Southwest Welding & Manufacturing Company v. The United States

413 F.2d 1167, 188 Ct. Cl. 925, 1969 U.S. Ct. Cl. LEXIS 50
CourtUnited States Court of Claims
DecidedJuly 16, 1969
Docket183-65
StatusPublished
Cited by35 cases

This text of 413 F.2d 1167 (Southwest Welding & Manufacturing Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwest Welding & Manufacturing Company v. The United States, 413 F.2d 1167, 188 Ct. Cl. 925, 1969 U.S. Ct. Cl. LEXIS 50 (cc 1969).

Opinion

OPINION

PER CURIAM:

This case was referred to Trial Commissioner Louis Spector with directions to make recommendation for conclusions of law under the order of reference and Rules 57(a) and 99(c) on plaintiff’s assignment of errors. The commissioner has done so in an opinion and report filed on August 23, 1968, wherein such facts as are necessary are stated. Exceptions to the commissioner’s opinion and report were filed by defendant and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the commissioner’s opinion and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Therefore, plaintiff is entitled to recover and further proceedings of this court are stayed pursuant to Rule 100 for a period of 90 days to afford the parties an opportunity to obtain an administrative resolution by the Board, or the contracting officer, of the equitable adjustment to which plaintiff is entitled under the “Changes” clause contained in the contract. Further action by the court will *1169 be deferred pending the outcome of these administrative proceedings.

OPINION OF COMMISSIONER

Spector, Commissioner:

The petition herein presents a contract claim in the amount of $543,843.76. It arises out of an agreement dated April 30, 1957, between plaintiff and the United States acting through the Corps of Engineers of the Department of the Army. The contract covered construction of penstocks and surge tanks in power plant units 4 and 5 of the huge Garrison Dam Project, Riverdale, North Dakota.

These penstocks were designed to convey water from an artificial lake to a turbine employed in the generation of electricity. Each penstock consisted of 36 sections. A section was created by forming and welding steel plate approximately 1 inch thick, into a tubular form about 60 feet long and 24 feet in diameter. Because of their size (which militated against manufacture elsewhere and shipment by common carrier to the project site), and because of the need to develop a mass-production type of welding procedure, these sections were formed and welded from rolled plate in a fabricating shop erected by the contractor at the job site. Thereafter, they were installed within an existing reinforced concrete lined tunnel, 29 feet in diameter, to form a penstock 1600 feet in length, 1300 feet of which was within the concrete tunnel. Each penstock was connected to two surge tanks, which were each about 135 feet high, by 65 feet in diameter.

For a better understanding of the facts which follow, it should be observed at the outset that this is a review 1 of two administrative decisions denying the claim. These decisions were issued by a Board of Contract Appeals representing the Chief of Engineers of the Army. On civil works construction (as distinguished from military construction), he is the duly authorized representative of the Head of the Department referred to in the “Disputes” article contained in this contract.

The issue involved is quite succinctly stated in the first of these administrative decisions, as follows:

The Contracting Officer, for reasons which he deemed sufficient, ordered the contractor to remove and replace all welds accomplished in the fabricating shop by using a single pass technique with twin arc automatic welding machines. The welds had been examined radiographically in the fabricating shop and passed by the Government inspectors. The appellant protested this order but performed the work as directed after giving notice to the Contracting Officer that it would be considered extra work. * * *

The administrative record underlying the aforementioned decisions of the Engineers Board is usually large. It features, for example, eight volumes and 2,154 pages of transcript at an initial hearing, plus four additional volumes totaling 650 pages at a supplemental hearing, plus interrogatories, depositions, and finally, 140 additional pages of transcript. This is surprising because the hearings had been preceded by a comprehensive stipulation of facts, and for the further reason that the Assignment of Errors and Response present no serious issues of fact. On the contrary they, and the accompanying briefs, demonstrate that the dispute herein revolves about the meaning of various contract provisions establishing testing and performance standards for the welding, of the contract terms relating to inspection and post-inspection rights of the parties, and the application of those various contract provisions to undisputed facts. These are fundamentally issues of law, and as stated recently by this court, the administrative decisions in such cases are “not binding on us, but the question may be *1170 determined for ourselves under Section 2 of the Wunderlich Act.” 2 3

The facts narrated above, and hereinafter, are summarized from a comprehensive and lengthy stipulation 3 entered into between the parties prior to the aforementioned hearings. Plaintiff, as a matter of fact, was willing to rest on that stipulation, but hearings were conducted at the Government’s election. 4 The recitation of facts in the Board’s decision also states that it relies on that stipulation. 5

There are two so-called exceptions to the stipulation which are virtually one and the same. They do not detract from the stipulation because they merely reserve that which is the primary issue in this ease, namely, whether or not plaintiff’s work was defective when measured against the standards of testing, inspection, and performance prescribed by the specifications, and the other contract terms drafted by the Government.

Thus, the parties agree that the welding in question exhibited certain characteristics or “manifestations” or “indications” which are the subject of the dispute between them. The contractor asserts that they are not rejectable defects or cracks within the meaning of the contract, and the Government insists that they are. Similarly, the Government asserts that the weld removal which it ordered constituted a “repair,” that term being consistent with the concept of a rejectable defect. Plaintiff prefers to characterize the work which it performed under protest as a “replacement.” 6

As above recited, each penstock was comprised of 36 sections. But this case is concerned solely with the welding of sections 2 to 15 of each penstock. Since welding was accomplished on both the exterior and interior of the sections, there were 95,802 inches of welding performed on the longitudinal seams and 253,314 inches of welding performed on the girth seams of these sections alone.

The work of welding plates together to form sections of the penstocks began in the contractor’s fabricating shop on September 5, 1957. When the sections were' completed, they were examined by Government inspectors in accordance with the provisions of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Konecranes Nuclear Equipment & Services, LLC
Armed Services Board of Contract Appeals, 2024
Environmental Chemical Corporation
Armed Services Board of Contract Appeals, 2022
Cascade Designs, Inc.
Armed Services Board of Contract Appeals, 2022
Ensign-Bickford Aerospace & Defense Company
Armed Services Board of Contract Appeals, 2016
United Technologies Corp. v. United States
39 Cont. Cas. Fed. 76,696 (Federal Claims, 1994)
M.A. Mortenson Co. v. United States
39 Cont. Cas. Fed. 76,555 (Federal Claims, 1993)
Wilner v. United States
28 Fed. Cl. 783 (Federal Circuit, 1993)
Wilner v. United States
26 Cl. Ct. 260 (Court of Claims, 1992)
Concrete Placing Co. v. United States
37 Cont. Cas. Fed. 76,267 (Court of Claims, 1992)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,080 (Court of Claims, 1991)
Delco Electronics Corp. v. United States
35 Cont. Cas. Fed. 75,679 (Court of Claims, 1989)
SMS Data Products Group, Inc. v. United States
35 Cont. Cas. Fed. 75,647 (Court of Claims, 1989)
Sms Data Products Group, Inc. v. The United States
853 F.2d 1547 (Federal Circuit, 1988)
Baltimore Contractors, Inc. v. United States
34 Cont. Cas. Fed. 75,267 (Court of Claims, 1987)
Assurance Company v. The United States
813 F.2d 1202 (Federal Circuit, 1987)
Sperry Corp. v. United States
33 Cont. Cas. Fed. 74,234 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
413 F.2d 1167, 188 Ct. Cl. 925, 1969 U.S. Ct. Cl. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwest-welding-manufacturing-company-v-the-united-states-cc-1969.