State of California v. United States

271 F.3d 1377, 51 Fed. Cl. 1377, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20360, 2001 U.S. App. LEXIS 25203, 2001 WL 1491579
CourtCourt of Appeals for the Federal Circuit
DecidedNovember 27, 2001
Docket01-5031
StatusPublished
Cited by42 cases

This text of 271 F.3d 1377 (State of California v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of California v. United States, 271 F.3d 1377, 51 Fed. Cl. 1377, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20360, 2001 U.S. App. LEXIS 25203, 2001 WL 1491579 (Fed. Cir. 2001).

Opinion

MICHEL, Circuit Judge.

Plaintiff-Appellant State of California appeals the judgment of the United States Court of Federal Claims holding that the Flood Control Act of 1928, codified at 33 U.S.C. § 702c (1994), immunizes the United States from breach-of-contract claims for damages arising from or related to flood control projects. Because we conclude that, to the extent sovereign immunity might otherwise apply, it has been waived by the previously-enacted Tucker Act, 28 U.S.C. § 1491 (1994), and the later *1379 enactment did not repeal the earlier by implication, we reverse, ordering judgment for the State of California, and remand for an assessment of damages.

BACKGROUND

In the mid-1950s, the State of California (“California”) and the United States, through the Department of the Interior, independently evaluated the possibility of expanding their respective water projects in the Central Valley of California. Both ultimately determined that only one, and the same, location for their respective projects was feasible. As a result, the parties began discussing a joint project. In 1960, Congress authorized the Secretary of the Interior (“Secretary”) to negotiate and enter into an agreement with California, subject to Congressional approval, for the construction of a joint-use facility. See Pub.L. No. 86^88, 74 Stat. 156 (1960) (“the San Luis Act”). The principal purpose of the San Luis Act was to furnish water for irrigation of approximately 500,000 acres of land in central California along the San Luis Unit, with contemplated incidental use for, among other things, recreational and fish and wildlife benefits. Id.

The Secretary exercised his congressionally granted authority on behalf of the United States, reaching an agreement with California in December 1961 (“the 1961 Contract”); the parties also entered into a Supplemental Agreement in 1972. The 1961 Contract provided that the United States would construct the joint-use facility and thereafter turn it over to California for operation and maintenance. Notably, it further provided that:

The United States and the State shall each pay annually an equitable share of the operation, maintenance, and replacement costs of the joint-use facilities, including claims paid by either party. The method of computation of the share to be paid by each agency shall be mutually agreed to by the State and the United States before the transfer of care, operation, and maintenance of joint-use facilities.

Before California began operating the joint-use facility, the parties agreed that the costs would be equitably apportioned as follows: California would cover 55% of the costs identified in the blocked excerpt above, and the United States would cover the remaining 45%.

Under San Luis Act § 2, the 1961 Contract became effective after the contract had been before Congress for ninety days, and was not disapproved by either the House or the Senate Interior and Insular Affairs Committees. See 87 Cong. Rec. 12,435 (July 2, 1962) (statement of Sen. Miller). In 1967, the United States Bureau of Reclamation completed construction of the San Luis Unit, a 102 mile canal that transports water from Northern California through the Central Valley to Southern California. Importantly, the canal crosses the path of several transitory streams such that, in times of heavy rainfall, water from those streams is diverted onto neighboring landowners’ property. As a result, between 1969 and 1993, the United States and California made payments totaling over $7 million, all related to damage from flood waters from such diversions. Each time, the parties paid their agreed-upon share of the claim— until March 1995.

In March 1995, a large storm caused a massive overflow of the transitory stream beds, causing property damage in excess of $5.3 million. Over the next four years, California paid many claims seeking corn *1380 pensation for this damage. When it sought partial reimbursement, however, the United States asserted — for the very-first time — that - it was not required to contribute its share because it was immune under the Flood Control Act of 1928, 33 U.S.C. § 702c.

California sued the United States for breach of contract in the Court of Federal Claims. The parties stipulated to the facts recounted above and cross-moved for summary judgment, agreeing that resolution of the suit turned on whether the cause of action was barred by the doctrine of sovereign immunity. Eschewing oral argument, the Court of Federal Claims granted the United States’ motion, denied California’s motion, and entered judgment for the United States. California v. United States, 47 Fed.Cl. 688 (2000). In reaching its decision, the court concluded that no liability could attach because the Flood Control Act covers all damage from floods and flood waters, and the San Luis Unit “was designed from its inception as a flood control project.” Id. at 696. And it was persuaded that, in light of the broad, sweeping language of the Flood Control Act, the 1961 Contract and its 1972 Supplement were entered into ultra vires, such that the section of those contracts requiring the United States to partially reimburse California for claims paid for flood damage arising from floods or flood waters was of no force or effect. Id. at 698 (“Regardless of whether the 1961 Contract and the 1972 Supplement contemplated the sharing of cost of flood claims, this court cannot enforce terms, whether freely negotiated or not, which are in violation of a congressionally-enacted statute [T]he conduct of the parties [is irrelevant because] an agency cannot ratify an arrangement which violates federal law.”).

Final Judgment was entered in favor of the United States on September 26, 2000, after which California timely filed its Notice of Appeal. We heard oral argument on October 2, 2001. The appeal is now ripe for disposition.

ANALYSIS

I.

We review a grant of summary judgment de novo, employing an identical standard to that applied by the trial court. Wolff Shoe Co. v. United States, 141 F.3d 1116, 1121 (Fed.Cir.1998). The mere -fact that the parties have cross-moved for summary judgment does not impel a grant of at least one motion; each must be independently assessed on its own merit. Ecolab, Inc. v. Envirochem, Inc., 264 F.3d 1358, 1364 (Fed.Cir.2001). Accordingly, summary judgment is appropriate here if, drawing all inferences in a light most favorable to the non-movant, there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-52, 106 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Milton v. United States
Federal Circuit, 2022
Boyer v. United States
Federal Claims, 2022
Ology Bioservices, Inc.
Armed Services Board of Contract Appeals, 2021
Glenn-Colusa Irrigation District v. United States
129 Fed. Cl. 593 (Federal Claims, 2016)
In re the Complaint of Ingram Barge Co.
194 F. Supp. 3d 766 (N.D. Illinois, 2016)
Mendez v. United States
121 Fed. Cl. 370 (Federal Claims, 2015)
Kibler v. United States
46 F. Supp. 3d 844 (C.D. Illinois, 2014)
Big Oak Farms, Inc. v. United States
105 Fed. Cl. 48 (Federal Claims, 2012)
Cardiosom, LLC v. United States
656 F.3d 1322 (Federal Circuit, 2011)
Lummi Tribe of the Lummi Reservation v. United States
99 Fed. Cl. 584 (Federal Claims, 2011)
Redland Co. v. United States
97 Fed. Cl. 736 (Federal Claims, 2011)
Bussie v. United States
96 Fed. Cl. 89 (Federal Claims, 2011)
Fischer v. United States
96 Fed. Cl. 70 (Federal Claims, 2011)
U.S. Home Corp. v. United States
92 Fed. Cl. 401 (Federal Claims, 2010)
Resource Investments, Inc. v. United States
85 Fed. Cl. 447 (Federal Claims, 2009)
Enron Federal Solutions, Inc. v. United States
80 Fed. Cl. 382 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
271 F.3d 1377, 51 Fed. Cl. 1377, 32 Envtl. L. Rep. (Envtl. Law Inst.) 20360, 2001 U.S. App. LEXIS 25203, 2001 WL 1491579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-california-v-united-states-cafc-2001.