U.S. Aeroteam, Inc. v. United States

Court of Appeals for the Federal Circuit·Decided July 5, 2022·No. 21-2272·Unpublished

Opinion

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit

U.S. AEROTEAM, INC.,

Plaintiff-Appellant

v.

UNITED STATES, Defendant-Appellee

2021-2272

Appeal from the United States Court of Federal Claims in No. 1:18-cv-01096-MBH, Senior Judge Marian Blank Horn.

Decided: July 5, 2022

MILTON C. JOHNS, Executive Law Partners, PLLC, Fairfax, VA, argued for plaintiff-appellant.

IGOR HELMAN, Commercial Litigation Branch, Civil Division , United States Department of Justice, Washington, DC, argued for defendant-appellee. Also represented by BRIAN M. BOYNTON, LISA LEFANTE DONAHUE, PATRICIA M. MCCARTHY.

2 U.S. AEROTEAM, INC. v. US

Before LOURIE, PROST, and TARANTO, Circuit Judges.

LOURIE, Circuit Judge.

U.S. Aeroteam, Inc. (“Aeroteam”) contracted with the United States Air Force to build ground support trailers. After Aeroteam incurred additional costs building the trailers , it requested compensation from the Air Force. The Air Force denied its request. Aeroteam filed a complaint at the United States Court of Federal Claims (“the Claims Court”). The Claims Court entered judgment in favor of the United States. U.S. Aeroteam, Inc. v. United States, No. 1:18-cv-01096-MBH (Fed. Cl. 2019), J.A. 3–9. We affirm the court’s judgment for the reasons explained below.

BACKGROUND

Aeroteam is a contractor that specializes in building components for the aerospace industry. In 2009, the Air Force awarded Aeroteam a contract to produce ground support trailers. J.A. 1709–10. The Air Force uses those trailers to transport aircraft engines. J.A. 1709.

In 2011, Aeroteam began having difficulties obtaining a key component of the trailers—the running-gear subassembly . J.A. 1712. The running gear is “essentially the drive train” for the trailer, “allow[ing] [it] to roll, brake, [and] steer.” J.A. 1710. To obtain the running gears, Aeroteam relied on PDI Ground Support Systems, an approved vendor under the contract. 1 J.A. 1711–12. PDI initially charged Aeroteam $20,300 per unit. J.A. 1711. After facing financial difficulties, however, PDI raised its price. J.A. 7 (845:1–6). In response, Aeroteam decided to manufacture the running gears itself. According to Aeroteam, it could produce them “as well or better than PDI.”

1 Under the terms of the contract, Aeroteam could procure the running gears only from certain approved vendors , including PDI. J.A. 1710–11.

U.S. AEROTEAM, INC. v. US 3

J.A. 1713–14; J.A. 1861 (342:3–12); J.A. 2125. Aeroteam was also concerned that PDI could not continue to supply it with the running gears in light of its financial situation. 2 Appellant’s Br. 8. Subsequently, Aeroteam formally asked the Air Force if it could assume responsibility for manufacturing the running gears. J.A. 1714. Its request read, in relevant part, as follows:

US Aeroteam proposes to manufacture the entire running gear and brake system for TT90-F-507 Trailers Sernos 0020-0041 because PDI has refused to complete the contract as awarded.

J.A. 2125 (capitalization modified). The contracting officer approved Aeroteam’s request, stating that the manufacturing change was “acceptable.” J.A. 1715–16. On September 6, 2012, the Air Force awarded Aeroteam a second contract to produce additional trailers. J.A. 1716.

Shortly after Aeroteam began manufacturing the running gears for the trailers, it discovered that its costs were higher than it had expected. J.A. 7. As a result, Aeroteam sought to recoup those costs and filed a request for equitable adjustment in the amount of $1,385,912 for the first contract and $4,022,273 for the second contract. J.A. 29–30; Contract No. FA8526-09-C-0007 and Contract No. FA8526-12-C-0039. As relevant here, both of Aeroteam ’s contracts were “firm-fixed-price,” meaning that they “place[d]” upon Aeroteam the “maximum risk and full responsibility for all costs and resulting profit or loss.” Federal Acquisition Regulation § 16.202-1; J.A. 1710, 1716.

The contracting officer denied Aeroteam’s request for equitable adjustment. J.A. 1717. Aeroteam then filed a complaint at the Claims Court, alleging three grounds for

2 The government disputes Aeroteam’s assertion that PDI could no longer produce the running gears. We further address that argument below.

4 U.S. AEROTEAM, INC. v. US

recovery: (1) constructive change, i.e., the Air Force ordered Aeroteam, expressly or impliedly, to perform work beyond the contract requirements; (2) cardinal change, i.e., the Air Force effected an alteration in the work so drastic that it effectively required Aeroteam to perform duties materially different from those it originally bargained for; and (3) commercial impracticability, i.e., because of unforeseen events, Aeroteam could perform the contract only at an excessive and unreasonable cost or performance would be commercially senseless.

The Claims Court denied Aeroteam’s claims, issuing its decision from the bench without a subsequent written opinion . With respect to the constructive and cardinal change claims, the court held that Aeroteam had failed to prove that the Air Force ordered it to manufacture the running gears. 3 Rather, according to the court, Aeroteam independently chose to do so. J.A. 7 (846:11–13); J.A. 8 (849:1–2). With respect to the commercial impracticability claim, the court found that Aeroteam could have continued to buy the running gears from PDI, albeit at a higher price. J.A. 5 (838:14–16). The court also pointed out that, because Aeroteam had entered into a fixed-price-contract, it assumed the risk that the price of the running gears would change. J.A. 6 (840:21–841:1); J.A. 7 (846:13–15).

After concluding that Aeroteam failed to prove its claims for recovery, the court entered judgment in favor of the government. J.A. 1. Aeroteam appealed to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).

DISCUSSION

This court reviews legal determinations of the Claims Court de novo and its findings of fact for clear error. Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1373 (Fed.

3 The Claims Court discussed cardinal change in conjunction with constructive change.

U.S. AEROTEAM, INC. v. US 5

Cir. 2005) (citing Glendale Fed. Bank, FSB v. United States, 239 F.3d 1374, 1379 (Fed. Cir. 2001)). “A finding is ‘clearly erroneous’ when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” United States v. U.S. Gypsum Co., 333 U.S. 364, 395 (1948).

Aeroteam argues that the Claims Court erred in denying its claims for (1) constructive change, (2) cardinal change, and (3) commercial impracticability. We address each argument in turn.

I

We turn first to Aeroteam’s argument regarding its constructive change claim. To demonstrate a constructive change, a contractor must show “(1) that it performed work beyond the contract requirements, and (2) that the additional work was ordered, expressly or impliedly, by the government .” Bell/Heery v. United States, 739 F.3d 1324, 1335 (Fed. Cir. 2014) (emphasis added) (citing Redland Co. v. United States, 97 Fed. Cl. 736, 755–56 (2011)). The parties’ dispute centers on the second element of constructive change.

Aeroteam argues that the Claims Court erred in denying its constructive change claim. According to Aeroteam, it did not choose to manufacture the running gears. Rather , the Air Force ordered it to make that change. The government responds that Aeroteam independently chose to manufacture the running gears, with no express or implied order from the Air Force.

Free access — add to your briefcase to read the full text and ask questions with AI

U.S. Aeroteam, Inc. v. United States, (Fed. Cir. 2022).

U.S. Aeroteam, Inc. v. United States (U.S. Aeroteam, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related