Calfon Construction, Inc. v. United States

35 Cont. Cas. Fed. 75,651, 17 Cl. Ct. 171, 1989 U.S. Claims LEXIS 104, 1989 WL 59516
CourtUnited States Court of Claims
DecidedJune 6, 1989
DocketNo. 792-87C
StatusPublished
Cited by12 cases

This text of 35 Cont. Cas. Fed. 75,651 (Calfon Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calfon Construction, Inc. v. United States, 35 Cont. Cas. Fed. 75,651, 17 Cl. Ct. 171, 1989 U.S. Claims LEXIS 104, 1989 WL 59516 (cc 1989).

Opinion

[172]*172ORDER

NETTESHEIM, Judge.

This case is before the court on defendant’s motion for summary judgment emanating from a motion to dismiss for failure to state a claim upon which relief can be granted. Plaintiff has opposed and argument has been held. At argument the court ruled that defendant’s motion should proceed under RUSCC 56. Defendant supplied its statement of uncontested material facts and renewed its summary judgment motion on additional grounds. Plaintiff once again has opposed. Further argument is deemed unnecessary.

FACTS

The record is rife with disputed issues of material fact. However, because one salutary purpose of summary judgment is to narrow issues for trial, see RUSCC 56(e), the court welcomes the opportunity to separate at least some wheat from the chaff. Except as noted, the following facts are undisputed. On September 30, 1983, Cal-fon Construction, Inc. (“plaintiff”), was awarded fixed-price contract No. N62474-83-C-2349 calling for concrete paving of the Hangar 300 aircraft apron located at the Naval Air Station in Fallon, Nevada (“Fallon”). The Invitation for Bids issued on August 19, 1983, contained the following Description of Work:

The work includes the furnishing of all labor, materials and equipment for demolition and removal, earthwork, storm drainage system, portland cement stabilized base course, asphalt concrete pavement, portland cement concrete pavement, cast-in-place concrete, joints, reinforcement and mooring eyes in concrete pavements, resealing in rigid pavements, pavement markings, concrete repairs, metal work, air start compressed air system, underground electrical work, airfield lighting, cathodic protection and incidental related work.

The contract price was $2,599,280. According to plaintiff’s President Vincent DeBel-lis, the scope of the work consisted of the following:

First, cut trenches in the existing port-land cement concrete (PCC) aircraft parking apron and install underground air lines, electrical ducts, manholes, catch basins, drain lines, and aircraft service console risers. Second, backfill to the level of existing concrete apron surface. Third, overlay the entire old concrete apron, including areas of trenching, with a one inch asphalt concrete (A.C.) bond breaker. Fourth, place an eight inch PCC overlay on top of the A.C. bond breaker over the entire apron. Fifth, install miscellaneous taxi-weight throats, shoulders, lighting and stripping____

Declaration of Vincent DeBellis, Feb. 14, 1989, ¶ 3. The contract drawings reflected a grading plan, finished elevations, and the typical overlay for the Hangar 300 apron. Drawing C-4 contained the finished elevation and contour grades to be met by the contract. Drawing G-13 depicted a typical finished concrete section showing an eight-inch PCC overlay.

Plaintiff proceeded to perform the contract in conformance with the contract specifications. A one-inch A.C. bond breaker was installed over the entire apron in conformance with the plans and specifications. Subsequent to the installation of the A.C. bond breaker and prior to commencing work on the PCC overlay, rain ensued. Plaintiff discovered that puddling had developed on the one-inch A.C. bond breaker. Plaintiff viewed the puddling as excessive and unsatisfactory. If plaintiff poured the PCC overlay to conform to the A.C. bond breaker, the same pattern of puddling would occur on the finished surface.

The General Provisions of the contract included paragraph 62(a), the contractor’s “Warranty of Construction:”

In addition to any other warranties set out elsewhere in this contract, the Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material or design furnished, or workmanship performed by the Contractor or any of his subcontractors or suppliers at any tier. Such warranty shall continue for a period of one [173]*173year from the date of final acceptance of the work, but with respect to any part of the work which the Government takes possession of prior to final acceptance, such warranty shall continue for a period of one year from the date the Government takes possession. Under this warranty, the Contractor shall remedy at his own expense any such failure to conform or any such defect____

Paragraph 62(f) identifies the situation where the defect is not the fault of the contractor or subcontractor:

Notwithstanding any other provision of this clause, unless such a defect is caused by the negligence of the Contractor or his subcontractors or suppliers at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government, nor for the repair of any damage which results from any such defect in Government furnished material or design.

(Emphasis added.)

Prior to commencing work on the concrete overlay, plaintiff commissioned an independent survey by the firm of Thompson & Hysell. The survey concluded that in order to meet the contours specified in Drawing C-4, different areas would require differing amounts of concrete. Drawing C-4 required paving to the contours, while Drawing C-13 required a uniform eight-inch thickness over the entire PCC overlay. Drawing C-4 shows a variation in contour elevations from 33.0 to 36.5 degrees. In order to create drainage lines, the elevations fluctuated from increases in elevation followed by decreases. Drawing C-13 shows typical details of the contractor’s work requirements. The details call for a uniform eight-inch PCC overlay.

According to Lt. Steven J. Markey, the Navy’s Assistant Resident Officer in Charge of Construction at Fallon, sometime after the contract starting date of July 1, 1985, Mr. DeBellis, along with Harold Lien, plaintiff’s Project Superintendent, and Murray Morin, the Quality Control Representative on the contract, informed the office of the Resident Officer in Charge of Construction (the “ROICC”) that there was a discrepancy in the contract drawings. Declaration of Lt. S.J. Markey, May 23, 1988, If 4. Mr. Morin asserts that he, not a representative of plaintiff, first alerted Lt. Markey to the problem, which he said was not apparent from the contract plans and specifications and characterized as variations in the elevations. Declaration of Murray Morin, May 30, 1989, ¶¶ 2-3. Mr. Lien informed Lt. Markey that in order to perform the concrete work to the finished contours, additional concrete would be required, which would increase the cost of performance. Markey Decir. If 4. Lt. Markey and, by deposition, Roy B. Smith, a Navy civil engineer working for the ROICC, take the position that Mr. Lien said to Mr. Smith that plaintiff had bid the job on the basis of paving to the contours. Markey Decir. ÍI6. Mr. Lien denies having made the statement. Declaration of Harold Lien, May 23, 1989, ¶ 4. The Daily Report of September 26,1984, proffered by defendant, is not consistent with an admission by Mr. Lien as to how plaintiff bid the contract. The remarks attributed to Mr. Lien merely disclose that “Brutoco [Bruto-co Engineering & Construction, Inc., plaintiff’s subcontractor] was planning to pave apron to contours.”

On September 25, 1985, Lt. Markey orally informed plaintiff that a concrete overlay of eight inches as shown in Drawing C-13 would be acceptable. Markey Decir. H 5. According to Lt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
Delhur Industries, Inc. v. United States
95 Fed. Cl. 446 (Federal Claims, 2010)
Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Engineered Demolition, Inc. v. United States
70 Fed. Cl. 580 (Federal Claims, 2006)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
SIPCO Services & Marine Inc. v. United States
42 Cont. Cas. Fed. 77,277 (Federal Claims, 1998)
North Star Alaska Housing Corp. v. United States
39 Cont. Cas. Fed. 76,607 (Federal Claims, 1993)
J.F. Allen Co. & Wiley W. Jackson Co. v. United States
37 Cont. Cas. Fed. 76,268 (Court of Claims, 1992)
IBI Security Service, Inc. v. United States
35 Cont. Cas. Fed. 75,740 (Court of Claims, 1989)
Calfon Construction Inc. v. United States
35 Cont. Cas. Fed. 75,738 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,651, 17 Cl. Ct. 171, 1989 U.S. Claims LEXIS 104, 1989 WL 59516, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calfon-construction-inc-v-united-states-cc-1989.