Powers v. Gilmour

297 F.2d 138
Court of Appeals for the Fifth Circuit·Decided December 13, 1961·No. No. 19014·Published·Cited by 3 cases

Opinion

GRIFFIN B. BELL, Circuit Judge.

Appellant Powers and his surety, American Employers Insurance Company complain of a jury verdict and judgment rendered thereon in the District Court in favor of Appellee, Gilmour, plaintiff [139] in the court below, and his surety, United States Fidelity and Guaranty Company, third party defendant there. Gilmour, as a subcontractor brought suit against Powers, the general contractor and his surety alleging the breach of a written subcontract. Powers had undertaken the construction of an addition to the Brunswick, Georgia hospital and Gilmour subcontracted with Powers to do the heating, plumbing and air conditioning work. Powers filed a counterclaim against Gilmour, and the third party defendant. The trial court by pretrial order limited the issues after the parties stipulated the amounts to be recovered depending on who should prevail so that the only issue left in the case for trial was whether the subcontract was breached by Powers or Gilmour.

The employees of Gilmour were members of a union and this was known to Powers at the time the subcontract was executed, while Gilmour knew at the time that Powers employed both union and non-union labor. Gilmour began performance under the subcontract in July, 1956. On August 1, 1956, a picket line was placed around the job site and the employees of Gilmour refused to cross it. It is undisputed, indeed stipulated, that neither Gilmour nor any of his employees had any part in or any connection with the picket line or the grievance which produced it, and that its creation and maintenance was wholly the work of labor union members who employed the picket line pursuant to their grievance against Powers for employing non-union labor.

On or about September 1, 1956, Powers obtained a temporary injunction in the state court enjoining the picketing and Gilmour’s men immediately returned to work and stayed on the job progressing the work under the subcontract until the injunction was dissolved on November 2, 1956. The picket line was then reinstated and again Gilmour’s men refused to cross it. Powers appealed from the order dissolving the injunction and in January, 1957 the Supreme Court of Georgia reversed the lower court holding that the picketing was illegal. Powers v. Courson, 213 Ga. 20, 21, 96 S.E.2d 577 (1957). The basis of the ruling, in addition to the admitted purpose of the picketing, was the refusal of union members employed on the job to cross the picket line.

The picketing continued from November 2, 1956 to the effective date of the judgment of the Georgia Supreme Court in January, 1957. The' testimony was that pending the court decision Gilmour attempted to get his men back to work through contact with union officials, and that he also attempted to employ other workmen to progress the contract.

Prior to the judgment of the Supreme Court of Georgia, and despite his contention before that court of the illegality of the picket line that the dispute was between him and the union and that the picket line was causing union members such as those employed by Gilmour to refuse to cross it, Powers by counsel and through the medium of a letter dated December 6, 1956 terminated the subcontract with Gilmour. The notice of termination in pertinent part is as follows:

“On behalf of Ed L. Powers Contracting Company, this is to notify you, that inasmuch as you have failed to diligently prosecute the work described and agreed upon in your contract dated May 7, 1956, Ed L. Powers Contracting Company will, in accordance with Article 1(a) and Article XIII of said contract, relet the same at the best terms obtainable by negotiation.”

Article XIII set out the method of termination. Article 1(a) of the contract on which Powers relied as the reason for terminating the contract is as follows:

“If, by reason of strikes, picketing or disputes of any nature between the sub-contractor and any individual, group or organization, this sub-contractor should be persistently, repeatedly, or for a period of fourteen (14) consecutive days, un[140] able to supply enough properly skilled workmen or proper materials to execute the work defined in this contract, then the contractor may proceed as outlined in Article XIII of this Contract.”

It was undisputed that Powers added this provision to the printed subcontract supplied by him. It was the position of Powers that the meaning of this provision was such as to make it operative in his favor in the event of picketing arising out of a dispute between Powers and others notwithstanding that Gilmour was in no way involved. Gilmour took the position and so testified that his understanding of this provision at the time the subcontract was executed was that it made him responsible in the event of a strike, picketing or dispute between him and other parties.

During the trial of the case counsel for Appellants stated to the court that it was through no fault of Gilmour that the picket line was established and maintained, and that the question before the court was whether the failure of the workmen of Gilmour to cross the picket line constituted a legal excuse for his failure to perform under the subcontract.

Appellants assign as error the insufficiency of the evidence but made no motion for a directed verdict. While there appears to be no basis in fact for this contention, suffice it to say that the question may not now be raised. Stokes v. Continental Assurance Company, 242 F.2d 893, 894 (5 Cir., 1957).

All of the other errors assigned fall into two categories: first, whether the provision contained in Article 1(a) of the subcontract binds Gilmour where the picket line arose out of a dispute wholly between Powers and others; and second, whether under the contract and as a matter of law Gilmour could be relieved of going forward under the contract if the labor dispute was such as to render him unable to furnish labor by the use of proper efforts.

The substance of the second category is that even if the disputed language in the contract is resolved in favor of Gilmour, nevertheless, Gilmour assumed the risk and was bound to perform under the contract nothwithstanding the labor dispute and resulting picket line may have rendered him unable to perform.

The District Court in view of the undisputed facts could have resolved the meaning of the provision contained in Article 1 (a) of the contract in favor of Gilmour as a matter of law.1 Ga.Code, Section 20-701; Bozarth v. Paschall, 1924, 158 Ga. 208, 209, 122 S.E. 683. Powers by inserting this language made Gilmour responsible for strikes, picketing or disputes between Gilmour, the subcontractor, and others. Here the dispute, and resultant picketing was between Powers and others. At any rate, the same result was obtained by submitting the meaning of the language to the jury as an ambiguity since the jury resolved its meaning in favor of Gilmour.

Free access — add to your briefcase to read the full text and ask questions with AI

Powers v. Gilmour, 297 F.2d 138 (5th Cir. 1961).

297 F.2d 138 (Powers v. Gilmour) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. R. H. Taylor
333 F.2d 633 (Fifth Circuit, 1964)
Powers v. Gilmour
297 F.2d 138 (Fifth Circuit, 1961)