Glenn-Colusa Irrigation District v. United States

129 Fed. Cl. 593, 2016 U.S. Claims LEXIS 1928, 2016 WL 7406447
CourtUnited States Court of Federal Claims
DecidedDecember 22, 2016
Docket15-1572C
StatusPublished
Cited by1 cases

This text of 129 Fed. Cl. 593 (Glenn-Colusa Irrigation District v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glenn-Colusa Irrigation District v. United States, 129 Fed. Cl. 593, 2016 U.S. Claims LEXIS 1928, 2016 WL 7406447 (uscfc 2016).

Opinion

Subject matter jurisdiction; Flood Control Act of 1970; divestment of Tucker Act jurisdiction

OPINION

FIRESTONE, Senior Judge.

Plaintiff, Glenn-Colusa Irrigation District (“GCID”), brought this action on December 23, 2015 invoking this court's jurisdiction under the Tucker Act, 28 U.S.C. 1491(a)(1) and seeking damages from the United States for an alleged breach of a cost-sharing agreement between GCID and the United States Army Corps of Engineers (“Corps”). Under the terms of the cost-sharing agreement, the Corps, “subject to receiving funds appropriated by the Congress of the United States ... and using those funds and funds provided by [GCID] ” agreed to construct the Riverbed Gradient Facility Project for the Sacramento River at the GCID intake. Mot. to Dismiss at A4. GCID claims that the Corps violated the cost-sharing agreement by failing to properly build the riverbed gradient facility.

The government has filed a motion to dismiss pursuant to Rule 12(b)(1) of the Rules of the Court of Federal Claims (“RCFC”) in which it argues that the court lacks jurisdiction over the dispute based on Section 221 of the Flood Control Act of 1970, 42 U.S.C. § 1962d-5b(c). Section 221 states as follows: “Enforcement; jurisdiction. Every agreement entered into pursuant to this section shall be enforceable in the appropriate district court of the United States.” The government argues that Section 221 vests an appropriate distinct court with exclusive jurisdiction over GCID’s breach of contract claim and therefore the case before this court must be dismissed.

The government’s motion is fully briefed and oral argument was held on December 20, 2016. For the reasons discussed below, the motion to dismiss is GRANTED.

*595 I. BACKGROUND

The following facts are taken from GCID’s complaint and for purposes of this motion are not disputed. GCID is an irrigation district diverting water from the Sacramento River pursuant to water rights perfected under California law prior to 1900. Compl. ¶ 3. As a result of litigation concerning impacts on winter-run salmon from GCID irrigation diversions, GCID and federal and state agencies agreed to jointly develop a long-term solution to address both protection of fishery resources and ensuring a reliable water supply for GCID. Id. ¶¶ 11-14. The solution was a Fish Screen Project consisting of two essential components: (1) a fish screen extension (fish screen) and (2) a Riverbed Gradient Facility for the Sacramento River at the GCID irrigation diversion intake (Gradient Facility). Id. ¶ 16.

The fish screen was authorized by Congress, built by the United States Bureau of Reclamation, and was turned over to GCID, which assumed ownership and responsibility for its operation, maintenance, and repair in 2011. Id. ¶¶ 17-19. The fish screen is in operation today and operates as intended. Id.

Congress originally authorized the Gradient Facility in 1990. Id. ¶ 20. The Gradient Facility was designed to mimic a natural riffle in the river in order to accommodate the passage of fish and boats. Id. ¶ 25. The increased water surface elevations provided by the Gradient Facility during low flows were intended to increase sweeping flows past the fish screen and to improve the overall performance of the Fish Screen Project. Id. Authorization for the Gradient Facility was modified several times, with Congress authorizing a total cost of $14,200,000 in 1996, a total cost of $20,700,000 in 1998, and finally a total cost of $26,000,000 in 1999. Id. ¶¶ 21-23.

GCID entered into a Project Cooperation Agreement (“Agreement”) with the Corps for the Gradient Facility in 1999. Id. ¶ 28. The Agreement set forth the responsibilities of GCID and the Corps with respect to cost sharing, construction, and operation and maintenance of the Gradient Facility. Id. ¶34. The Agreement provided that design and construction of the Gradient Facility would be the responsibility of the Corps and the Corps was required to “expeditiously construct the Project _” Id. ¶35. GCID was responsible for contributing a minimum of 25 percent of the total project costs. Id. ¶36. Upon completion of the project, the Agreement provided that GCID would assume responsibility for the operation, maintenance, repair, replacement, and rehabilitation of the project. Id. ¶ 42.

The Agreement included a provision dealing with potential damages from faulty construction. It required GCID to indemnify the Corps from “all damages arising from the construction, operation, maintenance, repair, replacement, and rehabilitation of the Project and any Project-related betterments, except for damages due to the fault or negligence of the Government or its contractors.” Id. ¶ 45 (emphasis added). The Agreement also included a dispute resolution provision. Mot. to Dismiss at A14.

GCID alleges that almost immediately after construction was completed in 2000, defects associated with the Gradient Facility were observed. Id. ¶ 52-53. The Corps convened a team of experts, known as the “Gradient Facility Blue Ribbon Panel,” in August 2008, to assess the design of the Gradient Facility and recommend correction of any deficiencies. Both prior to and following release of the Blue Ribbon Panel Report, GCID alleges that it repeatedly tried to get the Corps to address the Gradient Facility’s defects. Id. ¶¶ 74-85. GCID alleges the defects were not addressed but that on March 22, 2013 the Corps notified GCID that construction of the Gradient Facility was “complete” and transferred responsibility for the Gradient Facility to GCID. Id. ¶ 86.

GCID alleges that the Gradient Facility has degraded as a result of the Corps’ failure to address its design and construction deficiencies. GCID contends that it has incurred, and will continue to incur, substantial costs because of the Corps alleged failure to fulfill its contractual obligations. Id. ¶¶ 91-93. GCID claims that by failing to address the design and construction defects associated with the Gradient Facility, the Corps has breached its contractual duties to GCID. *596 GCID further alleges that its attempt to resolve the dispute under the dispute resolution provision of the Agreement has failed and thus its breach of contract claims are ripe for adjudication.

GCID filed the present action on December 23, 2015 and the government filed its motion to dismiss on April 7, 2016, arguing that this court lacks jurisdiction over the dispute. Briefing on the government’s motion is complete and oral argument was,heard on December 20, 2016. The matter is now ripe for disposition.

II. DISCUSSION

A. Standard of Review

This case comes before the court on the government’s motion to dismiss for lack of jurisdiction pursuant to RCFC 12(b)(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
129 Fed. Cl. 593, 2016 U.S. Claims LEXIS 1928, 2016 WL 7406447, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glenn-colusa-irrigation-district-v-united-states-uscfc-2016.