Acchione v. Commonwealth

32 A.2d 764, 347 Pa. 562, 1943 Pa. LEXIS 480
CourtSupreme Court of Pennsylvania
DecidedMay 26, 1943
DocketAppeal, 28
StatusPublished
Cited by15 cases

This text of 32 A.2d 764 (Acchione v. Commonwealth) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Acchione v. Commonwealth, 32 A.2d 764, 347 Pa. 562, 1943 Pa. LEXIS 480 (Pa. 1943).

Opinion

Opinion by

Me. Justice Patterson,

This was a proceeding under the Act of April 25, 1927, P.L. 381, to modify an arbitration award.

John B. Acchione, trading as Acchione Contracting Company, was awarded two highway construction contracts for the Commonwealth of Pennsylvania. The first contract, executed December, 1933, had to do with Section 8 of State Highway Route No. 153, and the second, executed September, 1934, with Section 10 of the same highway. The work under the Section 8 contract required eleven months and was completed and accepted on November-20,1934. Tlie Commonwealth was anxious to have the Section 10 contract completed quickly, and after the bid was accepted it asked the contractor to complete the work, on or before November 25,1934, which the contractor agreed to do. At a conference prior to the signing of the Section 10 contract, the contractor indicated that the presence of facilities of certain utilities might cause delay. The Commonwealth agreed to assist the contractor in obtaining removal of these facilities. The site on Section 10 was not cleared until two months after work had begun, and the contract was not completed until May 24, 1935. The appellant contends-that the delay in the completion of the contracts,, due to the presence of the facilities of the utilities, caused him to suffer a loss of $5,046.80 on Section 8 and $20,847.11 on Section 10.

The contracts provided, inter alia, that : (1) (section 4) “The bidder is required to examine carefully the sité of and the proposal, plans, specifications- and contract form for the work contemplated, and it will be assumed that he has judged for and satisfied himself as to the conditions to be encountered . . (2) (section 40) “The contractor’s attention is drawn to. county *564 bxddges and certain other work which it may be necessary to construct, which are not under the supervision of this Department. He shall investigate such matters fully and satisfy himself as to the performance of such work so he can anticipate its execution and shall not make claim or hold the Department liable for his failure satisfactorily to anticipate the performance of the work . . .”; (3) (section 101) “The contractor shall keep in touch with all public service companies, individuals, and others owning or controlling any structures or tracks within the limits of the highway which may have to be removed, reset or reconstructed and shall give due notice in advance to the responsible party of the work required and time it should be completed . . .” ; and (4) “All questions or disputes arising between the parties . . . shall be referred to the Secretary of Highways and the Attorney General . . . whose decision and award shall be final, binding, and conclusive upon all parties without exception or appeal; and all rights or rights of any action . . . are hereby expressly waived.”

The contractor contended that the Commonwealth was obligated to deliver the site of the work free of obstacles which would interfere with the performance of the contracts and that its failure to do so constituted a breach of contract entitling him to damages in the amount of $25,893.91. The Commonwealth took the position that the contracts placed the duty of securing the removal of all obstacles and utility facilities on the contractor, or, in the alternative, that the Commonwealth was only liable for an “unreasonable” delay and that there was no evidence that the two months required for the removal of the facilities was “unreasonable.”

The controversy was submitted to arbitration and the board found the “. . . obligation on the part of the employer to give his contractor free access to the site at which the work is to be performed free and clear of obstructions . . .” was not applicable in this situation, and that the “. . . spirit of the specifications includes *565 the removal of poles among the responsibilities thus imposed.” The board awarded the contractor $2,270. on one excavation item caused by the delay.

The contractor appealed to the Court of Common Pleas of Dauphin County to modify this award, to include all damages caused by the delay. The Commonwealth contended that under the arbitration clause the award of the arbitrators was the final authority on questions of fact and of law, which contention is again made. The court below found that it had jurisdiction and concluded that the contractor covenanted to make no claim for damages for delay in the performance of his contract, when such delay was occasioned by the failure of utilities or others to remove structures from the site. The award of $2,270. for additional excavation costs was modified and reduced to $455.61 and all other claims of the contractor were refused. This appeal by the plaintiffs was then taken.

The Commonwealth’s assertion that the arbitrator’s award was the final authority on questions of fact and of law is without merit. In Philadelphia Housing Authority v. Turner Construction Co., 343 Pa. 512, the Court had before it a contract of an agency of the Commonwealth which provided for arbitration which should be conclusive. In that case we said (p. 518) : “Section 16 [Act of 1927] is mandatory and applies the provisions of the act of which it is a part to any written contract to which the Commonwealth or any agency thereof is a party.” Again, in Seaboard Surety Company v. Commonwealth, 345 Pa. 147, the Court, confronted with the identical arbitration provision in a contract to build a section of state highway, held as follows (p.151) : “Thus, it is clear that the Act of 1927 governs the award here under consideration, even though the arbitration clause of the contract provides that the atoard shall be final and conclusive and there shall be no .right of appeal.”

The provisions of the contracts did not place tlm duty of securing the removal of the utility facilities upon *566 either party, and we find nothing which indicates that the Commonwealth agreed to secure the removal of the facilities, or deceived the contractor in this respect. The provisions under consideration did place the contractor upon notice that he was required to examine the site, investigate matters not under the control and supervision of the Commonwealth and notify all parties owning or controlling structures within the limits of the highway to remove or reset them. The only reasonable interpretation of the language of the contracts is that the Commonwealth agreed to deliver the site burdened with existing obstructions over which it exercised no direct control. From previous experience the contractor had reason to know that some delay would ensue, and the cost of such reasonable delay was a proper element of expense to be estimated and included in the bid. 1

The authorities cited by counsel are not applicable in the present situation because both contracting parties had knowledge of pre-existing conditions under the immediate control of third persons which might delay the performance of the work. In Henry Shenk Co. v. Erie County, 319 Pa. 100, the Court refused to allow a general contractor to recover damages resulting from delay caused by third parties and events which were foresee *567 able at the time the contract was entered into.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ceco Corp. v. Carson Concrete Corp.
691 F. Supp. 850 (E.D. Pennsylvania, 1988)
Flamini v. General Accident Fire & Life Assurance Corp.
477 A.2d 508 (Supreme Court of Pennsylvania, 1984)
EC Ernst, Inc. v. Koppers Co., Inc.
476 F. Supp. 729 (W.D. Pennsylvania, 1979)
Pennsylvania Turnpike Commission v. Sanders & Thomas, Inc.
336 A.2d 609 (Supreme Court of Pennsylvania, 1975)
Litton RCS, Inc. v. Pennsylvania Turnpike Commission
376 F. Supp. 579 (E.D. Pennsylvania, 1974)
Pennsylvania Turnpike Commission v. Sanders & Thomas, Inc.
316 A.2d 127 (Commonwealth Court of Pennsylvania, 1974)
Remsco Associates, Inc. v. Beaver Falls Municipal Authority
63 Pa. D. & C.2d 561 (Beaver County Court of Common Pleas, 1973)
Crowell v. H. L. Yoh Co.
49 Pa. D. & C.2d 97 (Philadelphia County Court of Common Pleas, 1969)
J. L. Turner Co. v. General State Authority
41 Pa. D. & C.2d 118 (Dauphin County Court of Common Pleas, 1966)
Luria Engineering Co. v. Aetna Casualty & Surety Co.
213 A.2d 151 (Superior Court of Pennsylvania, 1965)
Amalgamated Transit Union, Division 85 v. Port Authority
208 A.2d 271 (Supreme Court of Pennsylvania, 1965)
Johnson v. Fenestra, Inc.
305 F.2d 179 (Third Circuit, 1962)
Jesse Johnson v. Fenestra, Incorporated
305 F.2d 179 (Third Circuit, 1962)
Moudy v. West Virginia Pulp & Paper Co.
121 A.2d 881 (Supreme Court of Pennsylvania, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
32 A.2d 764, 347 Pa. 562, 1943 Pa. LEXIS 480, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acchione-v-commonwealth-pa-1943.