Fortec Constructors v. United States

32 Cont. Cas. Fed. 73,702, 8 Cl. Ct. 490, 1985 U.S. Claims LEXIS 947
United States Court of Claims·Decided July 15, 1985·No. No. 547-82C·Published·Cited by 17 cases

Opinion

OPINION

YOCK, Judge.

This contract case arises out of a dispute over a contract for the construction of an aircraft fuel maintenance facility at Moody Air Force Base, Georgia. During the course of performance of the contract, six unilateral modifications were issued by the Government. As a result, the plaintiff contends that it is entitled to extensions of contract time for work performed beyond the contract requirements and to additional direct and extended overhead costs incurred in performing this extra work, together with remission of all liquidated damages.

Facts

The plaintiff, Fortec Constructors, a Florida joint venture, is engaged in the business of Government construction, with annual Government contract volume, since 1970, ranging from $2 million to $35 million. On April 28, 1978, the plaintiff was awarded a contract by the Army Corps of Engineers (Corps), Savannah District, in the sum of $930,000, for the construction of an aircraft fuel maintenance facility at Moody Air Force Base, Georgia. The facility contained a hangar, constructed on a heavy concrete slab with a drain pit located in the center, and concrete block bays constructed on either side of the hangar. One of the bays was for offices and the other was for equipment and storage. The contract also called for site work involving construction of force mains, water lines, a concrete apron in front of the hangar, an asphalt roadway leading to the facility, and a water tank. The contract consisted of both drawings and specifications, including the Corps’ standard construction contract General Provisions dated January 3, 1977.

The notice to proceed was acknowledged by the contractor on June 16, 1978. Originally, the contract duration was 360 days, with liquidated damages to be assessed in the amount of $135 per day thereafter. The contract completion date was extended, however, through July 6, 1979, at which time liquidated damages began to be as[492] sessed by the Corps against Fortec. The Government assessed liquidated damages against the plaintiff for the period July 7, 1979, through February 24, 1980, for a total of $31,455 (233 days at $135 per day).

During the course of performance of the contract, 12 modifications were issued by the Government. The plaintiff, however, refused to accept the Corps’ offered remuneration for modifications P005, P006, P007, P009, P010, and P011. Accordingly, these modifications were issued unilaterally. As a result of these modifications, the plaintiff contends that it is entitled to: (1) extensions of contract time for work performed beyond the contract requirements; (2) additional direct and extended overhead costs incurred in performing this extra work; and (3) remission of all liquidated damages. Fortec also seeks additional compensation of $1,825.85 on behalf of its mechanical subcontractor, Rhodes Mechanical, for work beyond the contract requirements relating to: (1) the Corps’ directive to move the hangar’s unit heaters or to install explosion-proof motors if the heaters were left in their initial locations, and (2) the Corps’ directive to install dielectric unions at an oil tank connection.

Thus, Fortec seeks payment of $32,-408.48 for the additional work beyond the amounts already authorized by the Corps, including payment of extended overhead, and remission of $31,455 in liquidated damages.

Discussion

A. Weather Modifications P005 and P007

Fortec, under Counts I and II of its Complaint, requests a time extension of 57 calendar days due to unusually severe weather encountered between October 1, 1978, and June 23,1979. This claim comes under contract General Provision 5(d)(1), which provides, in part, as follows:

The Contractor’s right to proceed shall not be terminated nor the Contractor charged with resulting damage if:
(1) The delay in the completion of the work arises from causes other than normal weather beyond the control and without the fault or negligence of the Contractor, including but not restricted to, * * * unusually severe weather * * *.

Unusually severe weather is “adverse weather which at the time of year in which it occurred is unusual for the place in which it occurred.” Broome Construction, Inc. v. United States, 203 Ct.Cl. 521, 531, 492 F.2d 829, 835 (1974). See also Cape Ann Granite Co. v. United States, 100 Ct.Cl. 53, 71-72 (1943) cert. denied 321 U.S. 790, 64 S.Ct. 785, 88 L.Ed. 1080 (1944). Proof of unusually severe weather is generally accomplished by comparing previous years’ weather with the weather experienced by the contractor. See Cape Ann Granite Co. v. United States, supra, 100 Ct.Cl. at 71-72. In the present case, contract provision lA-06(b), a meteorological chart of past weather averages, established the usual weather conditions to be expected during contract performance. Notwithstanding the occurrences of unusually severe weather, however, a plaintiff is only entitled to an extension of contract time if such unusually severe weather has an adverse impact on the construction being performed. See Essential Constr. Co., ASBCA Nos. 18491, 18611, 18652, 18707, 78-2 BCA 1113,314.

On a daily basis, the contractor completed a Daily Inspection Report (DIR) and the Government completed a Quality Assurance Report (QAR). These reports record daily rainfall, temperature extremes, and a rating of how the weather affected work that day.1 While certain testimony indi[493] cated that the parties did not always complete the reports on a daily basis, the Court believes that the DIRs and the QARs represent the most reliable documents presented regarding both the actual weather at the job site and its effect on job performance. Accordingly, the Court has utilized these documents in assessing the merits of the plaintiff’s weather claims.

During October 1978, Fortec claims five days of weather delay. According to contract provision lA-06(b), October averages 2.01 inches of rain, with four days receiving at least a .10 inch of rainfall. In October of 1978, both the DIRs and the QARs recorded only two days of rain, with a total monthly rainfall of .25 inches, and only one day in which at least a .10 inch of rain fell. This amount of precipitation is below the monthly average and does not constitute unusually severe weather. Therefore, For-tec’s claim for five days of weather delay is denied.

Free access — add to your briefcase to read the full text and ask questions with AI

Fortec Constructors v. United States, 32 Cont. Cas. Fed. 73,702, 8 Cl. Ct. 490, 1985 U.S. Claims LEXIS 947 (cc 1985).

32 Cont. Cas. Fed. 73,702 (Fortec Constructors v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Mactec, Inc. v. Bechtel Jacobs Company, LLC
346 F. App'x 59 (Sixth Circuit, 2009)
Southern Comfort Builders, Inc. v. United States
67 Fed. Cl. 124 (Federal Claims, 2005)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Goldberger Foods, Inc. v. United States
37 Cont. Cas. Fed. 76,111 (Court of Claims, 1991)
Wilner v. United States
37 Cont. Cas. Fed. 76,101 (Court of Claims, 1991)
CCM Corp. v. United States
36 Cont. Cas. Fed. 75,876 (Court of Claims, 1990)
Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
Fortec Constructors, Etc. v. The United States
804 F.2d 141 (Federal Circuit, 1986)
Fortec Constructors v. United States
804 F.2d 141 (Federal Circuit, 1986)