Perkin-Elmer Corp. v. United States

47 Fed. Cl. 672, 2000 U.S. Claims LEXIS 191, 2000 WL 1429499
CourtUnited States Court of Federal Claims
DecidedSeptember 26, 2000
DocketNo. 98-378C
StatusPublished
Cited by2 cases

This text of 47 Fed. Cl. 672 (Perkin-Elmer Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perkin-Elmer Corp. v. United States, 47 Fed. Cl. 672, 2000 U.S. Claims LEXIS 191, 2000 WL 1429499 (uscfc 2000).

Opinion

OPINION

FIRESTONE, Judge.

This matter comes before the court on plaintiffs motion for summary judgment. In this action, plaintiff, Perkin-Elmer Corp. (“Perkin-Elmer”), appeals the final decision of the Air Force’s Contracting Officer (“CO”) demanding $8,315,253.80 plus interest for damages due to an alleged latent defect in certain wear metal analyzing instruments Perkin-Elmer manufactured for the Air Force.1 23Perkin-Elmer contends in its motion for summary judgment that the Air Force waited too long to revoke acceptance of the instruments under the applicable Federal Acquisition Regulations (“FAR”) and case law, which require that action be taken within a “reasonable time” after the latent defects have become known. It is not disputed that the Ah' Force determined that the product was defective in 1991, but did not issue a final CO decision revoking acceptance until 1997. The Air Force argues that its actions in connection with the revocation were reasonable and timely. For the reasons that follow, the court concludes that under the undisputed facts of this case the [673]*673Air Force did not act within a “reasonable time.” Accordingly, Perkin-Elmer’s motion for summary judgment is GRANTED.

FACTS

The facts are not in dispute and may be summarized as follows. In 1982 the Air Force awarded Perkin-Elmer an initial contract for the design and development of a portable wear metal analyzer (“PWMA”) prototype. PWMAs are instruments designed to evaluate the condition of aircraft engines by analyzing the concentration of various metals in the engines’ oil. PWMAs allow the Air Force to determine which engine parts are deteriorating and, therefore, need to be replaced. At the time of the contract, the Air Force needed a fairly large machine to conduct the analysis. The value of a portable analyzer is that it can be carried by one person and used in the field.

Following design of the prototype PWMA, the Air Force in 1986 awarded Perkin-Elmer contract no. F41608-86-D-0273, for the production of the PWMAs. Between 1988 and 1990, the Air Force took delivery of 133 PWMAs. Although the Air Force had accepted the PWMAs, problems with the instruments surfaced in 1991, when the Air Force tested them prior to deployment. These concerns led the Air Force to hire the Southwest Research Institute (“SwRI”) of San Antonio, Texas to test ten of PerkinElmer’s PWMAs. In September 1991, SwRI issued its report in which it concluded that all ten of the PWMAs it tested failed to meet the contractual requirements. In particular, SwRI noted that the PWMAs did not produce accurate results and, thus, could not be relied upon in the field.

In December 1991 and again in January 1992, the Aii’ Force wrote to Perkin-Elmer stating that the PWMAs “cannot be used to satisfy the Government’s requirements,” and that the Air Force might exercise its “contractual remedies” against Perkin-Elmer. During 1993, the division of Perkin-Elmer that produced the PWMAs was purchased by Orbital Science Corp. (“Orbital Science”). Subsequently, the Air Force, Perkin-Elmer, and Orbital Science attempted to settle the dispute over the PWMAs by having Orbital Science buy back the PWMAs from the Air Force. These settlement efforts eventually failed.

During this same time period, the Air Force Office of Special Investigation began investigating whether to pursue a possible False Claims Act, 31 U.S.C. §§ 3729-3731 (1994), case against Perkin-Elmer based on the problems concerning the PWMAs. By March 27, 1995, however, the government had decided not to file a False Claims Act ease against Perkin-Elmer. Perkin-Elmer was notified of the government’s decision not to file the False Claims Act case some time before March 1995.

More than one year later, on May 10,1996, the Air Force issued a demand letter to Perkin-Elmer revoking acceptance of the PWMAs and seeking $8,315,253.80. The letter stated that the demand was based on “[p]ost-acceptance testing [that] was conducted for the Air Force by Southwest Research Institute (SwRI) during the period 7 June through 30 September 1991.” The demand letter restated SwRI’s 1991 conclusion that “[p]ost delivery testing of a sample of ten Portable Wear Metal Analyzer (PWMA) spectrometers delivered under the contract resulted in the finding that the units do not meet contract requirements____” Thereafter, according to the CO’s assertion in her final decision, an attempt to re-open settlement negotiations in June 1996 failed.

More than another year passed until July 1997, when the Air Force hired Stephen W. Mabie, an engineering consultant, to pinpoint the reason for the variation in test results between the Air Force’s testing and PerkinElmer’s testing. The expert concluded that Perkin-Elmer had used the wrong testing protocol. After receiving the expert report, the CO issued a final decision on October 25, 1997, alleging that Perkin-Elmer had “unilaterally changed the methods used during Acceptance Testing” and had used “a non-compliant oil injector during testing.” The letter stated:

My view, as Contracting Officer, is that none of the PWMAs delivered by PerkinElmer met the requirement of the contract. Perkin-Elmer’s proposal promised to comply with existing drawings and sup[674]*674ply a pre-production prototype. Approval by the Government Quality Assurance Evaluator (QAE) was based on a data package which included certificates of conformance and test data. Subsequent to acceptance, extraordinary Government testing disclosed that the PWMAs do not perform in accordance with contractual requirements. Further, investigation has disclosed that Perkin-Elmer unilaterally changed the methods used during Acceptance Testing to ensure that it obtained passing results.
Information developed by the Government led to concerns that the PWMAs you delivered to the Air Force did not meet contract specifications. Post-acceptance testing was conducted for the Air Force by Southwest Research Institute (SwRI) during the period 7 June thi’ough 30 September 1991. Testing of a sample of ten Portable Wear Metal Analyzer (PWMA) spectrometers delivered under the contract resulted in the finding that the units do not meet contract requirements in the areas of repeatability, and accuracy.

The CO reiterated her demand for the amount of $8,315,253.80 “for the debt owed by Perkin Elmer concerning this matter” and informed Perkin-Elmer that it could appeal her decision to the Armed Services Board of Contract Appeals or the Court of Federal Claims. Plaintiff filed the present action on April 17, 1998. Defendant filed its counterclaim on November 30,1998.

The parties conducted discovery regarding whether the government’s revocation was made in a reasonable time. Thereafter, plaintiff moved for summary judgment. Briefing was completed and oral argument was heard on September 21, 2000.

DISCUSSION

I. Summary Judgment

Summary judgment is appropriate where there is no genuine issue of material fact, and the moving party is entitled to judgment as a matter of law. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Mingus Constructors, Inc. v. United States, 812 F.2d 1387

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee Lewis Construction, Inc. v. United States
54 Fed. Cl. 88 (Federal Claims, 2002)
Lion Raisins, Inc. v. United States
51 Fed. Cl. 238 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
47 Fed. Cl. 672, 2000 U.S. Claims LEXIS 191, 2000 WL 1429499, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perkin-elmer-corp-v-united-states-uscfc-2000.