Nova group/tutor-saliba v. United States

125 Fed. Cl. 469, 2016 U.S. Claims LEXIS 198, 2016 WL 1056794
CourtUnited States Court of Federal Claims
DecidedMarch 16, 2016
Docket15-885C
StatusPublished
Cited by5 cases

This text of 125 Fed. Cl. 469 (Nova group/tutor-saliba v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nova group/tutor-saliba v. United States, 125 Fed. Cl. 469, 2016 U.S. Claims LEXIS 198, 2016 WL 1056794 (uscfc 2016).

Opinion

Rule 12(b)(6); Motion to Dismiss; Constructive Change; Timely Written Notice; FAR 52.243-4; Actual Notice; Extenuating Circumstances Excusing Timely Written Notice.

OPINION AND ORDER

WILLIAMS, Judge.

This Contract Disputes Act case comes before the Court on Defendant’s motion to dismiss for failure to state a claim upon which relief can be granted. Plaintiff, a joint venture, entered into a contract with the Naval Facilities Engineering Command (“NAVFAC”), a component of the United States Navy, to design and build a pier at the Puget Sound Navy Shipyard in Bremerton, Washington. Plaintiff alleges two constructive changes and seeks $1,881,900, plus interest.

Defendant argues that Plaintiffs claim is barred because Plaintiff failed to give written notice of its constructive change claim within 20 days as required by FAR 52.243-4. Because Plaintiff has plausibly alleged that the Government had actual knowledge of the facts giving rise to its changes claim, Defendant’s motion to dismiss is denied.

Background.

On May 2, 2008, NAVFAC awarded Contract No. N44255-08-C-6000 to Plaintiff Nova Group/Tutor-Saliva (“NTS”). Compl. 1. The contract encompassed the design and construction of a new ship repair wharf (“Pier B”) at the Puget Sound Navy Shipyard in Bremerton, Washington. NTS was required to complete work within 1,345 calendar days, and the contract included a liquidated damages clause imposing $35,475 per day for delay past the contract deadline. Id. at ¶¶ 8,10.

The contract granted NTS and its subcontractors discretion in choosing the method of analyzing forces upon the pier’s piles. Id. at ,¶ 20. The “Designer of Record” for NTS, KPFF Consulting (“KPFF”), selected the American Concrete Institute Building Code Requirement for Structural Concrete, 2005 version (“ACI 318-05”) and chose to analyze and confirm global stability using ACI 318-05, Section 10.13.6(a). NTS transmitted four design submittals to NAVFAC at various phases, and NAVFAC in turn provided NTS with 382 design review comments. Id. at ¶¶ 23-24. None of NAVFAC’s 382 design review comments addressed the global stability of Pier B’s piles or the NTS designer’s choice of determining global stability using ACI 318-05, Section 10.13.6(a). Id. at ¶ 25. NAVFAC approved the last of NTS’s Pier B design submissions on November 12, 2009, including the structural design of Pier B. Id. at ¶ 26.

More than five months after the last design was approved, NAVFAC’s construction manager, in a March 8, 2010 letter, questioned NTS’s design compliance with the contract, stating:

Based on the attached BergerABAM correspondence dated 12 February 2010, the Navy has concerns that the final approved design, relying heavily upon a SAP 2000 model with respect to the performance design loads, may not be in conformance with the RFP when considering global stability and the observed out of tolerance piles.

Id. at ¶ 41, Ex. 2.

The cited memorandum from the Government engineer, BergerABAM, questioned *471 KPFF s chosen analytics method, stating in pertinent part:

ISSUES RELATED TO EFFECTIVE LENGTH FACTORS There are three related issues that became the focus of our review of the use of effective length factors for Pier B.
* sfc %
3. The design approach did not include a check for overall stability of Pier B for load combinations based on the RFP provisions. Use of provisions from the 2005 Building Code Requirements for Structural Concrete by the American Concrete Institute (ACI 318-05) is a design requirement for Pier B and addresses stability. Reference to ACI 318-05 as a design requirement is found in the basis of design by KPFF.
KPFF maintains the evaluation of ACI 318-05 Section 10.13.6a demonstrates the pier satisfies sidesway buckling under gravity load condition. However, this particular provision is based on results from an analytical model, which is susceptible to the accuracy of the input properties of geometry and structural characteristics of the physical system. Consequently, Ber-gerABAM contends Chapter 10.13.6c is the more appropriate provision because the geometric properties can be verified, are more apparent, and are directly related to Euler buckling (global instability.) With this evaluation, it appears to satisfy properties generally associated with good engineering practice only under favorable conditions of structural properties.

Id. at Ex. 2.

NAVFAC in its March 8th letter did not direct NTS to stop construction , on the Pier. Id. at Ex. 2. However, on the same day, NTS stopped operations and began re-evaluating the Government-approved design. Id. at ¶¶ 44-45. NTS claims that if it had continued construction and the Government’s concerns had proven valid, “then NTS could have faced extensive additional corrective construction work.” Id. at Ex. 1; Pl.’s Resp. 5. NTS argued that “no reasonably prudent contractor would continue with critical construction in the face of such a notice from the Navy.” Compl. Ex. 1. NTS alleges that the Government “knew that NTS had stopped performing critical Pier B construction work” during this re-analysis of the Government-approved design. Id. at ¶46. Between March 8 and May 27, 2010, NTS and KPFF participated in meetings with the Government and “furnished detailed reports substantiating NTS’s original design.” Id. at ¶ 45,

During this period of reanalysis, KPFF hired an independent third-party designer to evaluate the initial Government-approved design. The designer, Ben C. Gerwick, Inc., concluded both that the design satisfied the requirements of the RFP and that ACI 318-05 Section 10.13.6(a) was an appropriate design method. Id. at ¶ 49.

On May 27, 2010, the Government sent NTS a letter containing a second BergerA-BAM memorandum concluding that the design of Pier B “adequately addressed global stability issues” and finding that it was “technically sufficient” to only consider ACI 318-05, Section 10.13.6(a) and not Section 10.13.6(c). Id. at ¶ 56. NTS resumed work the same day. Id. at ¶ 61.

NTS claims a constructive change based on NAVFAC’s decision to question the global stability of Pier B design, due to Government misinterpretation of the Contract Documents — an “incorrect assumption that NTS had relied on the wrong ACI standard in its global stability calculations.” Id. at ¶ 58. NTS further claims misinterpretation of the Contract Documents through NAVFAC’s “decision to require NTS to re-evaluate the Pier B pile design based on the unfounded concern that NTS (through KPFF) had not initially evaluated or designed for global stability in accordance with the correct ACI standard;” Id. at ¶ 98.

After May 27, 2010, NTS attempted to mitigate construction delays, impacts, and inefficiencies by accelerating the remaining Pier B construction work, adding manpower and equipment and providing for “significant levels of overtime.” Id. at ¶¶ 63-64.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
125 Fed. Cl. 469, 2016 U.S. Claims LEXIS 198, 2016 WL 1056794, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nova-grouptutor-saliba-v-united-states-uscfc-2016.