Merritt-Chapman & Scott Corp. v. United States

528 F.2d 1392, 21 Cont. Cas. Fed. 84,529, 208 Ct. Cl. 639, 1976 U.S. Ct. Cl. LEXIS 137
CourtUnited States Court of Claims
DecidedJanuary 28, 1976
DocketNo. 89-64
StatusPublished
Cited by38 cases

This text of 528 F.2d 1392 (Merritt-Chapman & Scott Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merritt-Chapman & Scott Corp. v. United States, 528 F.2d 1392, 21 Cont. Cas. Fed. 84,529, 208 Ct. Cl. 639, 1976 U.S. Ct. Cl. LEXIS 137 (cc 1976).

Opinion

Nichols, Judge,

delivered the opinion of the court:

This case comes before the court on defendant’s request, filed April 18, 1975, for review by the court of Trial Judge Louis Spector’s recommended decision of February 5, 1975. The case has a long and detailed history, 'having already occasioned five Corps of Engineers Board of Contract Appeals decisions, two recommended trial judge opinions, and one decision by this court, 194 Ct. Cl. 461, 489 F. 2d 185 (1971).

In an experiment sponsored by the American Bar Association 'and the Federal Judicial Center, and assented to by all parties concerned, the above named panel, sitting in Washington, D.C., heard oral argument delivered by counsel in New York, New York, using “Picturephone” facilities provided by the American Telephone & Telegraph Company. The facilities did their part and it is now up to us to do ours.

I.

The contract out of which this case arose was between Savin Construction Corporation, wholly-owned subsidiary and predecessor in interest of plaintiff, and the United States Government, 'acting through the Army Corps of Engineers, for the construction of the New Cumberland Locks and Dam on the Ohio Biver. Twin locks were to be built, involving the construction of 3 lock walls. An existing highway, Ohio State Highway No. 7, ran directly over the specified location of the middle lock wall for about three-fourths of its length. Defendant 'as part of its obligation to furnish the construe[643]*643tion site, contracted with the State of Ohio to relocate the 2-mile section of State Highway No. Y. Defendant agreed to construct the subgrade for the relocated highway along a new alignment, following which the State Highway Department would have the permanent road placed. Once the new Highway No. Y Was opened to traffic, the State would turn the existing Highway No. Y over to defendant so that plaintiff could excavate fit in furtherance of the lock and dam project.

Accordingly, in March 1955, the defendant entered into two contracts for the construction of the subgrade, scheduled for completion 'as of October 1,1955.

Plaintiff had been awarded the contract on October 24, 1955. The contract provided that plaintiff could not remove any part of existing State Highway No. Y “until the relocated highway is opened to traffic, which will be about 1 December 1955.” Further, plaintiff was instructed that disposal operations had to be completed by May 1, 1956. (This was due to a contract between defendant and Ohio Edison Company, permitting defendant to use adjacent Ohio Edison land to dispose of the excavated material as long as the 'disposal was terminated by May 1,1956).

On November 4,1955, plaintiff received Notice to Proceed and thereupon mobilized its men and equipment to initiate excavation. The construction of the cofferdam and pouring the concrete structures within the cofferdam area depended on the excavation being completed. Existing Highway No. Y was not in fact made available to plaintiff on December 1, 1955, as the contract provided, but instead on April 14,1956. The Government did not issue a formal suspension order suspending the work as it could and should have done under the Suspension of Work Clause and therefore plaintiff maintained its men and equipment in a state of readiness.

Plaintiff filed a formal claim with the Contracting Officer for the monetary consequences of defendant’s failure to provide old Route Y on time. The claim was denied and plaintiff appealed to the Corps of Engineers Board of Contract Appeals under the Disputes and the Suspension of Work Clauses.

[644]*644It should be noted that the issue has always been a partial, not a complete suspension of work, and any reference to suspension hereinafter means this. Plaintiff described its damages allegedly resulting from the Government’s partial suspension of work in failing to turn the site over in time as follows:

First. Increased excavation costs were incurred because the Government required the ¡contractor to excavate in an area between the old and new Eoutes 7, a narrow, restricted confined and unproductive ¡area. The V-shaped excavation, which narrowed as it deepened because of the slope requirements, acted as a trap for rain and ground water, aggravating excavation problems.

Second. Increased costs, such as idled equipment costs, were incurred because the Government did not issue a formal order suspending work, thus plaintiff was obligated to maintain its men and equipment in a state of readiness.

Third. Increased costs were incurred because of an overall delay to the project.

The Board, on December 10, 1963, determined that the Government did partially suspend the contractor’s operations for 18 days and remanded the case to the contracting officer to consider quantum. Eng. BCA No. 2126 (1963). On plaintiff’s motion for reconsideration, the Board found that the Government’s partial suspension “unreasonably delayed the contractor to some extent between January and 14 April 1956.” Eng. BCA No. 2126 (1964). A third opinion was issued denying the Government’s request for reconsideration. Thereafter on March 14, 1968, the Board determined that plaintiff had not shown any damage. Eng. BCA No. 2675, 68-1 BCA ¶ 6935. Plaintiff appealed to this court and we issued a decision on March 19, 1971, remanding the case to the Board to determine “the existence or the amount of damages.” 194 Ot. Cl. at 476,439 F. 2d at 194. We specifically noted that “we do not make any determination on the substantive merits of the claim.” 194 Ct. Cl. at 464,439 F. 2d at 186. Thus our remand was broader than a remand only to determine quantum.

Several aspects of our prior decision bear repeating in light of the Board’s fifth decision. We held that the Government’s [645]*645failure to band over tbe existing highway to plaintiff on the specified date resulted in effect in a partial suspension of work by the Government, actionable under the Suspension of Work Clause quoted infra. Plaintiff was denied access to a necessary part of the work site. The lack of a formal suspension order did not make the suspension any the less effective under the doctrine of Constructive Suspensions. Once it is determined that there was a partial suspension of work for the convenience of the Government, two separate questions emerge: 1st, did the suspension delay the work for an unreasonable length of time, and 2nd, if so, did this unreasonable delay cause additional expense or loss, and in what amount (quantum). We remanded the case because we thought that the Board “rolled all these questions into one,” 194 Ct. Cl. at 474, 439 F. 2d at 192, however we did determine that the suspension lasted from December 1,1955, until at least April 14,1956, and this delay was unreasonably long. The Board was instructed to allow both parties to present further evidence and to consider whether the unreasonable delay caused any additional expense or loss to the contractor, and if so, in what amount. We did not determine whether the contractor had in fact been harmed by the delay but stated, “it is not out of place to say that prima facie it does seem that a delay of four-and-one-half months, in the circumstances thus far revealed by the record, would probably lead to some harm to this contractor. It may be that, for various reasons, plaintiff suffered no detriment at all from the withholding of Highway No. 7 for this long period, but, as of now, we do not see that conclusion as either clear or certain.” 194 Ct. Cl. at 476, 431 F. 2d at 194.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Boland, Inc.
Armed Services Board of Contract Appeals, 2024
Phylway Construction, LLC
Armed Services Board of Contract Appeals, 2022
Matcon Diamond, Inc.
Armed Services Board of Contract Appeals, 2020
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
K-Con Building Systems, Inc. v. United States
100 Fed. Cl. 8 (Federal Claims, 2011)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Wayne Knorr, Inc. v. Department of Transportation
973 A.2d 1061 (Commonwealth Court of Pennsylvania, 2009)
GASA, Inc. v. United States
79 Fed. Cl. 325 (Federal Claims, 2007)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
CJP Contractors, Inc. v. United States
45 Fed. Cl. 343 (Federal Claims, 1999)
Hoffman Construction Co. v. United States
42 Cont. Cas. Fed. 77,247 (Federal Claims, 1998)
Coastal Industries, Inc. v. United States
39 Cont. Cas. Fed. 76,722 (Federal Claims, 1994)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Wilner v. United States
37 Cont. Cas. Fed. 76,101 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
528 F.2d 1392, 21 Cont. Cas. Fed. 84,529, 208 Ct. Cl. 639, 1976 U.S. Ct. Cl. LEXIS 137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merritt-chapman-scott-corp-v-united-states-cc-1976.