The Austin Company v. The United States

314 F.2d 518, 161 Ct. Cl. 76, 1963 U.S. Ct. Cl. LEXIS 176
CourtUnited States Court of Claims
DecidedMarch 6, 1963
Docket177-61
StatusPublished
Cited by35 cases

This text of 314 F.2d 518 (The Austin Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Austin Company v. The United States, 314 F.2d 518, 161 Ct. Cl. 76, 1963 U.S. Ct. Cl. LEXIS 176 (cc 1963).

Opinion

LARAMORE, Judge.

This case is being heard on plaintiff’s motion and defendant’s cross-motion for summary judgment, and involves interpretation of a contract which plaintiff says was later found to be impossible of performance.

The Austin Company, plaintiff, entered into a contract with the United States on August 11, 1954, to design, manufacture, test and deliver a Digital Data Recording and Transcribing System, for the contract price of $177,500. This was to be a system, incorporating the use of a servo-mechanism, to gather data from remote locations aboard a ship, amplify the information so gathered, and transmit it to a central point where it was to be converted to digital form suitable for use in a computer and finally recorded on magnetic tape. No system of this kind had ever been previously manufactured or developed.

Before execution of the contract, the plaintiff reviewed the defendant’s specifications and determined that the system as so described could not be manufactured with the required precision set forth in the specifications because of the *519 inherent time lag involved in the operation of the servo-mechanism. The plaintiff then studied the problem, and on June 1, 1954 submitted a technical proposal embodying modifications of the defendant’s specifications, including an implementation designed to compensate for the characteristic error of the servomechanism. The plaintiff’s proposal also contemplated a system having greater accuracy than that outlined in the defendant’s specifications. After .conferring with the defendant’s representatives, the plaintiff. further supplemented and revised its proposal. Both the defendant and the plaintiff believed the plaintiff’s proposal sound and workable and would result in a more precise system. Therefore, the plaintiff’s proposal was incorporated into the specifications of the contract which was then signed on August 11, 1954.

The plaintiff diligently proceeded to attempt to develop and manufacture the eontracted-for system, and incurred expenditures of $290,000 to this end. However, due to a phenomenon called “jitter”, which is noise of electrical or mechanical origin caused by vibrations and other disturbances, and which sometimes occurs in highly sensitive electronic systems, it was discovered that it was impossible for plaintiff to manufacture the called-for system, as specified, with the desired precision. After granting plaintiff several extensions of time to produce the system, the defendant finally terminated the contract when it became apparent that plaintiff could not make the system as required.

The main question before the court is whether, under the termination provisions of the contract, the plaintiff is entitled to recover the expenditures, not in excess of the contract price, which it incurred in its effort to manufacture the contracted-for system. Plaintiff’s primary claim is that it is entitled to recover such expenditures because its nonperformance was, in the words of the contract, “due to causes beyond the control and without the fault or negligence of the Contractor.”

The aforementioned clause is further implemented by another provision of the contract, which reads as follows:

“(b) The Contractor shall not be liable for any excess costs if any failure to perform the contract arises out of causes beyond the control and without the fault or negligence of , the Contractor. Such causes include, but are not restricted to, acts of God or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusu-. ally severe weather, and defaults of subcontractors due to any of such causes * *

Other termination provisions of the contract provide that when the contrae^ tor’s failure to perform is due to causes beyond the control of the contractor, as determined in the above-quoted provision, the contract shall be considered terminated for the convenience of the Government and the contractor may recover its costs, not in excess of the contract price, incurred while attempting to perform.

• The facts here indicate that plaintiff's failure to perform was solely due to the fact that it was impossible for it to manufacture a workable system as set forth in the specifications, which were the plaintiff’s own design. However, the Government strongly urges that the system proposed in the contract was not impossible of being developed. Whether it was or was not, we do not know. All we do know is that plaintiff could not develop the system according to its plans. This, however, is not to say that the proposed system was impossible of manufacture. It certainly was foreseeable. For example, in the not too distant past, while perhaps foreseeable, no organization would have thought possible, or undertaken a contract to construct a device whereby a living human body could be put in orbit around the earth; nevertheless it has been accomplished. Thus, in this case, we cannot categorically say that it was or is impossible to achieve the goal called for in plaintiff’s contract.

*520 Notwithstanding this, because plaintiff could not develop the system as planned, it claims that its failure to perform was due to causes beyond its control and thus is excused under the exculpatory provisions of the contract.

The defendant disputes plaintiff’s claim that its failure of performance was covered by the exculpatory termination clause in the contract. Defendant contends that the clause in question was limited to excuse of nonperformance solely due to occurrence of extraneous contingencies of the kind specifically enumerated thereunder. Defendant cites the rule of ejusdem generis, i. e., general words in a contract are limited by particular words to things of the same kind or class, to support its contention that the words “causes beyond the control” refer solely to extraneous factors which might prevent performance, because only these kind of factors were enumerated in explanation of the causes to be considered.

We agree with the defendant that the rule of ejusdem generis is applicable to interpretation of the nonperformance clause in this contract, and operates tp restrict the clause to exculpation of nonperformance due to the kind or class of extraneous contingencies enumerated therein, i. e.: acts of God. etc. As we view the issue, if the plaintiff’s failure of performance was due to the absolute impossibility of performance inherent in the subject matter of the contract itself, and which impossibility already existed at the time the contract was entered into, plaintiff’s failure would not be excused under the exculpatory clause of the contract. See Carnegie Steel Company v. United States, 240 U.S. 156, 36 S.Ct. 342, 60 L.Ed. 576.

Furthermore, on an overall view of the facts of this case, we think that plaintiff is not entitled to recover. Plaintiff was not under any compulsion to enter into the contract. However, before it did so contract, it studied the specifications prepared by the defendant and decided they were unworkable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christopher Glass and Aluminum, Inc v. Tishman Construction Corporation of Illinois
2020 IL App (1st) 191972-U (Appellate Court of Illinois, 2020)
Short Bros. PLC v. United States
65 Fed. Cl. 695 (Federal Claims, 2005)
Ferguson Propeller, Inc. v. United States
59 Fed. Cl. 51 (Federal Claims, 2003)
Davies Precision Machining, Inc. v. United States
35 Fed. Cl. 651 (Federal Claims, 1996)
United Technologies Corp. v. United States
38 Cont. Cas. Fed. 76,452 (Federal Claims, 1992)
Hawaiian Bitumuls & Paving v. United States
38 Cont. Cas. Fed. 76,402 (Court of Claims, 1992)
Sterling Millwrights, Inc. v. United States
38 Cont. Cas. Fed. 76,316 (Court of Claims, 1992)
Aleutian Constructors v. United States
37 Cont. Cas. Fed. 76,203 (Court of Claims, 1991)
Norwood Manufacturing, Inc. v. United States
36 Cont. Cas. Fed. 75,917 (Court of Claims, 1990)
Johns-Manville Corp. v. United States
34 Cont. Cas. Fed. 75,361 (Court of Claims, 1987)
Colorado-Ute Elec. Ass'n, Inc. v. Envirotech Corp.
524 F. Supp. 1152 (D. Colorado, 1981)
Atlas Ready-Mix of Minot, Inc. v. White Properties, Inc.
306 N.W.2d 212 (North Dakota Supreme Court, 1981)
Olson Plumbing & Heating Co. v. United States
602 F.2d 950 (Court of Claims, 1979)
Sornsin Construction Co. v. State
26 Cont. Cas. Fed. 83,215 (Montana Supreme Court, 1978)
Sun Oil Co. v. United States
572 F.2d 786 (Court of Claims, 1978)
Dynalectron Corp. v. United States
518 F.2d 594 (Court of Claims, 1975)
Foster Wheeler Corp. v. United States
513 F.2d 588 (Court of Claims, 1975)
J. A. Maurer, Inc. v. United States
485 F.2d 588 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
314 F.2d 518, 161 Ct. Cl. 76, 1963 U.S. Ct. Cl. LEXIS 176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-austin-company-v-the-united-states-cc-1963.