CCM Corp. v. United States

36 Cont. Cas. Fed. 75,876, 20 Cl. Ct. 649, 1990 U.S. Claims LEXIS 226, 1990 WL 78846
CourtUnited States Court of Claims
DecidedJune 8, 1990
DocketNo. 599-86C
StatusPublished
Cited by10 cases

This text of 36 Cont. Cas. Fed. 75,876 (CCM Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CCM Corp. v. United States, 36 Cont. Cas. Fed. 75,876, 20 Cl. Ct. 649, 1990 U.S. Claims LEXIS 226, 1990 WL 78846 (cc 1990).

Opinion

OPINION

FUTEY, Judge.

This case is before the court after a trial on the merits. Plaintiff, a construction contractor, claims that the presence of tar beneath a concrete walkway constitutes an unanticipated site condition which entitles it to an equitable adjustment of a contract price. In addition, plaintiff requests compensation for performance delays allegedly caused by defendant from approximately June 1, 1983, until “sometime” in October 1983. In response, defendant asserts that plaintiff has failed to demonstrate that the tar-based waterproofing system is materially different from the known and usual system. Furthermore, defendant argues that' plaintiff is entirely responsible for the claimed contract delay.

Factual Background

This government contract case involves the refurbishment of an enclosed walkway between two buildings at a Veterans Medical Center (VMC). At issue is the “differing site conditions” contract provision as it applies to the performance of the re-waterproofing of the enclosure. This case first came before the court on September 25, 1986. Subsequently, this court entered an Order which granted defendant’s motion for partial summary judgment.1 CCM Corp. v. United States, 15 Cl.Ct. 670 (1988). The statement of facts made in that earlier order will be elaborated here.

Plaintiff is a corporation organized and existing under the laws of the Commonwealth of Massachusetts, with its principle place of business in Methuen, Massachusetts. Prior to the submission of its bid, plaintiff’s president and an estimator for plaintiff made a visual inspection of the site. However, they did not inquire about the nature of the existing waterproofing system. Plaintiff did not attend the pre-bid conference and official pre-bid inspection held on February 10, 1983.

On March 10, 1983, plaintiff submitted its bid on the firm-fixed price contract.2 At [651]*651that time plaintiff did not know what type of waterproofing existed on the structural concrete surface. Based solely upon its president’s prior experience, plaintiff expected that the existing waterproofing system was asphalt. Plaintiff intended to use Jacor, Inc., as a waterproofing subcontractor. Plaintiff’s bid proposal indicated the hot rubberized asphalt system to be used was Firestone No. 6125.3

On May 3,1983, plaintiff entered into the contract with defendant. Plaintiff’s duties were to furnish all the materials and perform the work for insulating and waterproofing existing connecting corridors for the Veterans Administration (VA) Medical Center at Brockton, Massachusetts, in strict accordance with the plans and specifications,4 for the price of $409,450.00. Specifically, the contract provides for plaintiff to furnish all labor, material, equipment and appurtenances necessary for the removal5 of the existing concrete wearing slab and fence on the connecting corridor roof walk, the replacement of the wearing slab with a new concrete wearing slab and new fence, the removal and replacement of the existing roofing, insulation and fencing on the connecting corridor roof walk, the furnishing of planting material, the installation of new fence support benches, free standing benches, planters, trash receptacles and ash urns.6 The work was to be finished within 180 calendar days from the receipt of the notice to proceed, which was received by plaintiff on May 23, 1983. Thus, the completion date of the contract was November 19, 1983. Change orders,7 as requested by plaintiff and issued by the defendant, extended the completion date to June 11, 1984.

The contracting officer (CO) issued the notice to proceed on May 18, 1983. Plaintiff acknowledged receipt of the notice on May 23, 1983.

On or about June 2, 1983, plaintiff commenced sawcutting the connecting corridors and encountered an existing tar pitch [652]*652waterproofing system. Unfortunately, the waterproofing system plaintiff intended to use, asphalt, cannot be applied on a surface previously exposed to tar without expensive decontamination procedures. Thus, the demolition expenses under the contract would cost more than plaintiff intended to pay. This is the essence of the case. Consequently, plaintiff claims that this system is incompatible with the hot-applied rubberized asphalt system upon which its bid was based.8 Plaintiff immediately advised the CO’s Technical Representative (TR) of the allegedly unanticipated site condition.9

On June 7, 1983, plaintiff submitted to defendant for approval, pursuant to the contract,10 an asphalt waterproofing system, Bithuthene Waterproofing Systems.11 On June 14, 1983, plaintiff submitted for approval a sample and specifications for the material Bithuthene 3000 (Bithuthene). On June 21, 1983, defendant approved Bithuthene subject to the condition that the manufacturer grant the 10-year warranty as required by the contract specifications. A few days later, plaintiff submitted yet another type of waterproofing material, Flintlastic,12 as the intended waterproofing material. This was approved by the defendant, pursuant to the contract, on July 7th, 1983.

Immediately after the 7th of July, it is not clear what transpired between the parties. Plaintiff claims that it was trying to resolve the tar question with defendant. Defendant denies this and asserts that plaintiff was “shopping around” for lower priced waterproofing materials than those already approved. In any event, numerous prime weeks for re-waterproofing were lost. On August 1, 1983, defendant wrote to plaintiff:

This is to inform you that the specifications under Section 02060-Demolition [653]*653must be complied with. The deck must be completely stripped of all remaining slabs, roofing, waterproofing, fencing and associated building elements and tar pitch so that the surface is acceptable to begin new membrane application.13

On August 25, 1983, plaintiff submitted yet another change order request for a waterproofing system. This time, plaintiff requested the waterproofing system Rho-flux. On September 1,1983, the CO denied plaintiff’s request for the use of Rhoflux and directed plaintiff to proceed with the contract work under the schedule utilizing Bithuthene. On September 9, 1983, plaintiff submitted a request for change order No. 6 seeking $22,865.00 and a 60-day extension of time for alleged material and labor costs associated with the use of Bithuthene.

On September 15, 1983, plaintiff met with representatives of W.R. Grace and Company (Grace), the manufacturer of Bithuthene. They told plaintiff of its requirements for issuance of a guarantee for the use of Bithuthene. On September 16,1983, Grace advised plaintiff that it was prepared to offer a 10-year warranty.14 Plaintiff then submitted a change order for the alleged costs associated with Bithuthene and a warranty. The CO denied plaintiff’s request on September 23, 1983.

On October 3, 1983, plaintiff submitted a revised claim totaling $48,584.00 for costs associated with the use of Bithuthene, which was denied by the CO on January 30, 1984.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
R.P. Richards Construction Co. v. United States
51 Fed. Cl. 116 (Federal Claims, 2001)
CJP Contractors, Inc. v. United States
45 Fed. Cl. 343 (Federal Claims, 1999)
Louis Leustek & Sons, Inc. v. United States
41 Fed. Cl. 657 (Federal Claims, 1998)
Sergent Mechanical Systems, Inc. v. United States
40 Cont. Cas. Fed. 76,860 (Federal Claims, 1995)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
HVAC Construction Co. v. United States
28 Fed. Cl. 690 (Federal Claims, 1993)
A.S. McGaughan Co. v. United States
37 Cont. Cas. Fed. 76,239 (Court of Claims, 1991)
Southland Enterprises, Inc. v. United States
37 Cont. Cas. Fed. 76,238 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,876, 20 Cl. Ct. 649, 1990 U.S. Claims LEXIS 226, 1990 WL 78846, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ccm-corp-v-united-states-cc-1990.