United Technologies Corp. v. United States

39 Cont. Cas. Fed. 76,696, 31 Fed. Cl. 698, 1994 U.S. Claims LEXIS 157, 1994 WL 441088
CourtUnited States Court of Federal Claims
DecidedAugust 15, 1994
DocketNo. 401-89C
StatusPublished
Cited by1 cases

This text of 39 Cont. Cas. Fed. 76,696 (United Technologies Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Technologies Corp. v. United States, 39 Cont. Cas. Fed. 76,696, 31 Fed. Cl. 698, 1994 U.S. Claims LEXIS 157, 1994 WL 441088 (uscfc 1994).

Opinion

[699]*699 OPINION

SMITH, Chief Judge.

This case comes before the court on defendant’s Motion for Reconsideration of the court’s December 18, 1992 opinion which granted plaintiffs motion for summary judgment. United Technologies Corporation v. United States, 27 Fed.Cl. 393 (1992). As this court stated in Weaver-Bailey Contractors, Inc. v. United States, 20 Cl.Ct. 158 (1990), “[a] motion for a new trial in a nonjury case or a petition for rehearing should be based upon manifest error of law or mistake of fact, and a judgment should not be set aside except for substantial reasons.” Id. (citing 11 Wright & Miller, Federal Practice and Procedure, Civil section 2804.). Additionally, “[t]o the extent that the motion for reconsideration merely reasserts ... arguments previously made ..., all of which were carefully considered by the Court ... there is no reason to vacate the Court’s earlier Opinion and Order.” Frito-Lay of Puerto Rico, Inc. v. Canas, 92 F.R.D. 384, 390 (D.C.Puerto Rico 1981).

In its present motion, defendant claims that “genuine issues of material fact exist in this case which preclude a grant of summary judgment.” Defs Br. filed January 5, 1993 at 1. Upon full consideration of defendant’s arguments, the court finds that there is no manifest error of law or mistake of fact which would require a reconsideration of this court’s previous opinion. Accordingly, and for the reason’s set forth below, defendant’s motion is denied.

FACTS

A detailed description of the facts of the case appears in United Technologies v. United States, 27 Fed.Cl. 393 (1992). However, for the convenience of the reader, a brief recitation of the facts is presented below.

On December 30, 1971, the government issued a Request for Proposals (RFP) for a cost reimbursement contract to design and develop the Black Hawk helicopter. The RFP required that certain components of the helicopter, including the spindles which attached the four main rotor blades to the aircraft, have a fatigue life of 5,000 hours. In determining the fatigue life of the spindles, two primary factors were considered: (1) the expected ground and flight conditions to which the spindle would be subjected during its life (the “usage, spectrum”), and (2) the results of S-N testing, which involved stress (S) versus the number of cycles to failure (N).

On August 30,1972, plaintiff, United Technologies Corporation, Sikorsky Aircraft Division (Sikorsky), was awarded Development Contract DAAJ01-73-C-0006 on a cost reimbursement basis. Although the contract contained the standard inspection clause which limited plaintiffs liability for deficiencies to six months after government acceptance, Sikorsky remained liable at any time for failure to comply with contract requirements, if such failure was (1) due to fraud, lack of good will or willful misconduct or (2) caused by an individual employee after any supervisory personnel had reasonable grounds to suspect such employee was habitually careless or unqualified.

The development contract required the spindles to meet a 10,000 hour fatigue life in accordance with the substantiation methodology established in Sikorsky Engineering Report (SER)-70100, which set forth the S-N curve and usage spectrum plaintiff would apply in testing the spindles.1 The government approved SER-70100 on November 18, 1977. Plaintiff contends that it fatigue tested six spindles and submitted SER-70116 to the government, substantiating that the spindles exceeded the 10,000 hour requirement. Plaintiff also asserts that the government accepted the test results on July 22, 1980.

Sikorsky was awarded the first Black Hawk production contract in 1977 during the maturity phase of the development contract. This contract was on a fixed-price incentive fee basis with three one-year production options. The contract contained two clauses upon which the government could rely for recovery. The first required Sikorsky to [700]*700correct any deficiencies discovered by either the government or plaintiff. The second clause was the standard fixed price incentive supply contract inspection which provided that any material or workmanship not in conformity with the requirements of the contract is “defective.”

On August 13, 1981, during the fourth and last option year of the first production contract, the government issued Contract Modification P00357 which required Sikorsky to increase the spindles’ diameter. The modification called for plaintiff to fatigue test four spindles, but did not require Sikorsky to develop a new substantiation methodology. With the government’s approval, plaintiff substantiated the new spindles using a new and more rigorous usage spectrum (the “MOD A” spectrum) and revised strength data. Under the new substantiation methodology, the new, thicker spindles had a fatigue life of 6,700 hours. The government accepted the spindles.

Sikorsky was awarded three production contracts and three Basic Ordering Agreements (BOAs) pursuant to which it supplied the remaining new, type 103 spindles. The contracts called for spindles with a 10,000 hour fatigue life under the original substantiation methodology. The BOAs did not specify the spindles’ required fatigue life, nor did they call for any new designs, methodology, or reports. There was no provision in the subsequent production contracts or the BOAs imposing liability on Sikorsky for design defects when design was plaintiffs responsibility under a prior contract.

A Black Hawk helicopter crashed in April 1985, killing all on board. During the crash investigation, the government determined that a spindle had fractured on the helicopter. Sikorsky fatigue tested 31 spindles in the following year as part of its post crash investigation. The government contends that these results revealed that the type 103 spindles did not actually have the required 10,000 hour fatigue life.

On March 21, 1989, the contracting officer issued a final decision finding Sikorsky liable for defective main rotor blade spindles and assessing damages in the amount of $49,503,-966.00. On August 29, 1989, the contracting officer rejected Sikorsky’s $6,994,794.00 claim for payment under the contracts on the basis of the alleged defect. On September 12, 1989, plaintiff filed its complaint in this court challenging both decisions. On October 10,1989, the government filed its answer asserting a counterclaim alleging the spindles were defective.

On December 18, 1992, this court granted plaintiffs motion for summary judgment on the government’s counterclaim alleging a design defect. The court held that “the helicopter rotor spindles were not defective, and the contractor is generally liable for latent defects under fixed-price contracts, but not those awarded on a cost reimbursement basis.” United Technologies, 27 Fed.Cl. at 393.

DISCUSSION

In its previous decision, the court held that the helicopter rotor spindles had the requisite fatigue life as measured by the contractual methodology developed by Sikorsky and accepted by the government. There was no evidence or showing of any dispute of a material fact on this issue. In addition, the court held that assuming that the government could somehow establish the existence of material facts precluding summary judgment on its latent defect claim, defendant had no contractual basis for recovery.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.A. Mortenson Co. v. United States
42 Cont. Cas. Fed. 77,264 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,696, 31 Fed. Cl. 698, 1994 U.S. Claims LEXIS 157, 1994 WL 441088, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-technologies-corp-v-united-states-uscfc-1994.