cir. 2004).

II.

We first address whether the district court erred by holding that the plaintiffs’ § 1983 claims must be mediated or arbitrated before pursuing judicial action.

Here, the parties agree that the district court erred in concluding that the mediation/arbitration clause covers constitutional claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

De Leon v. San Antonio
W.D. Texas, 2025
Herrera v. Cruz-Ramos
D. Puerto Rico, 2022
Preston Hollow v. Cottonwood Devel
23 F.4th 550 (Fifth Circuit, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
845 F.3d 461, 2017 WL 74706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/masso-torrellas-v-municipality-of-toa-alta-ca1-2017.