United States v. R. H. Taylor

333 F.2d 633
Court of Appeals for the Fifth Circuit·Decided September 14, 1964·No. 20516·Published·Cited by 25 cases

Opinion

HUTCHESON, Circuit Judge.

The United States as assignee of its contractor’s claims and demands against a subcontractor for contractual overpay-ments instituted this action for recovery on those claims. 1 An order granting appellee-subcontractor’s motion for summary judgment was entered, and the United States appeals that order. The order was in error. The United States’ motion for summary judgment should have been granted. On this appeal the primary questions before the court are, what law applies to the interpretation of a disputes clause in a subcontract under a contract to perform work on a government project and how such a clause should be interpreted.

Peter Keiwit Sons contracted with the United States Government acting through the Atomic Energy Commission for the construction of a gaseous diffusion plant near Portsmouth, Ohio. On March 3, 1953, appellee TaylorWheless 2 entered into a subcontract with Keiwit to remove and grade dirt at the plant site. The subcontract required that payment should be made to the subcontractor on the basis of the number of cubic yards of material acceptably excavated. The amount of material excavated was to be determined by measuring it “in original position from cross-sections taken before stripping and after excavation and computed by the average end area method.” The parties later orally agreed to substitute the load count method for the average end method of material measurement as a practical way of making periodic quantity determinations upon which to base progress payments.

The work under the subcontract was completed in November, 1953. Keiwit then computed by the average end area method the work performed by Taylor-Wheless. Based on this computation in November, 1954, Keiwit issued Taylor-Wheless a final pay estimate indicating that payments made by the load count method exceeded those due under the average end area method, after subtracting retainage, by approximately $383,000.00. Taylor-Wheless rejected this estimate as inaccurate. Keiwit requested the Atomic Energy Commission to employ an independent survey group to determine if there was an overpayment. Such a group was employed, and they concluded that under the average end area method the overpayment less retainages amounted to $337,973.52. This computation presented to Taylor-Wheless on July 25, 1955, was also refused as inaccurate.

The parties failed to resolve their dispute and Keiwit referred the dispute to the Commission’s General Manager of Oak Ridge Operations under the provisions of the subcontract’s disputes clause. The clause was subsequently amended by agreement between the parties to provide for disputes determination by the Commission. The dispute was, therefore transferred to the Atomic Energy Commission Advisory Board of Contract Appeals (Board). No hearing had been held prior to this transfer.

The Board, after a hearing, found that after Keiwit’s initial submission of the dispute, as prescribed by the disputes clause of the contract, Keiwit and Taylor-Wheless agreed to modify the dis *636 putes clause by agreeing to submit disputes to the Commission rather than the Manager of Oak Ridge Operations. They further found that Taylor-Wheless and its attorney suggested times and places of hearing, that the chairman set a hear-' ing, that Taylor-Wheless indicated it was preparing for the hearing, agreed to a postponement of the hearing date, requested further postponements of the hearing, and, after failing to negotiate a settlement with Keiwit in December, 1956, objected to the jurisdiction of the Board and withdrew from the proceedings.

The Board proceeded to determine the issue as to overpayment under the average end area method of computation. Taylor-Wheless did not participate in the hearing. The Board did consider a document previously presented Keiwit by Taylor-Wheless entitled “Statement in Support of Taylor-Wheless Co.’s Final Estimate”. The document attempted to justify accuracy of the load count computations and attacked the accuracy of the average end area computations made by Keiwit prior to the independent survey. After considering oral and documentary evidence and Keiwit’s brief, the Board found an overpayment in the amount determined by the independent surveyors. They relied on this survey since they found that there was no showing that the final figures reflected inaccurate application of the computation principle called for in the contract, 3 and there was adequate basis in the record for finding that the computations were accurate. This fact finding of an overpayment of $337,973.52 was adopted by the Deputy General Manager of the Atomic Energy Commission on April 8, 1958.

On August 4, 1958, the Commission’s Portsmouth Area Manager, as Contracting Officer, determined Keiwit’s overpayment to Taylor-Wheless was an allowable cost and discharged Keiwit from any obligation with respect to government funds advanced for these payments. On August 19, 1958, Keiwit assigned its claims for overpayment against Taylor-Wheless to the United States. The United States instituted this action in the district court praying for judgment in the amount of the disputes award on both the decision of the Board and the underlying claim. Taylor-Wheless moved to dismiss, then moved for summary judgment on the grounds that: withdrawal from the disputes procedure invalidated the award; the Atomic Energy Commission and not the Board was the proper hearing agency; the assignment was invalid and unenforceable; and, finally, the suit constituted a suit on an implied contract and was, therefore, barred by the Mississippi Three Year Statute of Limitations. 4 The United States moved for summary judgment on the grounds that the award and the underlying claim were valid, viable, and enforceable. The court granted the motion of Taylor-Wheless and denied that of the United States.

The court held that: the parties had entered into an arbitration agreement; this was a remedial rather than a substantive matter; and the law of Mississippi would apply to the enforcement of the agreement in a suit such as this in which the government claimed as as-signee. Under Mississippi law the court held that “a party has a complete right, to withdraw from arbitration proceedings any time prior to the making of an award”. Therefore, the court reasoned, the award was invalid. Both parties admit that this is an accurate statement, of the law of Mississippi. They both rely on McClendon v. Shutt, 237 Miss. 703, 115 So.2d 740 (1959) and Machine Prod. Co. v. Prairie Local No. 1538, 230 Miss. 809, 94 So.2d 344, 95 So.2d 763 (1957).

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. R. H. Taylor, 333 F.2d 633 (5th Cir. 1964).

333 F.2d 633 (United States v. R. H. Taylor) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vetro, Inc. v. Active Plumbing and Heating, Inc.
403 F. Supp. 2d 1033 (D. Colorado, 2005)
Reliant Energy Services, Inc. v. Enron Canada Corp.
349 F.3d 816 (Fifth Circuit, 2003)
Turner Ozanne v. Hyman Power
111 F.3d 1312 (Seventh Circuit, 1997)
Turner/Ozanne v. Hyman/Power
111 F.3d 1312 (Seventh Circuit, 1997)
Linan-Faye Construction Co. v. Housing Authority
847 F. Supp. 1191 (D. New Jersey, 1994)
Whittaker Corp. v. Calspan Corp.
810 F. Supp. 457 (W.D. New York, 1992)
United States v. Hunter
700 F. Supp. 26 (M.D. Florida, 1988)
Irving Trust Co. v. Nationwide Leisure Corp.
562 F. Supp. 960 (S.D. New York, 1982)
Martinez v. Socoma Companies, Inc.
20 Cont. Cas. Fed. 83,050 (California Supreme Court, 1974)
United States v. Transamerica Insurance Company
357 F. Supp. 743 (E.D. Virginia, 1973)
United States v. Winter
319 F. Supp. 520 (E.D. Louisiana, 1970)
United States v. Fort Benning Rifle and Pistol Club
387 F.2d 884 (Fifth Circuit, 1967)