DPJ Company v. FDIC

CourtCourt of Appeals for the First Circuit
DecidedAugust 16, 1994
Docket93-2145
StatusPublished

This text of DPJ Company v. FDIC (DPJ Company v. FDIC) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DPJ Company v. FDIC, (1st Cir. 1994).

Opinion

August 16, 1994 UNITED STATES COURT OF APPEALS UNITED STATES COURT OF APPEALS FOR THE FIRST CIRCUIT

No. 93-2145

DPJ COMPANY LIMITED PARTNERSHIP,

Plaintiff, Appellant,

v.

FEDERAL DEPOSIT INSURANCE CORPORATION, AS RECEIVER FOR BANK OF NEW ENGLAND, N.A.,

Defendant, Appellee.

ERRATA SHEET

The opinion of this court issued on July 27, 1994, is amended as follows:

On page 7, footnote 1, line 3, change "Cobblestone" to

"Cobblestone".

On page 8, paragraph 2, line 1, change "reliance of damages" to "reliance damages".

UNITED STATES COURT OF APPEALS FOR THE FIRST CIRCUIT

FEDERAL DEPOSIT INSURANCE CORPORATION, AS RECEIVER FOR BANK OF NEW ENGLAND, N.A.,

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MASSACHUSETTS

[Hon. Edward F. Harrington, U.S. District Judge]

Before

Torruella, Circuit Judge,

Coffin, Senior Circuit Judge,

and Boudin, Circuit Judge.

Robert D. Loventhal with whom Robert D. Loventhal Law Office was

on brief for appellant. Gregory E. Gore, Counsel, Federal Deposit Insurance Corporation,

with whom Ann S. DuRoss, Assistant General Counsel, and Robert D.

McGillicuddy, Senior Counsel, were on brief for appellee.

July 27, 1994

BOUDIN, Circuit Judge. DPJ Company Limited Partnership

("DPJ") is a Massachusetts real estate developer. On

February 12, 1988, it entered into a commitment letter

agreement with the Bank of New England. Subject to various

conditions being satisfied, the agreement contemplated the

creation of a three-year $2.5 million line of credit on which

DPJ could draw to finance primary steps in land development

ventures (e.g., deposits, option payments, and architectural

and engineering services).

The commitment letter provided that the creation of the

line of credit--an event called the "closing" (as in

"closing" a deal)--would occur after DPJ met various

requirements, such as the delivery to the bank of certain

documents, appraisals, and the like. DPJ also had to pay a

non-refundable loan commitment fee of $31,250 immediately.

In satisfying the conditions, DPJ spent a total of

$180,072.37 in commitment fees, closing costs, legal fees,

survey costs, points, environmental reports and other such

items.

The line of credit was "closed" on July 23, 1988.

Between that time and January 6, 1991, DPJ borrowed

approximately $500,000 from the bank pursuant to the line of

credit. The bank failed on January 6, 1991. On February 1,

1991, the bank's receiver, the Federal Deposit Insurance

Corporation, disaffirmed the line of credit agreement

-2-

pursuant to its statutory authority to repudiate contracts of

failed banks. 12 U.S.C. 1821(e)(1). Although the FDIC may

repudiate such contracts, the injured party may under the

statute sue the FDIC as receiver for damages for breach of

contract; but, with certain exceptions, the injured party may

recover only "actual direct compensatory damages," 12 U.S.C.

1821(e)(3)(A)(i), and may not recover inter alia "damages

for lost profits or opportunities." Id. 1821(e)(3)(B)(ii).

On May 22, 1991, DPJ filed an administrative claim with

the FDIC to recover the costs and expenses it incurred

pursuant to the commitment letter mentioned to obtain the

line of credit. 12 U.S.C. 1821(d)(5). The FDIC disallowed

the claim. DPJ then brought suit in the district court to

recover its claimed damages. Id. 1821(d)(6)(A). Both

sides moved for summary judgment.

The district court entered a decision on September 10,

1993, denying recovery to DPJ. The court concluded that DPJ

was "really seek[ing] to recoup its closing costs as

compensation for its lost borrowing opportunity resulting

from the FDIC's disaffirmance." In substance, the court held

that the "loss of borrowing capability" does not constitute

"actual direct compensatory damages." In support of its

decision it cited and relied upon Judge Zobel's decision in

FDIC v. Cobblestone Corp., 1992 WL 333961 (D. Mass. Oct. 28,

1992). DPJ then appealed to this court.

-3-

The critical statutory phrases--"actual direct

compensatory damages" and "lost profits and opportunities"--

have been the recurrent subject of litigation. See, e.g.,

Howell v. FDIC, 986 F.2d 569 (1st Cir. 1993); Lawson v. FDIC,

3 F.3d 11 (1st Cir. 1993). We have read the limitation of

recovery to compensatory damages, and the exclusion barring

lost profits or opportunities, against the background of

Congress' evident purpose: "to spread the pain," in a

situation where the assets are unlikely to cover all claims,

by placing policy-based limits on what can be recouped as

damages for repudiated contracts. Howell, 986 F.2d at 572;

Lawson, 3 F.3d at 16.

Contract damages are often calculated to place the

injured party in the position that that party would have

enjoyed if the other side had fulfilled its part of the

bargain. Subject to various limitations, lost profits and

opportunities are sometimes recovered under such a "benefit

of the bargain" calculation. A. Farnsworth, Contracts

12.14 (2d ed. 1990); C. McCormick, Damages, 25 (1935). Yet

where an injured claimant cannot recover the full benefit of

the bargain--for example, because profits cannot be proved

with sufficient certainty--there is an alternative, well-

established contract damage theory:

[O]ne who fails to meet the burden of proving prospective profits is not necessarily relegated to nominal damages. If one has relied on the contract, one

-4-

can usually meet the burden of proving with sufficient certainty the extent of that reliance . . . . One can then recover damages based on reliance, with

deductions for any benefit received through salvage or otherwise."

Farnsworth, supra, 12.16, at 928 (emphasis added).

As McCormick has explained, "[t]his recovery is strictly

upon the contract," McCormick, supra, 142 at 583. It is

not a remedy for unjust enrichment, nor is it rescission of

the contract. It is a contract damage computation that

"conform[s] to the more general aim of awarding compensation

in all cases, and [it] departs from the standard of value of

performance only because of the difficulty in applying the

[latter standard]." Id. at 583-84. See generally In re Las

Colinas, Inc., 453 F.2d 911, 914 (1st Cir. 1971) (citing

numerous authorities), cert. denied, 405 U.S. 1067 (1972).

Subject to common-law limitations, to which we shall

return in due course, expenditures by DPJ in fulfilling its

part of the bargain can properly be recovered as compensatory

damages under this alternative reliance theory. Certainly

damages so computed do not offend the terms of the federal

statute. The FDIC does not dispute that the $180,072.37 in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
DPJ Company v. FDIC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dpj-company-v-fdic-ca1-1994.