Sornsin Construction Co. v. State

26 Cont. Cas. Fed. 83,215, 590 P.2d 125, 180 Mont. 248, 1978 Mont. LEXIS 709
CourtMontana Supreme Court
DecidedDecember 28, 1978
Docket13699
StatusPublished
Cited by9 cases

This text of 26 Cont. Cas. Fed. 83,215 (Sornsin Construction Co. v. State) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sornsin Construction Co. v. State, 26 Cont. Cas. Fed. 83,215, 590 P.2d 125, 180 Mont. 248, 1978 Mont. LEXIS 709 (Mo. 1978).

Opinion

MR. JUSTICE HARRISON

delivered the opinion of the Court.

Plaintiff, Sornsin Construction Company, brought this action in the District Court of the First Judicial District to recover damages for the alleged breech of a contract for the construction of an irrigation pump system on the Yellowstone River near Sidney, Montana. From a judgment for plaintiff, defendant State of Montana appeals.

On July 28, 1970, the Montana Water Resources Board (MWRB) (now the Department of Natural Resources and Conservation) issued an invitation for bids on a contract for the construction of an irrigation pump system project. The project entailed constructing three river pump units to pump water from the Yellowstone River and four relift pump stations to pump the water from the river units into various irrigation canals. The project was designed by the Portland, Oregon, design unit of the United States Department of Agriculture Soil Conservation Service.

Plaintiff received a number of plans, specifications and drawings from the MWRB which it used in preparing its bid. After the contract had been awarded to plaintiff and work had begun, it became apparent that a number of specifications were only approximations. Specifically, the listed elevations for the river bed in the neighborhood of 1880 feet, varied from the actual elevations as *251 much as 15 feet. These discrepancies resulted in increased costs to' plaintiff. In addition, a number of other claims developed through the course of performance of the contract which defendant refused to compensate. Plaintiff sued, and a jury trial commenced on April 12, 1976, continuing through May 6, 1976. The jury awarded damages to plaintiff in the amount of $335,328 plus $6,751.05 in costs. The original bid submitted by plaintiff and accepted by defendant had been $962,108.40.

The issues raised by appellant on appeal are:

1. Did Sornsin Construction Company assume the risk of failure of its proposed cofferdam designs?

2. Did Sornsin Construction Company assume the risk that the material to be excavated at Pump Unit 3 might not stand on a vertical cut?

3. Was the giving of Instruction No. 22 error?

4. Under the terms of this contract, was the contractor responsible for damage prior to acceptance?

5. Is a contractor who bids on an item, knowing that the quantity listed for that item is wrong, entitled to recover lost profits on the excess quantity?

6. Did Sornsin Construction Company prove that material suitable for compacted granular earth fill was not available at the site of Pump Unit 1-A?

7. May the contractor recover for extra work not recovered by a change order?

8. Did the District Court err by admitting plaintiff’s Exhibit Nos. 119, 131 and 141 in evidence?

9. Did the District Court err by refusing to admit defendant’s Exhibit No. 555 in evidence?

10. Is the verdict and judgment supported by the evidence?

The parties agree only on the statement of Issue Nos. 3, 8, 9, and 10. As a result, in the discussion of all issues, the issues will be presented in pairs to emphasize the alternative positions of the parties.

*252 Issue 1

Prior to discussion of Issue No. 1, we set forth the general principle as stated in Big Sky Livestock, Inc. v. Herzog (1976), 171 Mont. 409, 558 P.2d 1107, 1110, that the role of the reviewing court is to limit its review to whether there is substantial credible evidence to support the verdict. In so doing, it will review the evidence in the light most favorable to the prevailing party. See Davis v. Davis (1972), 159 Mont 355, 497 P.21d 315, and State Highway Commission v. Vaughan (1970), 155 Mont. 277, 470 P.2d 967.

D-1. Did Sornsin Construction Company assume the risk of failure of its proposed cofferdam designs?

P-1. Did the State breach its warranty of accuracy and sufficiency of its plans and specifications; were there “differing site conditions”; if so, did the State breach the contract by failing to pay therefore?

Defendant argues that plaintiff assumed the risk that its original cofferdam plans would not work.

Plaintiff responds by asserting that defendant breached its warranty regarding plans and specifications; there were “differing site conditions”, and defendant is estopped from so doing.

The issue involves the three river pump units. To construct these units, it was necessary to first remove the water from the area using cofferdams. The river bed turned out to be lower than plaintiff anticipated resulting in having to utilize larger and more expensive cofferdams.

The State admits the plans from which plaintiff drew its estimates were not consistent with respect to the elevation of the river bed. The State goes on to argue, however, that this discrepancy in the plans should have put plaintiff on notice to make further inquiry, pursuant to Clause 12 of the general provisions of the contract:

“12. CONDITIONS AFFECTING THE WORK.
The Contractor shall be responsible for having taken steps reasonably necessary to ascertain the nature and location of the work, *253 and the general and local conditions which can affect the work or the cost thereof. Any failure by the Contractor to do so will not relieve him from responsibility for successfully performing the work without additional expense to the Contractor Local Organization. The Contracting Local Organization assumes no responsibility for any understanding or representations concerning conditions made by any of its officers or agents prior to the execution of this contract, unless such understanding or representation are expressly stated in the contract.”

The other clause pointed out by the State along this same line is Clause 2:

“2. SPECIFICATIONS AND DRAWINGS
The Contractor shall keep on the work a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawing and specifications, the specifications shall govern. In case of discrepancy either in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at his own risk and expense. The Contracting Officer shall furnish from time to time such detail drawings and other information as he may consider necessary, unless otherwise provided.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SMC Corp. v. NJ WATER SUPPLY AUTH.
759 A.2d 1223 (New Jersey Superior Court App Division, 2000)
Lutey Construction-The Craftsman v. State
851 P.2d 1037 (Montana Supreme Court, 1993)
Beco Corp. v. Roberts & Sons Construction Co.
760 P.2d 1120 (Idaho Supreme Court, 1988)
State Highway Commission v. Brasel & Sims Construction Co.
688 P.2d 871 (Wyoming Supreme Court, 1984)
Department of Natural Resources & Conservation v. United States
30 Cont. Cas. Fed. 70,906 (Court of Claims, 1983)
Stenerson v. City of Kalispell
629 P.2d 773 (Montana Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
26 Cont. Cas. Fed. 83,215, 590 P.2d 125, 180 Mont. 248, 1978 Mont. LEXIS 709, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sornsin-construction-co-v-state-mont-1978.