Wilner v. United States

26 Cl. Ct. 260, 1992 U.S. Claims LEXIS 229, 1992 WL 102478
CourtUnited States Court of Claims
DecidedMay 14, 1992
DocketNo. 595-89C
StatusPublished
Cited by23 cases

This text of 26 Cl. Ct. 260 (Wilner v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilner v. United States, 26 Cl. Ct. 260, 1992 U.S. Claims LEXIS 229, 1992 WL 102478 (cc 1992).

Opinion

OPINION

NETTESHEIM, Judge.

This construction contract case is before the court after trial on the merits. Melvin Wilner, d/b/a Wilner Construction Company (“plaintiff”), seeks recovery for alleged government-caused delay on the critical path of a construction project. Plaintiff contends that the Government delayed work relating to duct revisions, open web joist (“OWJ”) revisions, and smoke detectors while these activities were on the critical path.1 This opinion resolves the [262]*262issue of whether delays attributable to the Government occurred along the project’s critical path and, if so, whether delay damages are owed to plaintiff. At the conclusion of trial, the court ruled from the bench on three other minor claims.

BACKGROUND

On September 16, 1985, the United States Department of the Navy (the “Navy”) awarded Contract No. N62474-83C-2280 to Wilner Construction Company. The contract, for construction of an Operational Trainer Facility at Camp Pendleton, California, called for a completion date of October 1, 1986. The Navy accepted the project as complete on December 22, 1987, 447 days after the original completion date specified in the contract.

General Provision 17 of plaintiff’s contract, a standard provision prescribed by the General Services Administration for government contracts, provides that a contractor shall be compensated for the costs associated with unreasonable delay that is the fault of the contracting officer. Thus, to recover delay damages plaintiff must establish that the Navy was responsible for unreasonable delay and that plaintiff incurred increased costs in performing the project as a result of that delay. Plaintiff contends that increased costs resulted from government-caused delay along the critical path of the project. One day of delay along the critical path of a project causes the completion date of a project to be extended one day. A delay relating to a specific activity on the project that does not affect the contract completion date is not a critical path delay. While non-critical path delay is compensable under General Provision 17, provided it is unreasonable and a contractor proves damages from such delay, Avedon Corp. v. United States, 15 Cl.Ct. 648, 652-53 (1988) (citing Chaney and James Constr. Co. v. United States, 190 Ct.Cl. 699, 706-08, 421 F.2d 728, 732-33 (1970)), this opinion deals solely with critical path delay, since plaintiff’s claimed damages are based on delay occurring along the critical path of the project and resulting in extension of the contract completion date due to government-caused delay.

In an earlier case involving plaintiff, Wilner v. United States, 23 Cl.Ct. 241 (1991), the court set forth what is entailed in critical path analysis:

“[T]he critical path method is an efficient way of organizing and scheduling a complex project which consists of numerous interrelated separate small projects. Each subproject is identified and classified as to the duration and precedence of the work. (E.g., one could not carpet an area until the flooring is down and the flooring cannot be completed until the underlying electrical and telephone conduits are installed.) The data is then analyzed, usually by computer, to determine the most efficient schedule for the entire project. Many subprojects may be performed at any time within a given period without any effect on the completion of the entire project. However, some items of work are given no leeway and must be performed on schedule; otherwise, the entire project will be delayed. These latter items of work are on the ‘critical path.’ A delay, or acceleration, of work along the critical path will affect the entire project____”

23 Cl.Ct. at 244-45 (quoting Haney v. United States, 230 Ct.Cl. 148, 168, 676 F.2d 584, 595 (1982)). A project’s critical path analysis should be updated regularly while the project is on-going to reflect the evolution of the critical path for the project. Wilner 23 Cl.Ct. at 245 (citing Fortec Constructors v. United States, 8 Cl.Ct. 490, 505 (1985)).

[263]*263A requisite for government liability for the consequences of a critical path delay is fault on the part of the Government. William A. Smith Contracting Co. v. United States, 155 Ct.Cl. 1, 9-10, 292 F.2d 847, 852 (1961) (citing cases). “ ‘Courts will deny recovery where the delays [of the Government and the contractor] are concurrent and the contractor has not established its delay apart from that attributable to the government.’ ” Wilner, 23 Cl.Ct. at 245 (quoting William F. Klingensmith, Inc. v. United States, 731 F.2d 805, 809 (Fed.Cir.1984)). Furthermore, the court is constrained by contract General Provision 17 to award delay damages only for the unreasonable portion of a government-caused delay. Not all delay that occurs along the critical path is unreasonable. Chaney, 190 Ct.Cl. at 713, 421 F.2d at 735. However, delay caused by defective specifications is per se unreasonable. Avedon, 15 Cl.Ct. at 658 (citing Beauchamp Constr. Co. v. United States, 14 Cl.Ct. 430, 438 (1988), and Chaney, 190 Ct.Cl. at 707, 421 F.2d at 732). Consequently, if plaintiff can prove that a defective specification caused delay along the critical path of the project, plaintiff will be entitled to compensation for all delay days along the critical path.

In order for the court to be able to award damages to plaintiff for government-caused delay along the critical path, the court must have before it evidence that establishes the critical path of plaintiff’s project.

Plaintiff produced at trial a diagram illustrating the work on the project involving duct revisions, OWJ revisions, and smoke detectors during the period from May 1986 to December 1987. Plaintiff testified that he derived the information for the diagram, Plaintiff’s Exhibit 965, from the Daily Reports to Inspector (the “DRIs”)2 and the Contractor’s Quality Control Daily Reports (the “CQC reports”)3 for the project. Plaintiff asserts that there are 269 delay and additional work days for the duct revision work resulting from the time the problem was discovered, August 28, 1986, until the time the revision work was completed, June 21, 1987, minus 28 days for contract work completed during that period; that there are 113 delay and additional work days for the OWJ revision work resulting from the time the work became critical, June 21, 1987, to the time the work was completed, September 15, 1987, minus 2 days for contract work completed during that period; and that there are 27 delay and additional work days for the smoke detector work resulting from the date the final fire inspection was initially scheduled, November 18, 1987, until the date the final fire inspection began, December 16, 1987.4

Plaintiff’s diagram is not a critical path analysis. Essential to a determination that an activity belongs on the critical path of a project is an understanding of how that activity affects the other activities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Renda Marine, Inc.
667 F.3d 651 (Fifth Circuit, 2012)
United States v. Renda Marine, Inc.
750 F. Supp. 2d 755 (E.D. Texas, 2010)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
Renda Marine, Inc. v. United States
65 Fed. Cl. 152 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
CJP Contractors, Inc. v. United States
45 Fed. Cl. 343 (Federal Claims, 1999)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Wilner v. United States
28 Fed. Cl. 783 (Federal Circuit, 1993)
Transamerica Insurance ex rel. Stroup Sheet Metal Works v. United States
38 Cont. Cas. Fed. 76,518 (Federal Claims, 1993)
Foley Co. v. United States
26 Cl. Ct. 936 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
26 Cl. Ct. 260, 1992 U.S. Claims LEXIS 229, 1992 WL 102478, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilner-v-united-states-cc-1992.