Laeamoee, Senior Judge,
delivered the opinion of the court:
This government contract case, governed by the Wunder-lich Act, 41 U.S.C. §§ 321 and 322, is before us for the second [209]*209time. Initially, we declined to accept the recommendation of the Trial Judge that we grant summary judgment for the plaintiff contractor1 and reverse the decision of the Armed Services Board of Contract Appeals (“ASBCA” or the “Board”) dismissing plaintiff’s claim.2 Instead, by Order,3 we remanded that portion of the case then under consideration, involving review of the Board’s action, for reopening and further consideration. The part remanded contained only the claims found in the third and fourth causes of action of plaintiff’s four-count petition, as only those counts concerned review of the Board’s decision.
Now, upon further consideration of the record, the briefs and arguments of counsel, and a review of the Board’s decision after remand,4 we conclude that the Board’s action was neither arbitrary, capricious, unsupported by substantial evidence, nor contrary to law. Therefore, counts three and four of the petition, involving review of the Board’s decision, must be dismissed.
I. History of the Oase
The contract at issue herein was awarded in response to a proposal submitted by plaintiff to the Navy upon its request for proposals for the production of Talos guided missile warheads. Four preproduction sample warheads, submitted for plant inspection as required by the contract, were approved by the Navy inspector for shipment and ballistic testing to be performed at a naval installation. However, plaintiff was thereafter informed that these samples had failed the ballistic tests, and the production and delivery schedule was postponed pending an investigation. In the course thereof, the failure of the ballistic tests was attributed by the parties to the fact that in fabricating the samples, plaintiff had followed only the contract’s mandatory drawings and design [210]*210specifications, substituting its own techniques of fabrication for references in the contract to certain advisory or suggested techniques.5
The problem with the samples tested appeared to involve the configuration of the weld hinge in what was termed the rod bundle of the warhead. Basically, the warhead was composed of a hollow cylinder with an explosive cavity. The rod bundle consisted of individual square steel rods welded together at their ends to produce an item somewhat resembling an expansion wrist watch band. For various technical reasons, the manner, shape and strength of the welds were vital to the warheads’ performance.6
A second group of four preproduction samples was subsequently manufactured in accordance with the mandatory cmd advisory specifications. These were then test-fired. While plaintiff was advised that these samples were acceptable, it is now clear that they never actually satisfied the ballistic test requirements contained in the contract which, it also turns out, could never have been met consistently even through the use of both mandatory and advisory specifications. In short, [211]*211the contract was impossible to strictly perform, because the performance required exceeded that given by the product called for in the contract’s drawings and designs.
Suffice it to say, production was allowed to proceed using as a model the second set of samples. The contract was completed and the fixed payment made by the government thereunder.
Plaintiff filed a claim under the “Disputes” and “Changes” clauses7 in the contract, for increased costs it attributed to the defects in the contract specifications. The claim was denied by the contracting officer and also on appeal by the Secretary of the Navy, represented by the ASBCA. Thereafter, plaintiff filed a petition in this court under our basic jurisdictional statute 28 U.S.C. § 1491, also citing the Wunderlich Act, supra.
The petition asserts four causes of action. The first contends a breach of contract in that plaintiff was required to embark upon a research and development program to pass the ballistic requirements, and to alter its manufacturing-methods to “hand make” the warheads, while defendant knew [212]*212tihat they would not consistently pass tbe ballistic tests whatever plaintiff did, and failed to so advise plaintiff. The second cause of action alleges a breach of contract in that plaintiff was advised that its second submission of preproduction samples met ballistic test requirements, when it did not, causing plaintiff to institute and to continue extraordinary manufacturing procedures not required by the contract. The third cause alleged that the government-furnished specifications were defective in that, if followed, the warheads would not meet the ballistic test requirements of the contract, and the decision of the ASBCA to the contrary was arbitrary, capricious, not supported by substantial evidence, and legally erroneous in its interpretation of the contract. Finally, as a fourth cause of action, plaintiff alleges that the ASBCA was arbitrary, capricious and legally in error in denying plaintiff’s timely motion for reconsideration when it came to light that defendant was withholding information as to the true status of the ballistic test results.
At a pretrial conference, it was concluded that the parties should initially file cross-motions for summary judgment with the Trial Judge with respect to Counts III and IV, presenting their respective positions with regard to the Board’s decision, without prejudice to plaintiff’s right to claim entitlement to a trial on the counts alleging breach of contract, should they remain after the decision on the motion. Cross-motions were thereupon filed and briefed.
As indicated above, the Trial Judge recommended that we grant plaintiff’s motion and remand the case to the ASBCA for a determination of the amount of the equitable adjustment to which plaintiff was to be entitled. Upon review pursuant to Buie 54 (b), we remanded the case, but for a different purpose. Our Order directed that the case be reopened by the Board, certain new evidence admitted8 and, finally, that the case be reconsidered. Upon remand, in a second opinion, the Board again denied plaintiff’s claim.
[213]*213Following this second Board decision, 'both parties filed with the court the notices required by Buie 150(d). Plaintiff urged further action by the court, while defendant was content to let the decision of the Board stand.
[214]*214In response to these notices, the Trial Judge ordered plaintiff to file a motion under Rule 141 (b) requesting the court to adopt, with some modifications, the Trial Judge’s previously recommended opinion. The case is, therefore, before us now on the parties’ Rule 150(d) cross-notices, which are deemed to incorporate and reassert their prior cross-motions for summary judgment, and plaintiff’s Rule 141(b) motion.
Free access — add to your briefcase to read the full text and ask questions with AI
Laeamoee, Senior Judge,
delivered the opinion of the court:
This government contract case, governed by the Wunder-lich Act, 41 U.S.C. §§ 321 and 322, is before us for the second [209]*209time. Initially, we declined to accept the recommendation of the Trial Judge that we grant summary judgment for the plaintiff contractor1 and reverse the decision of the Armed Services Board of Contract Appeals (“ASBCA” or the “Board”) dismissing plaintiff’s claim.2 Instead, by Order,3 we remanded that portion of the case then under consideration, involving review of the Board’s action, for reopening and further consideration. The part remanded contained only the claims found in the third and fourth causes of action of plaintiff’s four-count petition, as only those counts concerned review of the Board’s decision.
Now, upon further consideration of the record, the briefs and arguments of counsel, and a review of the Board’s decision after remand,4 we conclude that the Board’s action was neither arbitrary, capricious, unsupported by substantial evidence, nor contrary to law. Therefore, counts three and four of the petition, involving review of the Board’s decision, must be dismissed.
I. History of the Oase
The contract at issue herein was awarded in response to a proposal submitted by plaintiff to the Navy upon its request for proposals for the production of Talos guided missile warheads. Four preproduction sample warheads, submitted for plant inspection as required by the contract, were approved by the Navy inspector for shipment and ballistic testing to be performed at a naval installation. However, plaintiff was thereafter informed that these samples had failed the ballistic tests, and the production and delivery schedule was postponed pending an investigation. In the course thereof, the failure of the ballistic tests was attributed by the parties to the fact that in fabricating the samples, plaintiff had followed only the contract’s mandatory drawings and design [210]*210specifications, substituting its own techniques of fabrication for references in the contract to certain advisory or suggested techniques.5
The problem with the samples tested appeared to involve the configuration of the weld hinge in what was termed the rod bundle of the warhead. Basically, the warhead was composed of a hollow cylinder with an explosive cavity. The rod bundle consisted of individual square steel rods welded together at their ends to produce an item somewhat resembling an expansion wrist watch band. For various technical reasons, the manner, shape and strength of the welds were vital to the warheads’ performance.6
A second group of four preproduction samples was subsequently manufactured in accordance with the mandatory cmd advisory specifications. These were then test-fired. While plaintiff was advised that these samples were acceptable, it is now clear that they never actually satisfied the ballistic test requirements contained in the contract which, it also turns out, could never have been met consistently even through the use of both mandatory and advisory specifications. In short, [211]*211the contract was impossible to strictly perform, because the performance required exceeded that given by the product called for in the contract’s drawings and designs.
Suffice it to say, production was allowed to proceed using as a model the second set of samples. The contract was completed and the fixed payment made by the government thereunder.
Plaintiff filed a claim under the “Disputes” and “Changes” clauses7 in the contract, for increased costs it attributed to the defects in the contract specifications. The claim was denied by the contracting officer and also on appeal by the Secretary of the Navy, represented by the ASBCA. Thereafter, plaintiff filed a petition in this court under our basic jurisdictional statute 28 U.S.C. § 1491, also citing the Wunderlich Act, supra.
The petition asserts four causes of action. The first contends a breach of contract in that plaintiff was required to embark upon a research and development program to pass the ballistic requirements, and to alter its manufacturing-methods to “hand make” the warheads, while defendant knew [212]*212tihat they would not consistently pass tbe ballistic tests whatever plaintiff did, and failed to so advise plaintiff. The second cause of action alleges a breach of contract in that plaintiff was advised that its second submission of preproduction samples met ballistic test requirements, when it did not, causing plaintiff to institute and to continue extraordinary manufacturing procedures not required by the contract. The third cause alleged that the government-furnished specifications were defective in that, if followed, the warheads would not meet the ballistic test requirements of the contract, and the decision of the ASBCA to the contrary was arbitrary, capricious, not supported by substantial evidence, and legally erroneous in its interpretation of the contract. Finally, as a fourth cause of action, plaintiff alleges that the ASBCA was arbitrary, capricious and legally in error in denying plaintiff’s timely motion for reconsideration when it came to light that defendant was withholding information as to the true status of the ballistic test results.
At a pretrial conference, it was concluded that the parties should initially file cross-motions for summary judgment with the Trial Judge with respect to Counts III and IV, presenting their respective positions with regard to the Board’s decision, without prejudice to plaintiff’s right to claim entitlement to a trial on the counts alleging breach of contract, should they remain after the decision on the motion. Cross-motions were thereupon filed and briefed.
As indicated above, the Trial Judge recommended that we grant plaintiff’s motion and remand the case to the ASBCA for a determination of the amount of the equitable adjustment to which plaintiff was to be entitled. Upon review pursuant to Buie 54 (b), we remanded the case, but for a different purpose. Our Order directed that the case be reopened by the Board, certain new evidence admitted8 and, finally, that the case be reconsidered. Upon remand, in a second opinion, the Board again denied plaintiff’s claim.
[213]*213Following this second Board decision, 'both parties filed with the court the notices required by Buie 150(d). Plaintiff urged further action by the court, while defendant was content to let the decision of the Board stand.
[214]*214In response to these notices, the Trial Judge ordered plaintiff to file a motion under Rule 141 (b) requesting the court to adopt, with some modifications, the Trial Judge’s previously recommended opinion. The case is, therefore, before us now on the parties’ Rule 150(d) cross-notices, which are deemed to incorporate and reassert their prior cross-motions for summary judgment, and plaintiff’s Rule 141(b) motion.
II. The Third, and Fourth Causes of Action
Counts III and IV of the petition request Wunderlich Act review of the decision of the Board denying plaintiff’s claim. Count IV requires little, if any, further consideration. As noted above, it alleges that the Board was arbitrary in refusing to reopen plaintiff’s case, admit new evidence and reconsider the matter, and the Board, under our instructions upon remand, reopened the case, admitted the new evidence, reconsidered the case and rendered a second decision.
The merits of the case, insofar as Wunderlich Act review is requested, are actually found in the third cause of action. Consideration of this count’s charge that the Board erroneously interpreted the subject contract requires further scrutiny of the contract terms.
The contract required that the warheads be “manufactured in strict accordance with the Bureau of Naval Weapons List of Drawings L.D. 53451-5, Revision A, and the drawings and specifications listed thereon.” The provision continued :
* * * The following list of drawings and specifications shall be applicable to the warhead assemblies to be furnished hereunder.
* * * # *t
[215]*215Sheet Eevision B (Confidential).
Sheet Eevision B
Drawing 2176094, Sheet 3, Eevision A (Confidential).
* * * . * *
[The actual list included numerous other drawings] Specification O.S. 11705 (Confidential).9
Drawing 2176094, Sheet 3, contained details “P” and “E”, which provided a representation of the weld hinge in the rod bundle referred to earlier. It will be remembered that this weld hinge was identified by the parties as the source of the unsatisfactory ballistic performance of plaintiff’s first set of preproduction samples.
There is considerable evidence in the record that plaintiff relied entirely upon its own technology and details “P” and “E” in fabricating the weld hinges in its first set of pre-production samples even though drawing 2176094 also referred, in a note, to a document entitled O.D. 20843, containing a suggested technique of fabrication. O.D. 20843 was introduced with the following preamble:
1.1 Purpose. This NAYWEPS Ordnance Data publication outlines instructions which are intended to serve as a guide for the fabrication and preparation of the rod bundle used on the warhead * * *.
While it is clear from the record, and the Board so found, that neither of the parties regarded O.D. 20843, or the drawings accompanying it, as mandatory in the same sense as other contract requirements,10 at the same time, we infer that this data was supplied with the intention of delineating [216]*216methods and designs which would produce a product acceptable to the government, if strictly followed by the contractor. Significantly, O.D. 20843 was entitled “Advisory Instructions for the Fabrication of the Bod Bundle * *
III. The (Controversy
Plaintiff urges that because the government-furnished specifications and drawings enumerated above were defective it incurred additional costs within the purview of the “Changes” clause in the contract. The additional expenses claimed include (1) the costs associated with manufacturing an unnecessary first set of four preproduetion samples, which were rejected, and (2) extra costs incurred in finally performing the contract in accordance with the more costly advisory welding specifications, when this did not produce a warhead which satisfied the contract’s ballistic requirements any more readily than did the welding technique plaintiff used to fabricate the first set of preproduction samples.
Plaintiff relies upon our holding in Hol-Gar Manufacturing Corp v. United States, 175 Ct. Cl. 518, 360 F. 2d 634 (1966), hereinafter “Hoi-Gar”. In that case, a contractor sued to recover additional costs it incurred in attempting to perform a contract to manufacture electric generator sets in accordance with specifications defectively drawn by the government. A change order amending the specifications had later been issued and accepted by the contractor with a reservation of its right to submit a claim for extra costs incurred in having first attempted to perform under the original specifications. In deciding the case when it came to this court after the ASBCA had denied the contractor’s claim, we held that where a change is required by reason of defective specifications or drawings for which the government is responsible, a contractor is entitled to an equitable adjustment to compensate not only for any extra costs occasioned by the change, but also for extra costs incurred in attempting to comply with the originally defective specifications.
We conclude, however, that plaintiff’s reliance on our holding in Hoi-Gar is misplaced. For reasons which follow, this [217]*217is so even though the facts here reveal that the government furnished defective specifications, and we deem a constructive change in the contract to have occurred when the ballistic test requirements were relaxed by the government to conform to the capability of the product to be manufactured in accordance with the existing specifications, both mandatory and advisory. And we are not unmindful of such cases as LaCrosse Garment Mfg. Co. v. United States, 193 Ct. Cl. 168, 432 F. 2d 1377 (1970); L. W. Foster Sportswear Co. v. United States, 186 Ct. Cl. 499, 405 F. 2d 1285 (1969), and cases therein cited, which stand for the proposition that a contractor is entitled to an equitable adjustment under the “Changes” clause for increased costs of performance due to defective specifications. But we have laid emphasis, in the preceding sentence, on the word due because of the three vital elements — (1) defective specifications, (2) causation, and (3) extra costs — in this case, as will appear, the element of causation is absent.
For purposes of analysis, we will examine plaintiff’s claim (presumably grounded upon the constructive change mentioned above) in two separate segments, taking up pre-change additional costs first. These costs were the result of plaintiff’s having produced an extra and perhaps unnecessary first set of four preproduction samples.
In Hoi-Gar, pre-change extra costs were awarded which were the direct result of the contractor having explicitly followed defective specifications furnished by the government but which, even though conscientiously followed, produced an unacceptable result. In the case at hand, plaintiff ignored a portion of the technical material furnished by the government, that is to say certain of the advisory specifications, and elected to employ welding techniques of its own in fabricating the initial set of preproduction samples. We reason that in rejecting the teaching of the advisories plaintiff assumed the risk that its own techniques would not yield an acceptable result. (No doubt, in return for anticipating the assumption of the risk, plaintiff had been able to place itself in an advantageous bidding position in its fixed-price proposal because [218]*218the advisories were evidently more costly to follow than the method plaintiff had planned to pursue.)11
Thus, the critical factual premise supporting our holding in Hoi-Gar, that the government’s specifications were fol-loived by the contractor without deviation, is not present in the case before us now. Plaintiff is not, therefore, entitled to reimbursement for its pre-change additional costs because such were incurred only as the direct and proximate result of plaintiff’s attempt to produce in accordance with its own less costly techniques, rather than the government-furnished design advisories.
The ASBCA, in its second decision, also considered the risk-shifting effect of plaintiff’s failure to first follow the advisories, and we are in agreement that:
* * * appellant [plaintiff] was on notice of the potential need to follow them and, when it chose not to do so initially, it assumed the risk that its own production methods might not work.
The above-quoted paragraph is generally in accord with and supported 'by the ratio decidendi of several of our decisions. In Austin Co. v. United States, 161 Ct. Cl. 76, 314 F. 2d 518, cert. denied, 375 U.S. 830 (1963), we assumed that plaintiff’s failure to perform was due solely to the fact that it was impossible to do so under the specifications. However, the latter were proposed by the plaintiff after it had reviewed defendant’s specifications and found them unworkable. We held that plaintiff, having promised to perform under its own substituted specifications, fully assumed the risk of impossibility of performance. As the government was responsible for losses due to its own specifications if they were defective, the converse should apply to the plaintiff. Accord, J. A. Maurer, Inc. v. United States, 202 Ct. Cl. 813, 485 F. 2d 588 (1973); [219]*219Bethlehem Corp. v. United States, 199 Ct. Cl. 247, 462 F. 2d 1400 (1972).12
We turn, now to the subject of post-change additional costs. It will be remembered that these allegedly resulted from the government’s insistence that plaintiff fabricate in accordance with the more costly advisory design specifications, even after the performance requirements of the contract had been constructively relaxed when it became known that they could not have been consistently met with the use of the advisories.
We must reject plaintiff’s argument that its eventual use of the advisories in fabricating the full number of warheads required by the contract called for an equitable adjustment. This we do because we cannot agree that the advisories were ever employed by plaintiff in a manner not contemplated by the parties db initio. The advisories were all part and parcel of the contract from its inception.
Moreover, the record does not support plaintiff’s conclusion that the government “insisted” on compliance with the advisories. Apparently, when the initial set of four preproduction samples was found unacceptable, both parties thought that if the advisory welding techniques had been used, the required ballistic performance might have been achieved. For that reason, plaintiff then elected to follow the advisories in producing its second set of preproduction samples. When this second set of samples was tested, it became clear to both plaintiff and the government that the ballistic specifications would never be met under the contract’s original design specifications, both mandatory and advisory. The performance requirements were, therefore, necessarily relaxed. Plaintiff continued to perform the contract by fabricating the warheads in accordance with the advisories. We conclude not that the advisories were “insisted” upon, but that plaintiff sought by their use to transfer to the government the risk that, when finally manufactured, the product would not ade[220]*220quately perform even under tbe relaxed ballistic standards. This option, all along contractually available, evidently became plaintiff’s safest course and, as such, its choice.
It must also be remembered that plaintiff was fully cognizant after the ballistic tests on the second set of four preproduction samples, and before the start of actual production under the contract, that the government stood ready to accept warhead units produced strictly in accordance with the advisories even if such were not capable of satisfying the original or modified ballistic requirements of the contract.
It was with that in mind that plaintiff manufactured the warheads, the government accepted them, and the fixed price of the contract was paid.
Plaintiff, therefore, in effect urges us to grant it an equitable price adjustment for having produced in a manner not only permissible under the original design specifications and drawings, but suggested by them. It is plain that to do so would, as the ASBCA found, be contrary to both logic and the pertinent law. Simply stated, we find that the costs for which plaintiff seeks reimbursement were not extra costs incurred as a consequence of the constructive change made in the contract.
The Board, in its second decision, summarized the point thus:
If the Government had not effectively changed the ballistic requirements so that the original requirements became immaterial, or if it had misled appellant into incurring extra costs in an impossible task while misrepresenting the ballistic test results, we would have a different case. Here appellant knew or should have known from the start that it might have to use the advisory specifications to achieve a successful result. We do not believe it is entitled to extra costs for having done just that after having tried its own methods and failed.
IV. Conclusion
Accordingly, for the above reasons, plaintiff’s motion under Buie 141 (b) is denied. Defendant’s cross-motion for summary judgment (incorporated and reasserted in its Buie 150(d) cross-notice) is granted. Plaintiff’s motion for summary [221]*221judgment (likewise incorporated and reasserted in its Rule 150(d) notice) is denied.
Counts III and IY of the petition are dismissed.