Gulf + Western Precision Engineering Co. v. United States

543 F.2d 125, 22 Cont. Cas. Fed. 80,736, 211 Ct. Cl. 207, 1976 U.S. Ct. Cl. LEXIS 163
CourtUnited States Court of Claims
DecidedOctober 20, 1976
DocketNo. 335-70
StatusPublished
Cited by3 cases

This text of 543 F.2d 125 (Gulf + Western Precision Engineering Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf + Western Precision Engineering Co. v. United States, 543 F.2d 125, 22 Cont. Cas. Fed. 80,736, 211 Ct. Cl. 207, 1976 U.S. Ct. Cl. LEXIS 163 (cc 1976).

Opinions

Laeamoee, Senior Judge,

delivered the opinion of the court:

This government contract case, governed by the Wunder-lich Act, 41 U.S.C. §§ 321 and 322, is before us for the second [209]*209time. Initially, we declined to accept the recommendation of the Trial Judge that we grant summary judgment for the plaintiff contractor1 and reverse the decision of the Armed Services Board of Contract Appeals (“ASBCA” or the “Board”) dismissing plaintiff’s claim.2 Instead, by Order,3 we remanded that portion of the case then under consideration, involving review of the Board’s action, for reopening and further consideration. The part remanded contained only the claims found in the third and fourth causes of action of plaintiff’s four-count petition, as only those counts concerned review of the Board’s decision.

Now, upon further consideration of the record, the briefs and arguments of counsel, and a review of the Board’s decision after remand,4 we conclude that the Board’s action was neither arbitrary, capricious, unsupported by substantial evidence, nor contrary to law. Therefore, counts three and four of the petition, involving review of the Board’s decision, must be dismissed.

I. History of the Oase

The contract at issue herein was awarded in response to a proposal submitted by plaintiff to the Navy upon its request for proposals for the production of Talos guided missile warheads. Four preproduction sample warheads, submitted for plant inspection as required by the contract, were approved by the Navy inspector for shipment and ballistic testing to be performed at a naval installation. However, plaintiff was thereafter informed that these samples had failed the ballistic tests, and the production and delivery schedule was postponed pending an investigation. In the course thereof, the failure of the ballistic tests was attributed by the parties to the fact that in fabricating the samples, plaintiff had followed only the contract’s mandatory drawings and design [210]*210specifications, substituting its own techniques of fabrication for references in the contract to certain advisory or suggested techniques.5

The problem with the samples tested appeared to involve the configuration of the weld hinge in what was termed the rod bundle of the warhead. Basically, the warhead was composed of a hollow cylinder with an explosive cavity. The rod bundle consisted of individual square steel rods welded together at their ends to produce an item somewhat resembling an expansion wrist watch band. For various technical reasons, the manner, shape and strength of the welds were vital to the warheads’ performance.6

A second group of four preproduction samples was subsequently manufactured in accordance with the mandatory cmd advisory specifications. These were then test-fired. While plaintiff was advised that these samples were acceptable, it is now clear that they never actually satisfied the ballistic test requirements contained in the contract which, it also turns out, could never have been met consistently even through the use of both mandatory and advisory specifications. In short, [211]*211the contract was impossible to strictly perform, because the performance required exceeded that given by the product called for in the contract’s drawings and designs.

Suffice it to say, production was allowed to proceed using as a model the second set of samples. The contract was completed and the fixed payment made by the government thereunder.

Plaintiff filed a claim under the “Disputes” and “Changes” clauses7 in the contract, for increased costs it attributed to the defects in the contract specifications. The claim was denied by the contracting officer and also on appeal by the Secretary of the Navy, represented by the ASBCA. Thereafter, plaintiff filed a petition in this court under our basic jurisdictional statute 28 U.S.C. § 1491, also citing the Wunderlich Act, supra.

The petition asserts four causes of action. The first contends a breach of contract in that plaintiff was required to embark upon a research and development program to pass the ballistic requirements, and to alter its manufacturing-methods to “hand make” the warheads, while defendant knew [212]*212tihat they would not consistently pass tbe ballistic tests whatever plaintiff did, and failed to so advise plaintiff. The second cause of action alleges a breach of contract in that plaintiff was advised that its second submission of preproduction samples met ballistic test requirements, when it did not, causing plaintiff to institute and to continue extraordinary manufacturing procedures not required by the contract. The third cause alleged that the government-furnished specifications were defective in that, if followed, the warheads would not meet the ballistic test requirements of the contract, and the decision of the ASBCA to the contrary was arbitrary, capricious, not supported by substantial evidence, and legally erroneous in its interpretation of the contract. Finally, as a fourth cause of action, plaintiff alleges that the ASBCA was arbitrary, capricious and legally in error in denying plaintiff’s timely motion for reconsideration when it came to light that defendant was withholding information as to the true status of the ballistic test results.

At a pretrial conference, it was concluded that the parties should initially file cross-motions for summary judgment with the Trial Judge with respect to Counts III and IV, presenting their respective positions with regard to the Board’s decision, without prejudice to plaintiff’s right to claim entitlement to a trial on the counts alleging breach of contract, should they remain after the decision on the motion. Cross-motions were thereupon filed and briefed.

As indicated above, the Trial Judge recommended that we grant plaintiff’s motion and remand the case to the ASBCA for a determination of the amount of the equitable adjustment to which plaintiff was to be entitled. Upon review pursuant to Buie 54 (b), we remanded the case, but for a different purpose. Our Order directed that the case be reopened by the Board, certain new evidence admitted8 and, finally, that the case be reconsidered. Upon remand, in a second opinion, the Board again denied plaintiff’s claim.

[213]*213Following this second Board decision, 'both parties filed with the court the notices required by Buie 150(d). Plaintiff urged further action by the court, while defendant was content to let the decision of the Board stand.

[214]*214In response to these notices, the Trial Judge ordered plaintiff to file a motion under Rule 141 (b) requesting the court to adopt, with some modifications, the Trial Judge’s previously recommended opinion. The case is, therefore, before us now on the parties’ Rule 150(d) cross-notices, which are deemed to incorporate and reassert their prior cross-motions for summary judgment, and plaintiff’s Rule 141(b) motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
Fru-Con Construction Corp. v. United States
42 Cont. Cas. Fed. 77,399 (Federal Claims, 1998)
Gulf + Western Precision Engineering Co.
24 Cont. Cas. Fed. 82,292 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
543 F.2d 125, 22 Cont. Cas. Fed. 80,736, 211 Ct. Cl. 207, 1976 U.S. Ct. Cl. LEXIS 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-western-precision-engineering-co-v-united-states-cc-1976.