Lutey Construction-The Craftsman v. State

851 P.2d 1037, 257 Mont. 387, 50 State Rptr. 321, 1993 Mont. LEXIS 94
CourtMontana Supreme Court
DecidedMarch 30, 1993
Docket91-479
StatusPublished
Cited by15 cases

This text of 851 P.2d 1037 (Lutey Construction-The Craftsman v. State) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lutey Construction-The Craftsman v. State, 851 P.2d 1037, 257 Mont. 387, 50 State Rptr. 321, 1993 Mont. LEXIS 94 (Mo. 1993).

Opinion

JUSTICE McDONOUGH

delivered the Opinion of the Court.

This is an appeal from the First Judicial District Court, Lewis and Clark County, of an order granting summary judgment for the defendant, State of Montana (State).

The sole issue on appeal is whether the District Court erred in granting summary judgment in favor of the State on the subissues *389 relative to a construction contract with the State. We affirm in part and reverse in part. The six subissues include:

I. Breach of Contract
II. Constitutionality of Section 18-1-402, MCA
III. Quantum Meruit
IV. Implied Warranty of Plans and Specifications
V. Fraud and Misrepresentation
VI. Breach of the Implied Covenant of Good Faith and Fair Dealing

Each of these subissues will be discussed in turn.

Lutey Construction — The Craftsman (Lutey), a construction contractor, entered into a contract with the State in August of 1984 to renovate the Yellowstone River Trout Hatchery in Big Timber, Montana. Morrison-Maierle, Inc. (Morrison), a firm of consulting engineers, was the architect/engineer on the renovation project.

Various problems occurred relative to the job and on August 12, 1985, the State sent Lutey a letter stating that Lutey was in default of the contract and the State was exercising its option to terminate the contract.

Lutey sent claims for time extensions and additional compensation to Morrison, who responded by letter on October 24,1985. The letter from Morrison recommended that many of Lutey’s claims be denied and requested more information about other claims. There is no evidence of further communication between the parties thereafter. A complaint was filed on August 22, 1989.

‘Under Rule 56(c), M.R.Civ.P., summary judgment is proper if the record discloses no genuine issues of material fact, and the moving party is entitled to judgment as a matter of law.” Kaseta v. N. Western Agency of Gr. Falls (1992), 252 Mont. 135, 138, 827 P.2d 804, 806. “[0]ur standard of review relating to conclusions of law ... is whether the tribunal’s interpretation of the law is correct.” Steer Inc. v. Department of Revenue (1990), 245 Mont. 470, 474-475, 803 P.2d 601, 603.

I. Breach of Contract

The State argues that the District Court was correct in concluding that Lutey’s breach of contract claim was barred by the statute of limitations. Section 18-1-402, MCA, provides that contract actions against the State, where no settlement procedure is provided to resolve conflicts, must be brought within one year after the cause *390 of action arises. The State contends that, according to Kitchen Krafters Inc. v. Eastside Bank (1990), 242 Mont. 155, 163, 789 P.2d 567, 571-572, Lutey’s cause of action accrued when the breach of the contract occurred, which was when he received the letter terminating the contract. Lutey, citing Zook Bros. Construction Company v. State (1976), 171 Mont. 64, 556 P.2d 911, counters that the statute of limitations does not run on his cause of action until he receives a final accounting from the State.

We agree with Lutey. Although we affirm Kitchen Krafters’ proposition that “the statute of limitations runs from the time of the breach and not from the time of injury ....”, we determine that the present case falls under the Zook exception.

In Zook, there were problems in the commencing of a highway construction project and the construction company filed a claim against the State for damages incurred due to the delay. The State rejected the claim so Zook provided documentation of the claim to which the State responded by auditing Zook’s records. Several meetings occurred between both parties and finally, the claim was orally denied by the Director of the State Highway Commission. Thereafter, Zook brought an action in District Court and that court concluded that Zook had suffered damages due to the State’s breach of contract.

On appeal to the Supreme Court, the State argued that Zook’s claim was barred by the statute of limitations because the cause of action arose at the time of the alleged breach, which was when the State ordered the work stoppage at the commencement of the project. This Court concluded that “a claim or dispute ARISES at the time the State submits a final estimate to the contractor for his approval or rejection.” Zook, 556 P.2d at 915. We also stated that the State “led Zook to believe that its claim would receive timely attention and would be reviewed by the State pending an administrative decision on its merits.” Zook, 556 P.2d at 915.

By the same token, Lutey contends that he was led to believe there would be a final accounting of his work on the Fish Hatchery renovation project when he was terminated. A portion of the termination letter read:

According to the terms of the contract, all funds due the contractor according to the contract shall be used to pay for completing the work. Funds remaining after completion of the work shall be paid to the contractor. If additional funds are needed to complete the work, the contractor shall pay the difference.

*391 The letter terminating the contract was dated August 12, 1985, and approximately one month later, Lutey submitted claims for additional compensation to Morrison, the State’s engineer. To date, Lutey has received only one letter, from the State’s engineer, Morrison, stating that its recommendation was to deny most claims and requesting more information on other claims. Lutey has not received any accounting from the State nor any information on his claims for additional compensation.

The argument that Zook completed the project while Lutey was terminated before the Fish Hatchery renovation was completed is immaterial. In the present case, Lutey insists that the State’s actions materially breached the contract, as in Zook, and that Lutey expected a final accounting from the State, as in Zook. The fact that Zook had completed the project and Lutey had not has no bearing on whether Lutey was entitled to a final accounting of the work it performed and any setoffs of the State.

This Court concludes that the trial court was in error when it granted summary judgment for the State on the breach of contract issue because the claim was barred by the statute of limitations. The statute does not begin to run until Lutey is provided with a final accounting from the State.

II. Constitutionality of the Statute

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Missoula County v. DOC
2024 MT 98 (Montana Supreme Court, 2024)
McConkey v. Flathead Electric Cooperative
2005 MT 334 (Montana Supreme Court, 2005)
Rodgers v. Mony Life Insurance
2005 MT 290 (Montana Supreme Court, 2005)
State v. Mitchell
2001 MT 158N (Montana Supreme Court, 2001)
Green v. Dix
Montana Supreme Court, 1996
Porter v. Galarneau
911 P.2d 1143 (Montana Supreme Court, 1996)
Banderob v. Estate of Banderob
Montana Supreme Court, 1996
Boland v. City of Great Falls
910 P.2d 890 (Montana Supreme Court, 1996)
Thornton v. Songstad
868 P.2d 633 (Montana Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
851 P.2d 1037, 257 Mont. 387, 50 State Rptr. 321, 1993 Mont. LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lutey-construction-the-craftsman-v-state-mont-1993.