Crowell v. H. L. Yoh Co.

49 Pa. D. & C.2d 97, 1969 Pa. Dist. & Cnty. Dec. LEXIS 130
CourtPennsylvania Court of Common Pleas, Philadelphia County
DecidedDecember 8, 1969
Docketno. 2534
StatusPublished

This text of 49 Pa. D. & C.2d 97 (Crowell v. H. L. Yoh Co.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Philadelphia County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crowell v. H. L. Yoh Co., 49 Pa. D. & C.2d 97, 1969 Pa. Dist. & Cnty. Dec. LEXIS 130 (Pa. Super. Ct. 1969).

Opinion

McCLANAGHAN, J.,

On December 31, 1953, defendant contracted with the United States of America for the preparation of descriptions for the Signal Corps according to the Federal standards of item identification (prime contract). The contract covered 120,000 each item for the consideration of $346,800, with deliveries to be made commencing January 1, 1954, through April 30, 1955. On August 10, 1954, by modification no. 3, the said contract was amended; and due to delays caused by the governmental agency, the delivery dates were revised to commence January 1, 1954, through April 30, [98]*981956. Under certain circumstances, the completion date could be extended, but not beyond June 30, 1956. The amended contract reduced the quantity of items to 95,000 each item from 120,000 each item and increased the prime contract price to $419,256.25.

Prior to said December 31, 1953, defendant had advised plaintiff that it was considering entering into the prime contract, and that it would subcontract with others for part of the materials and work called for under said contract. Subsequently, on March 15, 1954, plaintiff and defendant entered into a written agreement wherein and whereby plaintiff would supply and perform part of the materials and work called for under the prime contract, to wit:

(a) Furnishing and embossing addressograph plates according to certain procedures;

(b) Furnishing and attaching tabs to each of the addressograph plate forms, in accordance with said procedures;

(c) Print on 3 x 5 cards the information contained on said addressograph plates, and

(d) Packing and addressing said 3x5 cards, in accordance with certain specifications.

Following modification no. 3 of the prime contract, plaintiff and defendant orally cancelled their written agreement of March 15, 1954 (exhibit “A”) and entered into a written agreement dated October 27, 1954 (exhibit “B”). Under exhibit “B” defendant was to furnish plaintiff with transmittal forms as promptly as defendant received the same under the prime contract. Plaintiff was thereafter to furnish the materials and perform the work involved, in performing according to certain written procedures, that part of the prime contract as follows:

(a) Furnish and emboss addressograph plates for the approximate amount of 235,000 frame and plate units at a unit price of $230 per thousand;

[99]*99(b) Furnish and attach tabs to each of said frames at a unit price of $18 per thousand;

(c) Print, pack and address approximately 7,000,000 3x5 cards, at a unit price of $4.50 per thousand.

The agreement between the parties provided that plaintiff would perform its work in accordance with the pace at which defendant would furnish plaintiff with materials necessary for plaintiff to perform its work. Defendant agreed that to the extent that the matter was within its control, the work to be performed by plaintiff would not extend beyond two years from the date of the subcontract of October 27,1954.

In the contract of March 15, 1954 (exhibit “A”) and in the contract of October 27,' 1954 (exhibit “B”), it was provided:

“. . . it is understood that this contract is subject to the same conditions and limitations that are contained in said Signal Corps’ contract,. . .”

During the course of the contract between defendant and the government, and of the contract between plaintiff and defendant, defendant, by reason of certain delays caused by the governmental agency, had requested the government to consider an equitable adjustment to relieve defendant from the large losses and damage occasioned by the governmental agency’s actions. Defendant requested an equitable adjustment of $798,262 over and above the contract price of $419,256.25. While defendant’s request'was being processed, defendant continued to perform under the prime contract and plaintiff continued to perform under its subcontract with defendant. On April 18, 1956, defendant had advised the government that while the contract provided for termination on April 30, 1956, an estimated additional period of 47 weeks would be required in order to complete the program. The government thereupon instructed defendant to [100]*100proceed with the delivery requirements and on April 30, 1956, defendant transferred all work in progress to the government.

Under the agreement marked exhibit “B,” the quantity of work to be performed by plaintiff was reduced but the rate of payment was increased. It is averred that pursuant to the contracts (exhibits “A” and “B”), plaintiff purchased materials in the amount of $14,227.55, incurred direct labor costs of $23,016.50, overhead charges of $27,036.67 and depreciation of $9,948.75, totalling $74,229.47. Plaintiff was paid $29,903.85 for work performed. Plaintiffs claim of $54,648.01, plus interest and costs, is arrived at by deducting $29,903.85 from said $74,229.47 to reflect a loss of $44,325.62. To this sum is added anticipated profit of $10,372.39, making a total claim of $54,698.01.

After negotiations, covering a period of several years, the government agreed to recognize the prime contract as having been 74.28 percent completed, and thereafter agreed to pay defendant $164,060.02, in addition to a sum equal to 74.28 percent of the prime contract price, or $323,439.98, making a total payment by the government to defendant of $487,500. Defendant, on July 19, 1957, had submitted to the government a cost breakdown totalling $844,541.45, and defendant thus claims to have suffered a loss under the prime contract of $357,041.45.

In the settlement item of $164,060.02, there was included by the government a payment to defendant of $5,000 under the caption “Subcontractor’s Claim.” The government’s report of the recommended settlement with defendant indicated that counsel for defendant was empowered to represent the subcontractor, and although defendant ventured that the subcontractor’s claim could be settled for $10,000 to $15,000, defendant agreed to the amount of $5,000 offered by the government and granted a release to the [101]*101government of any future claims arising out of said subcontract. Moreover, on June 9, 1958, in accepting the government’s contract settlement offer of $487,500, defendant, through counsel, agreed that included therein was the subcontractor’s claim, if any, which we (defendant) shall meet, if and when it arises.

Plaintiff alleges that both previous and subsequent to the settlement of defendant’s claim against the government plaintiff had frequently demanded that defendant pay to it the amount provided by the subcontract; that prior to settlement with the government, defendant had advised plaintiff it could not settle with plaintiff until it completed settlement negotiations with the government. After said settlement, plaintiff and defendant were unable to agree upon the amount of compensation defendant was obliged to pay plaintiff under the subcontract.

In the written contracts (exhibits “A” and “B”), between plaintiff and defendant, it is set forth that the prime contract of December 31, 1953, and various supplements thereto, had been exhibited to plaintiff and were available for its inspection at any time, at the office of defendant.

Plaintiff denies that in defendant’s settlement negotiations with the government said defendant was empowered to represent plaintiff in re its claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acchione v. Commonwealth
32 A.2d 764 (Supreme Court of Pennsylvania, 1943)
Union Paving Co. v. City of Philadelphia
95 Pa. Super. 342 (Superior Court of Pennsylvania, 1928)
Luria Engineering Co. v. Aetna Casualty & Surety Co.
213 A.2d 151 (Superior Court of Pennsylvania, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
49 Pa. D. & C.2d 97, 1969 Pa. Dist. & Cnty. Dec. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crowell-v-h-l-yoh-co-pactcomplphilad-1969.