Zook Bros. Construction Company v. State

556 P.2d 911, 171 Mont. 64, 1976 Mont. LEXIS 514
CourtMontana Supreme Court
DecidedAugust 25, 1976
Docket12983
StatusPublished
Cited by22 cases

This text of 556 P.2d 911 (Zook Bros. Construction Company v. State) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zook Bros. Construction Company v. State, 556 P.2d 911, 171 Mont. 64, 1976 Mont. LEXIS 514 (Mo. 1976).

Opinions

MR. JUSTICE CASTLES

delivered the opinion of the court.

Plaintiff appeals from a judgment of the district court, Lewis and Clark County.

Zook Brothers Construction Company (Zook) and the Montana Department of Highways (State) entered into a contract in June 1967, whereby Zook agreed to construct a segment of highway referred to as the “Montana City Project”, a 6.083 segment of interstate and secondary highway in Jefferson County, south of Helena, Montana. The contract allowed 300 days for completion of the project and involved a $3,000,000 contract between the parties.

The instant case involves Zook’s claim for damages allegedly caused by the State’s failure to inform Zook the State lacked right-of-way access to portions of the project, which is claimed to have caused a delay in scheduled operations and escalated costs of completion. Zook contends 1) it is entitled to damages for costs incurred in completion of the project, 2) for the cost of “standby” on equipment it was unable to utilize due to unforeseen delays, and 3) for profits allegedly lost on this project and subsequent projects due to the delays and tieup of assets.

[67]*67The delays relied upon by Zook as a basis for its claim were occasioned (a) by Montana Power Company’s problem in obtaining a right-of-way for relocation of a utility line, and (b) by the inability of the State to obtain right-of-way across various mining claims through the project.

(a) The utility delay.

The State, after planning the general location of the highway to be constructed, took steps to secure a right-of-way and to remove existing utilities from the area. The Montana Power Company was contacted regarding the relocation of an electrical transmission line. A relocation contract with Montana Power was approved by the State on June 27, 1967 and contained a provision that all utility moves were expected to be completed by August 31, 1967. Relocation of the power line was critical to Zook’s schedule for construction, in that the line had to be removed prior to construction of a frontage road upon which Zook had planned to divert traffic to complete the main highway construction. The power line was not relocated until April 1968.

(b) The mining claim delay.

The State encountered problems in obtaining the right-of-way through various mining claims within the work area. Zook was advised to begin construction on July 17, 1967, although the State was aware there were various problems obtaining right-of-way through the mining claims. At a preconstruction conference held between the State representatives and Zook personnel on July 19, 1967, Zook advised the State of its schedule for completion of the various phases of the project. The State discussed such diverse problems as safety and the protection of- wildlife habitat. The State did not advise Zook personnel of the right-of-way difficulties it was encountering.

Upon receipt of the State’s order to proceed on July 17, 1967, Zook began to mobilize all of the necessary equipment for completion of the project according to the agreed schedule. However, on July 27, 1967, the State issued a suspension order to Zook which prevented Zook from proceeding with construction in the [68]*68area of the mining claims during negotiation for and testing of these claims. Zook’s schedule called for completion of “Frontage Road No. 4” by September 15, 1967, and diversion of traffic from the existing route to utilize sophisticated blasting techniques, which were intended to reduce great quantities of rock to a size that would allow excavation with self-loading “scrapers” of large rock cuts. Zook also planned to use large quantities of the excavated rock and material as fill in the area involved in the mining claim stop order. However, because of the State’s failure to obtain the necessary right-of-way, Zook was forced to abandon its plan of traffic diversion and various fill and excavation requirements were delayed several weeks.

Restrictions on work in the vicinity of the mining claims were lifted on September 22, 1967; the power poles were removed by October 17, 1967; Frontage Road No. 4 was then available for construction work.

On September 6, 1967, Zook personnel informed the State by letter that the utility pole problem and the “mining claims delay has really fouled up our schedule for completion of this project and we feel we should be given full consideration for these delays.”

On November 12, 1968, Zook submitted a claim for damages resulting from the delays which it claimed caused the 116 day over-run on the scheduled completion date. This claims was rejected by the State. On March 24, 1972 Zook filed a “complete Documentation” [Zook’s description] of its claim for an amount far in excess of its original claim. Following the submission of this claim, the State undertook an audit of the Zook records for the purpose of evaluation of that portion of the claim relating to equipment standby costs. Zook’s claim was orally denied by the Director of the State Highway Commission after several meetings between the parties to discuss that claim.

Zook brought suit in the district court to recover the amount claimed, based on the State’s alleged breach in failing to secure the right-of-way. After a lengthy trial the district court determined:

[69]*69“The State of Montana materially breached its contract with Zook and the damages which Zook suffered thereby were a direct and proximate result of such breach.”

Zook was awarded a total of $ 140,917 in damages, consisting of $125,000 for maintenance of equipment in standby status, and $15,917 as additional expense for traffic control costs incurred due to its inability to complete Frontage Road No. 4.

Zook appeals claiming it is entitled to damages far in excess of those granted by the district court. The State cross-appeals on the basis Zook’s claim is barred by the special statute of limitations prescribed by section 83-602, R.C.M.1947, and by the terms of the contract and the judgment of the district court that a breach had occurred is not supported by the evidence. Hearing was had on March 5, 1976, before this Court, and on March 25, 1976, the Court ordered additional briefs and argument limited to:

1. Causal connection between breach and damages.

2. Equipment standby costs.

3. Traffic control costs.

4. Administrative costs.

Arguments heard on June 3, 1976 were restricted to a discussion of the four items enumerated.

The State contends the claim of Zook is barred by the provisions of section 83-602, R.C.M.1947, which provides in pertinent part:

“Whenever any contracting agency of the state of Montana provides a procedure for the settlement of any question or dispute arising between the contractor and said agency, the contractor, before proceeding to bring an action in court under provision of this act, must resort to such procedure within the time specified in his contract or, if no time is specified, within ninety (90) days after the question or dispute has arisen * * *

The contract between the parties contains a provision requiring:

[70]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Missoula County v. DOC
2024 MT 98 (Montana Supreme Court, 2024)
Republic Contracting Corp. v. South Carolina Department of Highways
503 S.E.2d 761 (Court of Appeals of South Carolina, 1998)
Edward Kraemer & Sons, Inc. v. City of Overland Park
880 P.2d 789 (Court of Appeals of Kansas, 1994)
Lutey Construction-The Craftsman v. State
851 P.2d 1037 (Montana Supreme Court, 1993)
Colorado Environments, Inc. v. Valley Grading Corp.
779 P.2d 80 (Nevada Supreme Court, 1989)
Ceco Corp. v. Carson Concrete Corp.
691 F. Supp. 850 (E.D. Pennsylvania, 1988)
Hostetter v. Donlan
719 P.2d 1243 (Montana Supreme Court, 1986)
Vandalia Ranch, Inc. v. Farmers Union Oil & Supply Co.
718 P.2d 647 (Montana Supreme Court, 1986)
State Highway Commission v. Brasel & Sims Construction Co.
688 P.2d 871 (Wyoming Supreme Court, 1984)
Jeffery v. Neville
620 P.2d 1218 (Montana Supreme Court, 1980)
C. J. Langenfelder & Son, Inc. v. Commonwealth
404 A.2d 745 (Commonwealth Court of Pennsylvania, 1979)
First SEC. Bank of Bozeman v. Goddard
593 P.2d 1040 (Montana Supreme Court, 1979)
Bohrer v. Clark
590 P.2d 117 (Montana Supreme Court, 1978)
Ferguson v. Town Pump, Inc.
580 P.2d 915 (Montana Supreme Court, 1978)
Zook Bros. Construction Company v. State
556 P.2d 911 (Montana Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
556 P.2d 911, 171 Mont. 64, 1976 Mont. LEXIS 514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zook-bros-construction-company-v-state-mont-1976.