Rumsey Mfg. Corp. v. United States Hoffman MacHinery Corp.

187 F.2d 927, 1951 U.S. App. LEXIS 3632
CourtCourt of Appeals for the Second Circuit
DecidedMarch 29, 1951
Docket21678_1
StatusPublished
Cited by13 cases

This text of 187 F.2d 927 (Rumsey Mfg. Corp. v. United States Hoffman MacHinery Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rumsey Mfg. Corp. v. United States Hoffman MacHinery Corp., 187 F.2d 927, 1951 U.S. App. LEXIS 3632 (2d Cir. 1951).

Opinion

L. FIAND, Chief Judge.

Both parties appeal from a judgment awarding damages to the plaintiffs for the defendant’s cancellation of a contract under which the Rumsey Company had promised to make and deliver to the defendant a large number of “adapters” — a small member of a naval projectile. The defendant had entered into a "prime contract” with the Navy to manufacture projectiles and placed three “Purchase Orders” with the Rumsey Company, all in the same form, the important words of which, for the purposes of this suit, were the following: “This purchase order is subject to all applicable rules, regulations and orders covering termination of the above designated direct or indirect government contract.” The “findings of fact” in the court below all appear on pages 406 and 407 of the report of the opinion; 1 and we shall *929 assume an acquaintance with them in what we have to say. The Navy cancelled the defendant’s contract and the defendant cancelled the “purchase orders” after a small part of the “adapters” had been delivered; the action was to recover for the expense which had been incurred, and for the profits lost. The plaintiffs sued without invoking the procedure provided by the Contract Settlement Act of 1944 ; 2 and the most important questions upon the appeal are (1) whether a subcontractor under a “war contract” may sue the “prime contractor” at common law, disregarding the Act; and (2) if so, whether in that event the measure of recovery, as laid down in the Act, is in any degree available to it. To an answer some analysis of the Act itself is necessary. Section 6 provides for the settlement of “termination claims,” which § 3(h) defines as claims of a “war contractor” “for the termination of any war contract”. A “war contractor” includes a “subcontractor” — § 3(c) — and ■“termination” includes any “work under a subcontract” — § 3(d). When a claim either of a contractor or a subcontractor is not settled “by agreement,” as § 6(c) permits, but by “determining fair compensation” under § 6(b), § 6(d) mentions seven items which shall be taken “into account,” and four which shall not. Section 7 as a whole provides for the settlement of “subcontractors’ claims,” and § 7(a) makes any settlement of a contractor with, his subcontractor “conclusive” against the “agency,” in cases where the settlement has been “approved, ratified or authorized” by the “agency.” If the “agency” does none of these things, § 7(d) gives it power to intervene in order directly to settle the claim of a subcontractor; but before doing so, not only must it “deliver to the subcontractor, and the war contractor liable to him, written notice stating its acceptance of responsibility for settling his claim,” but it must also procure the subcontractor’s “consent,” whereupon “the Government shall become liable for the settlement of his claims.” In the event of the failure of an “agency” and any “war contractor”— “prime” or subcontractor — to arrive at a settlement, § 13 sets up the procedure which shall be followed, but which is applicable only to cases where “the contracting agency” has become “responsible for settling any termination claim * * * by agreement”. When § 13 does apply, the “agency” may file its findings, and must do so within ninety days if the “war contractor” demands that it shall. If the “war contractor” is not satisfied, he has the option of appealing to an “Appeal Board,” or of suing in the Court of Claims or in a district court — § 13(b). Section 13(c) sets out the procedure both before the Appeal Board or a court. Although nothing in § 13 prescribes the seven items which § 6(d) makes proper in measuring “fair compensation” under § 6(b) when an “agency” is settling a termination claim, resort to either the Appeal Board or to a court is a review of the action of the “agency,” and it is reasonable to suppose that a court must as much follow § 6(d) as the Appeal Board- must. At any rate we shall so assume, and it would follow that, if the action at bar was authorized by § 13(b)(2) the subcontractor would have been entitled to invoke the seven items of § 6(d), and would have been subject to the four limitations of that section.

It appears to us that the scheme or plan of the Act is reasonably apparent. It was of course to be expected that “prime contractors” would let out some of the work to subcontractors, that the accounts between the two would have to be settled, and that the “prime contractor” would wish whatever he paid the subcontractor to be credited to him in his own settlement with the “agency.” Thus the “agency” had a lively interest in the “prime contractor’s” settlement with his subcontractor, which § 7(a) recognized when it gave the “agency” power to “approve” the terms which the contractor was willing to tender to the subcontractor, or to “ratify” his settlement, if he had made one, or to “authorize” him to settle on his own terms if it thought him “reliable” enough. These courses the “agency” might take as be *930 tween the contractor and itself; and they involved no action by it vis-a-vis the subcontractor. However, it might happen that the subcontractor, although by hypothesis he had no contract with the “agency,” was so unreasonable in his demands upon the “prime contractor” that he was blocking that speedy settlement which the Act was especially designed to promote. In that event the “agency” might intervene directly and “settle” the subcontractor’s claim, though only in case it had been able to induce the subcontractor to consent by offering the liability of the United States. In that event § 13 would come into play and we may assume that, if that happened, the subcontractor might not sue the contractor. Be that as it may, in the absence of such an agreement the “agency” was not authorized to “settle” a subcontractor’s claim at all, and there is no reason to suppose that the Act meant to put any limitations upon his action at common-law against the contractor. The only exception is that the regulations require all subcontractors promptly to file with “prime contractors” any claims they might have against them. 3

In the case at bar the Rumsey Company refused to make any settlement agreement with the Navy, although the Navy offered to become “responsible” for settling the claim under § 7(d). The district judge in his opinion quotes from a “conference between officers and directors” of the Rumsey Company on December 21, 1946, in which it “decided to reject the Navy offer of direct settlement but to encourage informal negotiations”. [88 Fed. Supp. 402.] The evidence of this conference we do not find in the record, but we assume that it must have occurred, since no one has disputed it; and the 21st finding is that the plaintiffs “did not follow the administrative procedure for the settlement of terminated war contracts provided for in the Contract Settlement Act of 1944.” It follows that they were free to sue the defendant at common law in contract because of its cancellation, as the district judge decided, and as indeed the attorneys for the defendant apparently conceded in the district court; and it also follows that none of the provisions of the Act relating to the “settlement” or “determination” of “termination claims” applied to the action. It was a bare suit in contract to be decided throughout without regard to the Act. The decision of the Supreme Court of Minnesota 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Capital Corp. v. United States
59 Fed. Cl. 563 (Federal Claims, 2004)
DPJ Company v. FDIC
First Circuit, 1994
Crowell v. H. L. Yoh Co.
49 Pa. D. & C.2d 97 (Philadelphia County Court of Common Pleas, 1969)
Laney Tank Lines, Inc. v. United States
237 F. Supp. 205 (E.D. South Carolina, 1965)
United States v. R. H. Taylor
333 F.2d 633 (Fifth Circuit, 1964)
Halifax Area Joint School System v. Chaundy
29 Pa. D. & C.2d 729 (Dauphin County Court of Common Pleas, 1962)
Breeze Corporations, Inc. v. United States
117 F. Supp. 404 (Court of Claims, 1954)
Apex Electrical Mfg. Co. v. Commissioner
16 T.C. 1171 (U.S. Tax Court, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
187 F.2d 927, 1951 U.S. App. LEXIS 3632, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rumsey-mfg-corp-v-united-states-hoffman-machinery-corp-ca2-1951.