William F. Klingensmith, Inc. v. United States

731 F.2d 805, 32 Cont. Cas. Fed. 72,527, 1984 U.S. App. LEXIS 14871
Court of Appeals for the Federal Circuit·Decided March 19, 1984·No. Appeal 83-1131·Published·Cited by 57 cases

Opinion

KASHIWA, Circuit Judge.

Pursuant to the Contract Disputes Act of 1978, 41 U.S.C. § 601 et seq., appellant (contractor) appeals a decision of the General Services Administration Board of Contract Appeals (the “Board”) denying its claim for a contract time extension of 32 calendar days plus impact costs of $72,032. The Board concluded that the delay occurred because of appellant’s poor scheduling and not because appellant was required to remove an unexpected smoke tunnel from the site. Because we conclude that the Board failed to address a second issue raised, whether the delay occurred because the government required appellant to change 10 footings to caissons, we vacate and remand the case to the Board for a full hearing on the merits of this issue.

Background

In April, 1977, the contractor was awarded a fixed-price contract by the General Services Administration (GSA) to construct a parking garage and ancillary structures. Work began in May, 1977, and the original completion date was February 10, 1978. There were extensive delays in the progress of the work and the building was not accepted by GSA until September, 1978.

As part of the wojk, appellant was to install the garage foundation, part of which consisted of footings and the remainder of caissons. 1 Appellant’s caisson subcontractor, Seaboard, arrived on the site in May and began work in earnest on June 10, 1977. On June 24, after having installed 43 caissons, the subcontractor left the site, returning on July 29. On August 8, Seaboard completed the caisson work.

Originally, 65 caissons were to be installed on the site. In Area 4, level C, unsuitable soil conditions, not marked on the drawings or shown in the test bore samples, required that ten additional caissons be substituted for the originally specified footings. As it became clear that the soil in this area was unsuitable for footings, the government directed appellant to continue excavating the footing holes until good fill was reached. Eventually the government *807 ordered appellant to change ten of the footings to caissons. (Change Order 30).

In Area 4, level C, there was also an underground smoke tunnel not indicated on the contract plans or the test borings. A portion of the tunnel had to be removed in order to install caissons and the government’s construction manager ordered appellant to remove the tunnel. (Change Order 5).

GSA reimbursed appellant for its direct costs in removing the smoke tunnel and for installation of the ten additional caissons. Appellant also requested a 32 calendar-day delay (23 work-day) contract time extension and delay damages of $72,032 for the time Seaboard was off the site. This request was denied by the contracting officer and the contractor appealed to the GSA Board of Contract Appeals.

The Board denied appellant’s claim, concluding that Seaboard was not delayed by the removal of the smoke tunnel because only a maximum of two caissons not yet installed could possibly have been affected by the removal of the tunnel. The Board stated that the delay was caused by appellant’s failure to make the areas needed for the caisson work available to Seaboard when it failed to remove unsuitable fill, as provided for in the contract plans. The Board concluded that appellant’s poor scheduling was the cause of the delay. On a Motion for Reconsideration, the Board affirmed its decision. This appeal followed.

I

On appeal, the contractor contends that the Board’s decision must be set aside because it failed to address appellant’s claim that the government’s order to install ten additional caissons was the cause of the delay, its decision being based entirely on the smoke tunnel issue. The government contends that having failed to raise this issue properly before the board, appellant is precluded from asserting it in this forum.

It is well settled that if appellant had not raised this issue before the Board, it could not raise it now for the first time on appeal. Conrac Corporation v. United States, 558 F.2d 994, 214 Ct.Cl. 561 (1977); Ace Construction Co. v. United States, 401 F.2d 816, 185 Ct.Cl. 487 (1968). The record, however, establishes that appellant did raise this issue to the Board. Appellant’s request for extension of time and delay damages, the basis for appellant’s claim before the Board, clearly states that the scope of the work covered was “over-depth drilling of caissons and additional caissons drilled due to changed conditions.”

Furthermore, appellant’s appeal petition to the Board lists several allegations, including:

V
That the specifications called for 10 spread footings, but due to the latent subsurface unsuitability (lack of a solid bottom), the excavated area had to be refilled and then drilled for caissons in place of the spread footings.
VI
That the General Services Administration’s indecision and lack of direction caused Appellant a 32 calendar day delay while the General Services Administration tried to decide what corrective actions to take.
VII
That this delay was a result of the changed conditions resulting from Change Order Nos. 18 and 30, and not concurrent with Change Order Nos. 18 and 30.[ 2 ]

Appellant’s answers to interrogatories, post-hearing brief, and witnesses’ testimony also contain similar allegations that the change from footings to caissons was the cause of the delay.

*808 The government does not contend that the contractor completely failed to raise this issue, but rather that it raised it in a confusing way. It asserts that after the Board issued its initial decision, which defined appellant’s claim as premised upon removal of the smoke tunnel, it was incumbent upon appellant to apprise the Board of its misunderstanding. 3

Appellant, however, did raise this issue in its Motion for Reconsideration. In this motion appellant stated that the Board’s decision was contrary to law and to the facts. It then listed a series of allegations in support of the motion, including:

9. It is undisputed that ten (10) footings were changed to caissons requiring substantial additional work, including the removal of additional uncontrolled fill.
10. The finding by the Board that some number of caissons less than ten (10) might have been affected by the additional work ignores the real delay experienced in the project and forgets that the delay of any number of caissons is nevertheless a delay and compensable to WFK.

Free access — add to your briefcase to read the full text and ask questions with AI

William F. Klingensmith, Inc. v. United States, 731 F.2d 805, 32 Cont. Cas. Fed. 72,527, 1984 U.S. App. LEXIS 14871 (Fed. Cir. 1984).

731 F.2d 805 (William F. Klingensmith, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

David Boland, Inc.
Armed Services Board of Contract Appeals, 2024
RBC Construction Corp.
Armed Services Board of Contract Appeals, 2020
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
243 Cal. App. 4th 571 (California Court of Appeal, 2015)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Sea Crest Construction Corp. v. United States
59 Fed. Cl. 615 (Federal Claims, 2004)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
P.R. Burke Corp. v. United States
277 F.3d 1346 (Federal Circuit, 2002)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
CJP Contractors, Inc. v. United States
45 Fed. Cl. 343 (Federal Claims, 1999)