Seaboard Lumber Company and Capital Development Company v. United States

308 F.3d 1283, 2002 U.S. App. LEXIS 21718, 2002 WL 31323419
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 18, 2002
Docket01-5097, 01-5124
StatusPublished
Cited by131 cases

This text of 308 F.3d 1283 (Seaboard Lumber Company and Capital Development Company v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seaboard Lumber Company and Capital Development Company v. United States, 308 F.3d 1283, 2002 U.S. App. LEXIS 21718, 2002 WL 31323419 (Fed. Cir. 2002).

Opinion

LINN, Circuit Judge.

Seaboard Lumber Co. (“Seaboard”) and Capital Development Co. (“CDC”) jointly appeal from decisions of the United States Court of Federal Claims assessing liability and awarding damages to the government resulting from the respective failures of each of the companies to perform on different timber sales contracts. Seaboard Lumber Co. v. United States, 48 Fed. Cl. 814 (2001) (“Seaboard II ”); Capital Dev. Co. v. United States, 49 Fed. Cl. 178 (2001). Seaboard also appeals from the rejection as a matter of law of its nonperformance defenses of force majeure, impossibility of performance, commercial impracticability and frustration of purpose. Seaboard Lumber Co. v. United States, 41 Fed.Cl. 401 (1998) (“Seaboard I”). Because the Court of Federal Claims did not err in its conclusions of law, and its findings of fact on damages are not clearly erroneous, we affirm.

I. BACKGROUND

A. The Timber Contracts

At issue in this appeal are one timber sale contract, designated the “What” contract, between Seaboard and the Forest Service, and six timber sale contracts, designated the “Bride,” “Pearl,” “Ram,” “Cougar,” “Short Flat,” and “Cow” contracts, between CDC and the Forest Service. Seaboard disputes both liability and damages resulting from its breach of the What contract. CDC disputes both liability and damages resulting from its breach of the Cow contract. CDC concedes liability but disputes damages resulting from its breach of the Bride, Pearl, Ram, Cougar, and Short Flat contracts.

1. The What Contract

In September 1980, Seaboard entered into the What contract — a fixed price contract to harvest timber. At that time, there was a housing boom and the price of timber was high. The contract required Seaboard, by the contract termination date of March 31, 1983, to cut, remove, and pay for all of the timber on the What parcel.

*1288 Between 1981 and 1983, the government allowed interest rates to rise in order to combat inflation, and at least in part because of the rise in interest rates, the housing and lumber markets softened. Many contractors ran into financial difficulties. The timber in all of the parcels at issue in this appeal was of sufficient quality to harvest, and the contractors had the opportunity to conduct a harvest if they so desired. Some logging contractors performed on their timber contracts during this period. Others did not.

In April 1983, the Forest Service allowed Seaboard a two-year extension of the contract term under the agency’s SOFT II extension policy, which allowed contract extensions due to then-depressed markets for forest products. The What contract expired, uncompleted, on December 28,1985.

The What contract contained a damages provision, Provision B9.4, which stated, in pertinent part, that:

Damages due the United States for Purchaser’s failure to cut and remove such timber meeting Utilization Standards shall be the amount by which Current Contract Value plus the cost of resale, less any effective Purchase Credit remaining at the time of termination, exceeds the resale value at new Bid Rates. If there is no resale, damages due shall be determined by subtracting the value established by said appraisal from the difference between Current Contract Value and Effective Purchaser Credit.

In 1984, Congress enacted the Federal Timber Contract Payment Modification Act, which stated that, effective 1985, “in any contract for sale of timber from the National Forests, the Secretary of Agriculture shall require a cash down-payment at the time the contract is executed and peri-odie payments to be made over the remaining time of the contract.” 16 U.S.C. § 618(d) (2000). The purported goal of these new financial requirements was to deter speculative bidding.

In 1987, the Forest Service resold the What contract. Pursuant to 16 U.S.C. § 618, the resale contract incorporated both a down payment requirement (10 percent of advertised resale plus a 20 percent bid premium) and a midpoint payment requirement (25 percent of the total contract value) that equaled $61,800 and $149,000, respectively. The original What contract contained neither financial requirement. In addition, the resale contract sold less timber than the original, 5,900 MBF 1 as opposed to the original 6,300 MBF, and contained a shorter logging period, 9.5 months of normal operating season as opposed to the original 18.5 months.

There were three bidders on the What resale, one fewer than on the original contract. The contract was resold for less than the then-current contract value of the remaining timber plus the cost of resale. Pursuant to the governing damages provision, the Forest Service’s contracting officer demanded the difference. The government subsequently reduced the requested damage amount to reflect what it estimated to be the effect of the down payment and midpoint payment requirements in reducing the resale price.

2. The Cow Contract

On April 15, 1983, CDC and the Forest Service entered into the Cow contract. The contract required CDC to cut, remove, and pay for all of the timber included in the sale by the contract termination date of March 31, 1985. By early 1985, CDC had removed over 75 percent of the original estimated volume of 4,300 MBF. CDC *1289 sought and the Forest Service granted a one-year extension pursuant to Special Provisions C8.23 & C8.231. 2 In July 1985, the contracting officer sent CDC a letter stating that the Cow contract “will not qualify for any further extensions.” Nevertheless, CDC requested a second one-year extension. The Forest Service denied this request. CDC abandoned the contract on December 26, 1985 after harvesting an amount of timber that was in excess of 100% of the original estimated volume but was not all of the timber in the Cow parcel.

The Cow contract, like CDC’s other contracts, contained Provision C9.4, which provides, in pertinent part:

Damages due the United States for Purchaser’s failure to cut and remove Included Timber meeting Utilization Standards shall be the amount by which Current Contract Value, plus costs described below, less any Effective Purchaser Credit remaining at time of termination, exceeds the resale value at new Bid Rates. If there is no resale, damages due shall be determined by subtracting the value established by said appraisal from the difference between the Current Contract Value and unused Effective Purchaser Credit, plus any of the following applicable costs:
(1) The cost of resale or reoffering;
(2) Any increase in Purchaser Credit Limit allowance for unconstructed Specified Road facilities which are needed to harvest the remaining uncut volume ....;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Langdon Engineering & Mgt
Armed Services Board of Contract Appeals, 2025
Skanska USA Civil Southeast, Inc.
Armed Services Board of Contract Appeals, 2025
Chugach Federal Solutions, Inc
Armed Services Board of Contract Appeals, 2024
Safaa Al-Rawaby Company
Armed Services Board of Contract Appeals, 2023
Heart & Core LLC
Armed Services Board of Contract Appeals, 2023
D-STAR Engineering Corporation
Armed Services Board of Contract Appeals, 2021
Halim v. United States
Federal Circuit, 2020
UGI Sunbury LLC v. Permanent Easement for 1.7575
949 F.3d 825 (Third Circuit, 2020)
Parwan Group Company
Armed Services Board of Contract Appeals, 2018
Canpro Investments, Ltd v. United States
130 Fed. Cl. 320 (Federal Claims, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
308 F.3d 1283, 2002 U.S. App. LEXIS 21718, 2002 WL 31323419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seaboard-lumber-company-and-capital-development-company-v-united-states-cafc-2002.