Phylway Construction, LLC

CourtArmed Services Board of Contract Appeals
DecidedOctober 11, 2022
DocketASBCA No. 62961
StatusPublished

This text of Phylway Construction, LLC (Phylway Construction, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phylway Construction, LLC, (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Phylway Construction, LLC ) ASBCA No. 62961 ) Under Contract No. W912P8-19-C-0015 )

APPEARANCES FOR THE APPELLANT: Brian S. Wood, Esq. Jacob W. Scott, Esq. Smith, Currie & Hancock, LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Thomas M. Taff, Jr., Esq. Engineer Trial Attorney U.S. Army Engineer District, New Orleans

OPINION ON GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT BY ADMINISTRATIVE JUDGE D’ALESSANDRIS

In 2019, respondent, the United States Army Corps of Engineers (USACE or government) awarded a Mississippi River levee construction project to appellant, Phylway Construction, LLC (Phylway). The levee work involved a construction technique called Deep Soil Mixing (DSM) that involved blending a hardening agent with the native soils, in situ, to improve the soil, and thus, performance of the levee. Relevant to this appeal, the contract provided that the contractor would not be permitted to perform levee work when the level of the Mississippi River exceeded 11 feet as measured at the Carrolton, Louisiana river gauge. Further, the contract provided that, in the event of high river levels, the contractor would be entitled to an extension of time consistent with Federal Acquisition Regulation (FAR) FAR 52.249- 10 Default (Fixed-Price Construction) – a provision that provides for non-compensable time extensions.

In 2019 and 2020, before and during performance of the levee project, the elevation of the Mississippi River exceeded 11 feet on 230 and 171 days, respectively. The number of high water days during this period was roughly two to three times the 1987-2018 average of 80 days per year. During these extended high water periods, Phylway’s subcontractor, JAFEC USA, Inc. (JAFEC), was unable to perform the DSM levee work, resulting in a higher cost of performance. The government issued four bilateral contract modifications extending the performance period by over a year (372 days). Phylway requested that JAFEC be permitted to perform certain contract work when the river level exceeded 11 feet, but the USACE declined the requests. In addition, Phylway’s requests for equitable adjustment were declined.

Phylway sponsors a pass-through claim by its subcontractor JAFEC, alleging a constructive suspension of work, or that the contract was commercially impracticable. The government moves for summary judgment based on the express terms of the contract assigning the risk to Phylway, and also because Phylway’s claims are barred by release and accord and satisfaction, based on the contract modifications extending the period of performance. We grant the government’s motion for summary judgment.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

I. The Contract

The government awarded Contract No. W912P819C0015 to Phylway on February 13, 2019, for $ 48,654,095 (R4, tab 6 at GOV90-93). The contract had a duration of 730 calendar days (id. at GOV90). The contract required Phylway to perform work including “clearing and grubbing, disposal of debris material, demolition of existing asphalt and replacing, levee enlargement construction, installation of deep material mixing for ground improvement, construction of levee ramps, surfacing, seeding, fertilizing, mulching, and any other related work” on the Mississippi River levee in Plaquemines Parish, Louisiana (id. at GOV343). Deep material mixing, or Deep Soil Mixing is an advanced ground improvement technique through blending a hardening agent with the native soils, in situ. (Compl. at ¶ 9). The process is a way to improve the character, strength, and stiffness of the soil. (Id.) As a revolver hollow shaft with mixing paddles and/or the mixing tool advance into the soil, the cement grout is pumped through the hollow shaft discharging laterally along the lower mixing paddle where it is mixed with the native soil. (Id.; R4, tab 6 at GOV543- 47)

The contract’s High River Work Restrictions clause provides:

At such time that the Mississippi River is at or above + 11.0 feet, NAVD 88 (2004.65) at the Carrolton gage (New Orleans District), all construction work shall cease until such time as the elevation subsides below + 11.0 feet. . . . Delays to the Contractor’s operations from ceasing work when the Mississippi River elevation is above + 11.0 feet at the Carrolton gage will be subject to the provisions of Section 00700, Contract Clause entitled “Default (Fixed- Price Construction)[”] (FAR 52.249-10).

2 (R4, tab 6 at GOV160)

Also relevant to this appeal, the contract includes a clause titled Time Extensions for Unusually Severe Weather, which states in relevant part:

(a) This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the Contract Clause in Section 00700, entitled Default (Fixed Price Construction) (FAR 52.249-10). In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied.

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

(a) The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) for temperature, precipitation and wet ground conditions or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor’s progress schedule must reflect these anticipated adverse weather delays in all-weather dependent activities. Also considered in the chart below was wind, fog, high or low tides, etc.

...

(d) The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month) and shall be calculated chronologically from the first to the last day of each month and shall be recorded as full days. If the number of actual adverse weather delay

3 days exceeds the number of days anticipated in paragraph b, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clause in Section 00700, entitled Default (Fixed Price Construction) (FAR 52.249-10).

(R4, tab 6 at GOV135-36 (Chart omitted))

The default clause referenced in the above contract clause, FAR 52.249-10 Default (Fixed-Price Construction) (APR 1984) is incorporated in full text in the contract (R4, tab 6 at GOV121-22). The default clause provides in relevant part that:

(b) The Contractor’s right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if—

(1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include—

(i) Acts of God or of the public enemy, (ii) Acts of the Government in either its sovereign or contractual capacity, (iii) Acts of another Contractor in the performance of a contract with the Government, (iv) Fires, (v) Floods, (vi) Epidemics, (vii) Quarantine restrictions, (viii) Strikes, (ix) Freight embargoes, (x) Unusually severe weather, or (xi) Delays of subcontractors or suppliers at any tier arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and the subcontractors or suppliers;

(id.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Holland v. United States
621 F.3d 1366 (Federal Circuit, 2010)
Natus Corporation v. The United States
371 F.2d 450 (Court of Claims, 1967)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Merritt-Chapman & Scott Corp. v. United States
528 F.2d 1392 (Court of Claims, 1976)
Jennie-O Foods, Inc. v. United States
580 F.2d 400 (Court of Claims, 1978)
DeMatteo Construction Co. v. United States
600 F.2d 1384 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
Phylway Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phylway-construction-llc-asbca-2022.