G.M. Shupe, Inc. v. United States

32 Cont. Cas. Fed. 72,712, 5 Cl. Ct. 662, 1984 U.S. Claims LEXIS 1354
CourtUnited States Court of Claims
DecidedJuly 31, 1984
DocketNo. 386-79C
StatusPublished
Cited by77 cases

This text of 32 Cont. Cas. Fed. 72,712 (G.M. Shupe, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G.M. Shupe, Inc. v. United States, 32 Cont. Cas. Fed. 72,712, 5 Cl. Ct. 662, 1984 U.S. Claims LEXIS 1354 (cc 1984).

Opinion

OPINION

LYDON, Judge:

In this construction contract case, plaintiff seeks to recover damages on behalf of itself and on behalf of Continental Drilling Company (Continental), its subcontractor, from defendant arising out of its construction of the Nambe Palls Dam in New Mexico for the Bureau of Reclamation, Department of the Interior (BOR). Plaintiff filed its petition (complaint) in this court as a direct access ease under section 10(a)(1), (3) of the Contract Disputes Act of 1978, codified at 41 U.S.C. § 609 (1982). Plaintiff advances five separate theories of recovery in claiming some $4 million as damages it incurred in construction of the Nambe Falls Dam. Defendant has raised a number of defenses, legal and factual, to the various damage claims asserted by plaintiff, and, in addition, has asserted a counterclaim in its amended answer against plaintiff in which it seeks to recover $78,922.75 which defendant claims it mistakenly paid plaintiff as contract proceeds.

I.

After trial on the merits and the compilation of a voluminous trial record, the par[669]*669ties filed detailed and extensive proposed findings of fact and expansive briefs, which were followed by oral argument. Plaintiff has presented ten separate claims. It is clear that six of the claims represent claims by plaintiff itself. It is also clear that two of the claims represent claims by plaintiff on behalf of Continental. As to one of the remaining two claims, it seems clear that this claim represents claims by both plaintiff and Continental. As to the other remaining claim the record is most confusing as to whether the claim is that of the plaintiff alone or whether it also includes a claim by Continental. The manner in which the claims and attendant proof and defenses were presented created some confusion and difficulty for the court. For example, the parties were unable to agree on whether certain claimed damages belonged under one claim category or another. The record, as constructed, provides little help in resolving the matter. Again, Continental presented its claim for damages primarily on the total cost theory, but it did break out specifically the individual amounts it sought for two separate claims. However, neither the record nor the parties provided much help to the court in breaking out other claims Continental asserts under the total cost wrapper.

The following facts, which are specifically found by the court, are herein set forth by way of background in order to place discussion and consideration of the various claims asserted by plaintiff and Continental in proper perspective. Additional facts, specifically found by the court, will be set forth when each claim is discussed and ruled upon infra.

Plaintiff, incorporated in the State of Washington, was formed in 1972 by Gerald M. Shupe (G. Shupe). Plaintiff was owned and managed by G. Shupe, Michael Quinn and Larry Campbell (Campbell). Prior to the formation of plaintiff, G. Shupe and Quinn had extensive experience in the construction of dams. Both also had long experience in negotiating claims arising out of construction contracts. Continental, a California corporation, also had many years of experience in performing drilling and grouting work on dam structures. At time of trial, Richard O. Thies (Thies) was president and general manager of Continental. Thies had a degree in geology and had been with Continental since the early 1940’s, working his way up the company ladder from drill helper to president. Thies was experienced in drilling and grouting work and in estimating work related thereto.

On June 11, 1974, plaintiff was awarded a contract by BOR to construct the Nambe Falls Dam. The work site was about 25 miles north of Sante Fe, New Mexico. Five bids were received by BOR relative to this work. Plaintiff’s low bid, which was accepted, was $5,119,753. Of the remaining four bids, the lowest was $5,475,000 and the highest was $6,368,587. BOR’s estimate for performing the contract was $4,777,507. While the relative closeness of the government’s estimate and the second lowest bid suggests that plaintiff’s bid should be considered reasonable without more, the fact that plaintiff’s bid anticipated completing the job 6 months earlier than the required completion date set forth in the contract suggests an overly optimistic approach to the contract, especially in light of the information contained in the pre-bid information made available to bidders regarding the geology, and the rock and soil conditions of the work site.

The contract in question contained the usual General Provisions found in federal government construction contracts, e.g., Specifications and Drawings (Article 2), Changes (Article 3), Differing Site Conditions (Article 4), Damages For Delay (Article 5), Disputes (Article 6), Payments to Contractor and release from contractor (Article 7) and Suspension of Work (Article 23). The contract also contained specific provisions related to the nature of the contract, i.e., dam construction. For example, section 4.1.2 (Open-Cut Excavation, General) and section 4.1.3 (Excavation, All Classes, For Concrete Arch Dam And Thrust Block). In the contract, BOR estimated the amount of anticipated excavation under bid item 39 to be 20,000 cubic yards, [670]*670and estimated that use of 21,250 bags of grout should be anticipated in performing the pressure grouting work required under bid item 17.

Information concerning the geology of the dam site and the rock and soil conditions at the dam site was available to bidders. This information indicated that difficulties were to be expected in drilling in the rocks and formation of the work site, with rock breakage and cavings clearly to be anticipated. G. Shupe testified that this information provided an excellent and clear description of what was encountered by plaintiff during construction of the dam. Plaintiff does not contend that any of its claims result from differing site conditions. On the other hand, Continental does contend that it encountered a differing site condition in performing its drilling and grouting work. The record, however, will not support this contention by Continental. The court finds that the pre-bid information furnished bidders clearly described the actual conditions that were encountered at the work site.

Plaintiff was given notice to proceed with the contract work on June 13, 1974. Work on the dam commenced on June 20, 1974. BOR accepted the contract work as substantially complete on April 13, 1976, the original contract completion date.

Nambe Palls Dam, as constructed, is a composite structure consisting of a prestressed concrete thin arch dam, a concrete thrust block, and an earth embankment dam. In effect, the thrust block joins the concrete and earth dams; it forms the left abutment for the concrete thin arch dam and the right abutment for the earth dam. An uncontrolled overflow spillway occupies the top central portion of the thin arch dam. The spillway is designed to traject discharges downstream and away from the thin arch dam. A small outlet works, located in the lower portion of the thin arch dam, is designed to provide for the downstream river requirements.

The prestressed concrete thin arch dam is located in a small gorge of the Rio Nambe. The thin arch dam is about 320 feet long and has a maximum height of 150 feet. The right abutment of the thin arch dam is keyed into the foundation rock.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BCI Construction USA, Inc.
Armed Services Board of Contract Appeals, 2024
Goodloe Marine, Inc.
Armed Services Board of Contract Appeals, 2023
Baker DC, LLC v. Baggette Constr., Inc.
378 F. Supp. 3d 399 (D. Maryland, 2019)
Merrick Construction, LLC
Armed Services Board of Contract Appeals, 2018
Dobyns v. United States
118 Fed. Cl. 289 (Federal Claims, 2014)
K-Con Building Systems, Inc. v. United States
115 Fed. Cl. 558 (Federal Claims, 2014)
SUFI Network Services, Inc. v. United States
108 Fed. Cl. 287 (Federal Claims, 2012)
Quinn Construction, Inc. v. Skanska USA Building, Inc.
730 F. Supp. 2d 401 (E.D. Pennsylvania, 2010)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Mactec, Inc. v. Bechtel Jacobs Company, LLC
346 F. App'x 59 (Sixth Circuit, 2009)
Alli v. United States
83 Fed. Cl. 250 (Federal Claims, 2008)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
Spodek v. United States
73 Fed. Cl. 1 (Federal Claims, 2006)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
Hi-Shear Technology Corp. v. United States
53 Fed. Cl. 420 (Federal Claims, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 72,712, 5 Cl. Ct. 662, 1984 U.S. Claims LEXIS 1354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gm-shupe-inc-v-united-states-cc-1984.