Redland Co. v. United States

97 Fed. Cl. 736, 2011 U.S. Claims LEXIS 518, 2011 WL 1338188
CourtUnited States Court of Federal Claims
DecidedApril 7, 2011
DocketNo. 08-606 C
StatusPublished
Cited by30 cases

This text of 97 Fed. Cl. 736 (Redland Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Redland Co. v. United States, 97 Fed. Cl. 736, 2011 U.S. Claims LEXIS 518, 2011 WL 1338188 (uscfc 2011).

Opinion

OPINION and ORDER

BLOCK, Judge.

The ancient Romans used an extensive system of roads such as the Via Appia, the famed cobbled Appian Way, to connect their vast empire. The empire spanned at its height much of Britain, Gaul (modern day France), Italy, and other lands surrounding the Mediterranean including North Africa, and Asia Minor up to the boundaries of the Tigris and Euphrates Rivers. Truly, all roads led to Rome.

Because they were paved, these roads could withstand heavy traffic and allowed the Romans to move their Legions quickly and efficiently to wherever they were needed to ensure the empire’s security. See Logan Thompson, Roman Roads, History Today, Feb. 1997, at 21, 21-22. In order to build and maintain these roads, the Romans depended, at least in part, on masterbuilder construction workers called “redemptores” to do the digging and paving pursuant to contract. See id. at 25; Cornelius van Tilburg, Traffic and Congestion in the Roman Empire 36-39 (2007); 2 A Dictionary of Greek and Roman Antiquities 947 (William Smith et al. eds., 3d ed., London, John Murray 1891). Today, the United States military also relies on contractors, modern day re-demptores, to meet its paving needs. To be sure, these paving needs include projects well beyond those even contemplated by the ancient Romans, such as the project giving rise to the dispute in this ease — the repaving of a parking area for jet aircraft.

Plaintiff, the Redland Company, Inc. (“Redland”), filed this complaint pursuant to the Contract Disputes Act (“CDA”),1 seeking [741]*741compensation on various claims arising from a paving contract with the United States Department of the Air Force (“the Air Force”). The Air Force awarded the contract to plaintiff in October 2000. Pl.’s Resp. to Def.’s Proposed Findings of Uncontrovert-ed Fact (“Pl.’s Resp. to Def.’s Proposed Findings”) ¶ 1. The contract required plaintiff to resurface an aircraft parking area at Homestead Air Reserve Base (“HARB”) in Florida, by removing the existing asphalt and concrete and then laying new asphalt and concrete. Id.; see Compl. Ex. 1.

Performance was to begin soon after the contract award. Pl.’s Resp. to Def.’s Proposed Findings ¶ 11. However, a work-suspension order from the Air Force delayed the start of performance for nearly four years. Compl. ¶ 7. Plaintiff alleges that it is entitled to compensation as a result of this four-year suspension of performance. Id. Plaintiff further alleges that, once work began, the Air Force’s actions substantially delayed project completion, prolonging the period of performance from an anticipated sixty-one days to well over a year. Id. ¶ 14. Finally, plaintiff alleges that it was required to perform additional work, i.e., work not contemplated under the contract, for which it was either inadequately compensated or not compensated at all. Id. ¶¶ 9-13. On these facts, plaintiff asserts multiple claims against defendant.

For the sake of convenience and clarity, the court has enumerated plaintiffs various claims. These begin with a claim for compensation for unabsorbed home office overhead during the four-year period of suspension (Claim 1). Thereafter, plaintiff asserts a claim for compensation for delayed project completion (Claim 2), removal of additional asphalt (Claim 3), removal and replacement of additional concrete (Claim 4), delayed access to HARB (Claim 5), removal of unanticipated buried metal and concrete (Claim 6), repairing an electrical duet bank (Claim 7), providing finish grade elevations (Claim 8), and, finally, repairing a crack in the concrete (Claim 9). Id. ¶¶ 7-14.

Before the court are the parties’ cross-motions for summary judgment pursuant to Rule 56 of the Rules for the Court of Federal Claims (“RCFC”). Defendant seeks summary judgment on Claims 1, 2, and 3. Def.’s Mot. for Partial Summ. J. (“Def.’s Mot. for Summ. J.”) at 1. For its part, plaintiff seeks summary judgment as to liability on all nine claims found in its complaint. Pl.’s Cross-Mot. for Summ. J. on Liability (“Pl.’s Mot. for Summ. J.”) at 1-2. In addition, plaintiff seeks summary judgment as to liability on a claim for breach of contract, which is found nowhere in its complaint and is raised for the first time in the motion for summary judgment. Id. at 13. For the reasons explained below, defendant’s motion is granted as to Claims 1 and 2, but denied as to Claim 3. Plaintiffs motion is granted as to Claims 6, 7, and 8, but is denied as to all other claims.

I. BACKGROUND

On October 30, 2000, the Air Force awarded plaintiff contract number FA6648-01-C0001 (“the contract”). Compl. ¶ 1; Pl.’s Resp. to Def.’s Proposed Findings ¶ 1. As noted above, the contract required plaintiff to repave a parking area for jet aircraft at HARB. Compl. ¶ 1; Pl.’s Resp. to Def.’s Proposed Findings ¶ 1. The parking area in question (the “project site” or “work site”) is located near an alert shelter for the Florida Air National Guard (appropriately known by the warlike name of “FANG”). Pl.’s Resp. to Def.’s Proposed Findings ¶ 2. This alert shelter houses fully fueled and armed jets that can be launched on short notice to intercept aircraft posing a threat to the United States. PL’s Resp. to Def.’s Proposed Findings ¶ 4. Plaintiff was to repave a three-lane section of the parking area. See Pfoh Dep. 82:11, Oct. 7, 2009.

On December 1, 2000, plaintiff received from the contracting officer (“CO”) a “notice to proceed,” which is the CO’s authorization for a contractor to begin work on a project. PL’s Resp. to Def.’s Proposed Findings ¶ 7. The contract required plaintiff to begin performance within fourteen days of receiving the notice to proceed. Compl. Ex. 1 at 1. However, also on December 1, 2000, and paradoxically received about the same time as the notice to proceed, the CO issued a second order suspending work until further notice. Def.’s Mot. for Summ. J. Ex. F. The [742]*742stated reason for the suspension was the delayed completion of another paving project in a different section of the parking area. Pl.’s Resp. to Def.’s Proposed Findings ¶ 8; Burgains Dep. 15:5-25, Nov. 4, 2009. Because FANG needed to ensure the availability of at least one section of the parking area at all times, plaintiff could not begin work until the other paving project was completed. Burgains Dep. 17:22-18:13.

During the period of suspension, the parties had sporadic discussions about when the suspension would be lifted and work could begin. Pl.’s Resp. to Def.’s Proposed Findings ¶ 9. On August 23, 2002, plaintiffs vice president requested that the Ar Force provide thirty days notice before requiring plaintiff to begin work. Id. ¶ 9. It is uncertain whether the Air Force responded to this request. Id. Eventually, in a letter dated July 21, 2004, the CO notified plaintiff that the Ar Force intended to lift the suspension on or about September 30, 2004. See Def.’s Mot. for Summ. J. Ex. X; see also Def.’s Resp. to Pl.’s Proposed Findings of Uneon-troverted Fact (“Def.’s Resp. to Pl.’s Proposed Findings”) ¶ 5. The Air Force ultimately lifted the suspension on October 18, 2004, with work to begin on October 20, 2004, and be completed by December 19, 2004. Pl.’s Resp. to Def.’s Proposed Findings ¶ 11.

Plaintiff alleges that, on the day the suspension was lifted, it and its subcontractor were delayed from entering HARB due to security clearance problems. Compl. ¶8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jabez-Absher Small Business Joint Venture
Armed Services Board of Contract Appeals, 2025
Walsh Turner Joint Venture II
Armed Services Board of Contract Appeals, 2025
Sheffield Korte Joint Venture
Armed Services Board of Contract Appeals, 2023
Financial & Realty Services, LLC v. United States
128 Fed. Cl. 770 (Federal Claims, 2016)
Baistar Mechanical, Inc. v. United States
128 Fed. Cl. 504 (Federal Claims, 2016)
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Nova group/tutor-saliba v. United States
125 Fed. Cl. 469 (Federal Claims, 2016)
H. J. Lyness Construction, Inc. v. United States
121 Fed. Cl. 287 (Federal Claims, 2015)
Jmr Construction Corp. v. United States
117 Fed. Cl. 436 (Federal Claims, 2014)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Robert E. Pearl v. United States
111 Fed. Cl. 301 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
97 Fed. Cl. 736, 2011 U.S. Claims LEXIS 518, 2011 WL 1338188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/redland-co-v-united-states-uscfc-2011.