United Technologies Corp. v. United States

38 Cont. Cas. Fed. 76,452, 27 Fed. Cl. 393, 1992 U.S. Claims LEXIS 157, 1992 WL 379674
CourtUnited States Court of Federal Claims
DecidedDecember 18, 1992
DocketNo. 401-89C
StatusPublished
Cited by8 cases

This text of 38 Cont. Cas. Fed. 76,452 (United Technologies Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Technologies Corp. v. United States, 38 Cont. Cas. Fed. 76,452, 27 Fed. Cl. 393, 1992 U.S. Claims LEXIS 157, 1992 WL 379674 (uscfc 1992).

Opinion

OPINION

SMITH, Chief Judge:

This matter is before the court on plaintiffs Motion for Summary Judgment on the government’s $49.5 million counterclaim. This ease arises out of a series of contracts between the United States Army and plaintiff, the Sikorsky Aircraft Division of United Technologies Corporation (Sikorsky), for the design and manufacture of the UH-60A Black Hawk Helicopter. The government contends that Sikorsky’s design for the helicopter’s main rotor spindles1 was defective. Plaintiff asserts that defendant cannot establish that the spindles were defective because the spindles have the requisite “fatigue” life under the contractually prescribed measurement methodology.2 Alternatively, plaintiff contends that the government is not entitled to damages because the spindles were produced under manufacturing contracts according to the design qualified by defendant under the prior development contract. Upon full consideration of the parties’ briefs, oral arguments, supporting documentation, and the caselaw, the court concludes that plaintiff must prevail on its motion.

PACTS

On December 30, 1971, the government issued a Request for Proposals (RFP) for a cost reimbursement contract to design and develop the Black Hawk Helicopter. Under the RFP, the winning bidder was to prepare an airworthiness qualification specification, or “substantiation methodology”, by which it could demonstrate compliance with the RFP’s general specifications.3 The RFP required that certain components of the helicopter, including the spindles, have a fatigue life of 5,000 hours. In determining the spindles’ fatigue life, two primary factors were considered: (1) the expected ground and flight conditions to which the spindle would be subjected during its life (the “usage spectrum”), and (2) the results of S-N testing, which involved the charting of stress (S) versus the number of cycles to failure (N). The RFP further specified that six specimens of each component be tested. After qualification testing was completed, the results were to be compiled and submitted in a report to the government.

The RFP also provided for a two-phase development contract. The first phase involved a 36 month period in which each contractor would design, develop, fabricate, test and qualify its prototype aircraft and aircraft system in accordance with the RFP’s general specifications. The government was then allotted one year in which to competitively test the prototypes and select a contractor to manufacture the aircraft under subsequent production contracts. Pursuant to the development contract’s maturity phase option4, the selected contractor would continue any necessary development engineering, including fatigue testing, for 22 months prior to entering into the production contract.

On August 30, 1972, Sikorsky was awarded Development Contract DAAJ01-73-C-0006 on a cost reimbursement basis. The contract contained the standard inspection clause which limited plaintiff’s liability for deficiencies discovered to six months after government acceptance. However, Sikorsky remained liable at any time for failure to comply with contract requirements, if such failure was (1) due to fraud, lack of good will or willful misconduct of [395]*395plaintiff’s officers, directors or key supervisory employees or (2) caused by an individual employee after any supervisory personnel had reasonable grounds to suspect such employee was habitually careless or unqualified.5

Sikorsky was responsible for the aircraft design only until the competitive stage of the development contract began. After that, the government assumed design responsibility.6 In the PIDS established by plaintiff, the spindles were to have fatigue lives of 10,000 hours instead of the 5,000 contemplated by the RFP. The development contract required the spindles to meet the 10,000 hour fatigue life in accordance with the substantiation methodology established in Sikorsky Engineering Report (“SER”)-70100, which set forth the S-N curve and usage spectrum plaintiff would apply in testing the spindles.7 The government approved SER-70100 on November 18, 1977. Plaintiff contends that it fatigue tested six spindles and submitted SER-70116 to the government, substantiating that the spindles exceeded the 10,000 hour requirement. Plaintiff also asserts that it submitted SER-70116 to the government on April 9, 1980, and that defendant accepted the test results on July 22, 1980.8

Plaintiff was awarded the first Black Hawk production contract in 1977 during the maturity phase of the development contract.9 This contract was on a fixed-price incentive fee basis with three one-year production options. The contract contained two clauses which plaintiff contends are the only basis upon which the government can rely for recovery. The first required Sikorsky to correct any deficiencies discovered by either the government or plaintiff, but was limited in scope:

This clause shall apply only to those deficiencies discovered by either the Government or the contractor within 24 months after acceptance of supplies or services called for during the first year production; within eighteen months after acceptance of the supplies or services called for during the second year (option) production; within twelve months after acceptance of the supplies or services called for during the third year (option) production; and within six months after acceptance of the supplies or services called for thereafter under this contract by the Government.10

“Deficiency” was defined as including design defects under any prior contract which were the responsibility of the contractor.

The second clause is the standard fixed price incentive supply contract inspection clause which provides:

All supplies shall be subject to inspection and test by the Government ... [and] [i]n case any supplies or lots of supplies are defective in material or workmanship or otherwise not in conformity with the requirements of this contract, the Government shall have the right either to reject them ... or to require their correction____
[396]*396Except as otherwise provided in this contract, acceptance shall be conclusive except as regards latent defects, fraud, or such gross mistakes as amount to fraud.11

On August 13, 1981, during the fourth and last option year of the first production contract, the government issued Contract Modification P00357 which required Sikorsky to increase the spindles’ diameter. This modification called for plaintiff to fatigue test four 103 spindles, but did not require Sikorsky to develop a new substantiation methodology. The modification also did not specify a different usage spectrum from the one contained in the first production contract PIDS. With the government’s approval, however, plaintiff substantiated the new spindles using a new and more rigorous usage spectrum (the “MOD A” spectrum) and revised strength data. Sikorsky reported the results of its tests on the four 103 spindles to the government. Under the new substantiation methodology, the spindles had a fatigue life of 6,700 hours. The government accepted the spindles.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Lee Lewis Construction, Inc. v. United States
54 Fed. Cl. 88 (Federal Claims, 2002)
Perkin-Elmer Corp. v. United States
47 Fed. Cl. 672 (Federal Claims, 2000)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)
Spandome Corp. v. United States
40 Cont. Cas. Fed. 76,738 (Federal Claims, 1995)
United Technologies Corp. v. United States
39 Cont. Cas. Fed. 76,696 (Federal Claims, 1994)
M.A. Mortenson Co. v. United States
39 Cont. Cas. Fed. 76,555 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,452, 27 Fed. Cl. 393, 1992 U.S. Claims LEXIS 157, 1992 WL 379674, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-technologies-corp-v-united-states-uscfc-1992.