Ceco Corp. v. Carson Concrete Corp.

691 F. Supp. 850, 1988 WL 69021
CourtDistrict Court, E.D. Pennsylvania
DecidedFebruary 25, 1988
DocketCiv. A. 85-1222
StatusPublished

This text of 691 F. Supp. 850 (Ceco Corp. v. Carson Concrete Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ceco Corp. v. Carson Concrete Corp., 691 F. Supp. 850, 1988 WL 69021 (E.D. Pa. 1988).

Opinion

OPINION

LOUIS H. POLLAK, District Judge.

The case at bar is a diversity suit tried to the court. This opinion constitutes the court’s findings of fact and conclusions of law.

The controversy arose out of the construction of a large office building in center-city Philadelphia in the early 1980s. The building — One Logan Square — is located just south of the Four Seasons Hotel and about two blocks from the Cathedral of Saints Peter and Paul. The general contractor for this large project was Turner Construction Company (“Turner”). Turner, in the spring of 1981, selected Carson Construction Corporation (“Carson”), a Pennsylvania corporation, as subcontractor for the entire reinforced concrete superstructure — the poured-in-place concrete flooring, vertical columns, and so-called “core area” containing elevator shafts, from the first floor to the top. Carson in turn subcontracted to The Ceco Corporation (“Ceco”), a Delaware corporation headquartered in Illinois, the concrete form-work for all areas of the superstructure other than the “core area.” It was contemplated that Ceco would utilize an expeditious and innovative mode of formwork with which it had considerable familiarity: in lieu of the conventional practice, under which separate sets of wooden forms are fabricated and assembled for each floor of a building, Ceco was to employ “flying forms” which are moved by crane from floor to floor as the pouring proceeds.

Ceco began its work in mid-July of 1981 and completed it in mid-October of 1982.

The Carson-Ceco subcontract price was $1,826,000. Certain change orders raised that figure to $1,964,079. Carson has paid Ceco $1,540,744.26, leaving a balance of $423,334.74.

In 1984 Carson advised Ceco that Turner had backcharged Carson $421,587 for the correction of work Turner had determined to have been improperly performed; Carson, in its turn, was holding Ceco accountable for the entire sum. Of these backcharges, $398,046 were said to reflect the cost of correcting the placement, on the perimeters of the poured concrete floors, of upwards of four hundred metal inserts (approximately one-third of the total) on which were hung the granite slabs that formed the outer facings of the building. Ceco denied that it was to blame for the mis-siting of the inserts. Ceco did accept responsibility for $22,000 of other backcharges— the cost of realigning certain vertical columns. Subtracting that $22,000 from the $423,334.74 withheld by Carson from the contract price, Ceco claims — and continues to claim — $401,334.74 to be due and owing as the net unpaid balance for performance of the subcontract.

Also in 1984, Ceco advised Carson that it was claiming $430,277 in delay damages because (1) performance of the subcontract had taken several months longer than Ceco and Carson had anticipated, and (2) (so Ceco asserted) Carson and others — but not Ceco — were responsible for the delays. With respect to these delay claims, Carson’s position was and is that (1) Ceco was, and Carson was not, responsible for much of the time lost on the job; (2) quite apart from who was to blame, the aggregate delay was not undue; and (3) in any event, Carson had made no contractual commitment to Ceco to protect it from delay.

With matters at impasse, Ceco in 1985 initiated this suit against Carson. Ceco seeks (1) the unpaid contract balance of $401,334.74 plus prejudgment interest; (2) delay damages (in the Joint Final Pretrial Order Ceco claimed $310,735; in its post-trial submission Ceco seeks $245,000); and (3) attorneys’ fees and other litigation-related expenses.

Carson denies that delay damages or attorneys’ fees and kindred expenses are ow *853 ing. Moreover Carson has filed a counterclaim which, if sustained, would substantially wash out Ceco’s claim for the unpaid contract balance. The counterclaim is the $421,587 backcharge claim referred to above. Of that figure, Ceco, as already noted, has acquiesced in $22,000, and Ceco’s calculation of the unpaid contract balance as $401,384.74 takes account of that $22,000 credit to Carson. The great bulk of Carson’s backcharges are the $398,-046 for the allegedly mis-sited metal inserts —a claim Ceco continues to dispute. As for the remaining $1541 in backcharges, Carson has not undertaken to document them in its post-trial proposed findings of fact; therefore, that aspect of the backcharge claims is deemed abandoned. In effect, then, the backcharges counterclaim amounts to $398,046.

The discussion that follows sorts out Ceco’s claims and Carson’s counterclaim. The starting point is an undisputed indebtedness of $401,334.74 running from Carson to Ceco. The first question to be considered is whether Carson also owes Ceco delay damages — and, if so, the amount of those damages; that question is addressed in Part I of this opinion. Part II addresses the question whether Ceco is liable to Carson for backcharges — and, if so, in what amount. Part III considers questions relating to interest and also to attorneys’ fees and kindred expenses.

I.

The Ceco Claim For Delay Damages

A. Does the Carson-Ceco Subcontract Protect Ceco Against Delays?

Ceco’s delay claims center on the discrepancy between, on the one hand, the performance timetable Carson and Ceco allegedly agreed upon and, on the other hand, the actual timetable. According to Ceco, the parties to the subcontract contemplated that Ceco’s work would get under way on June 1, 1981, and would be completed in February of 1982, whereas in fact Ceco did not get the green light until the middle of July, 1981, and did not finish until the middle of October, 1982. Ceco contends that these delays (a) were not of its own making and (b) increased its performance costs substantially. Ceco seeks to recover pursuant to Condition 2, the second of twenty-six pre-printed “Conditions” which comprise the last two pages of a seven-page Ceco document entitled “Proposal and Contract,” also known as “Form 110E.” The first five pages of Form 110E are typed, not pre-printed, and cover in some detail a number of matters having particular reference to Ceco’s role in the One Logan Square project. 1 The caption headings are “SCOPE,” “EXCLUSIONS,” “SPECIFIC PROVISIONS,” “PLAN REFERENCE,” “OSHA,” “PRICE,” AND “TERMS.” Two of .these particularized provisions (paragraph 6 of SCOPE and paragraph 14 of SPECIFIC PROVISIONS) expressly supersede two of the pre-printed Conditions. Condition 2 — the pre-printed Condition relied on by Ceco — is captioned “Delay.” It reads as follows:

Ceco will not be responsible for delays in performance caused by delays due to strikes, jurisdictional disputes, disputes between union and non-union personnel, shortages of materials and equipment, fires, acts of nature, wars, or other circumstances reasonably beyond Ceco’s control. In the event of delays beyond Ceeo’s reasonable control, the time set for performance shall be extended for a period equivalent to the period of delay, and Ceco shall not be liable for damages for such delay. In the event of substantial delay in the progress of the work, for which Ceco is not responsible, Ceco shall have the right to remove its equipment upon two weeks’ notice. If, as a result of circumstances beyond its reasonable *854

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. L. Hall Construction Company v. The United States
379 F.2d 559 (Court of Claims, 1966)
Zook Bros. Construction Company v. State
556 P.2d 911 (Montana Supreme Court, 1976)
Siefford v. Housing Auth. of City of Humboldt
223 N.W.2d 816 (Nebraska Supreme Court, 1974)
Reaction Molding Technologies, Inc. v. General Electric Co.
588 F. Supp. 1280 (E.D. Pennsylvania, 1984)
Bethlehem Steel Corp. v. Litton Industries, Inc.
468 A.2d 748 (Supreme Court of Pennsylvania, 1984)
C. J. Langenfelder & Son, Inc. v. Commonwealth
404 A.2d 745 (Commonwealth Court of Pennsylvania, 1979)
Magar v. Lifetime, Inc.
144 A.2d 747 (Superior Court of Pennsylvania, 1958)
Daset Mining Corp. v. Industrial Fuels Corp.
473 A.2d 584 (Supreme Court of Pennsylvania, 1984)
Acchione v. Commonwealth
32 A.2d 764 (Supreme Court of Pennsylvania, 1943)
Ericksen v. Edmonds School District No. 15
125 P.2d 275 (Washington Supreme Court, 1942)
Universal Builders, Inc. v. Moon Motor Lodge, Inc.
244 A.2d 10 (Superior Court of Pennsylvania, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
691 F. Supp. 850, 1988 WL 69021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ceco-corp-v-carson-concrete-corp-paed-1988.