Joseph Bell, Sophie Karp, Hyman M. Oberman, Lena Smith, the Rainier Company, Inc., a Dissolved Corporation v. The United States

404 F.2d 975, 186 Ct. Cl. 189, 1968 U.S. Ct. Cl. LEXIS 189
CourtUnited States Court of Claims
DecidedDecember 13, 1968
Docket384-65
StatusPublished
Cited by47 cases

This text of 404 F.2d 975 (Joseph Bell, Sophie Karp, Hyman M. Oberman, Lena Smith, the Rainier Company, Inc., a Dissolved Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph Bell, Sophie Karp, Hyman M. Oberman, Lena Smith, the Rainier Company, Inc., a Dissolved Corporation v. The United States, 404 F.2d 975, 186 Ct. Cl. 189, 1968 U.S. Ct. Cl. LEXIS 189 (cc 1968).

Opinion

OPINION

PER CURIAM: *

Plaintiffs 1 seek review of a decision by the Armed Services Board of Contract Appeals, ASBCA No. 3565, in which the appeal of The Rainier Company, Inc. (Rainier) from an adverse decision by the contracting officer was denied. They allege that the Board’s decision was arbitrary, capricious, and unsupported by substantial evidence and contend that they are entitled to either damages or an equitable adjustment in the sum of $115,-900.22 under a contract between Rainier and defendant, acting through the Ordnance Corps, Department of the Army.

The contract, dated March 20, 1953, called for the manufacture of 62,552 bomb parachutes at a price of $67.628 per unit or a total contract price of $4,230,-266.60 2 By a contract modification, the original delivery schedule was changed to provide for delivery of a pilot lot of parachutes in October 1953, and for monthly deliveries beginning in February 1954, at the rate of 5,500 units per month until anticipated completion in January 1955. Article 37 of the contract contained a so-called “broad form” of “Changes” clause of the type published in paragraph 7-103.2d of the Army Procurement Procedure, which read in pertinent part as follows:

The Contracting Officer may at anytime, by a written order, and without notice to the sureties make changes of any one or more of the following types: — (a) changes in the directions as to shipment and packing of any supplies ; (b) increases or decreases in the quantity of supplies to be furnished hereunder, the total increases, in the aggregate, in the quantity of said supplies not, however, to exceed 62,552 and the total decreases, in the aggregate, in the quantity of said supplies not, however, to exceed 6,255; (c) changes in the drawings or specifications, where the supplies to be furnished are to be specially manufactured in accordance with the drawings and specification; (d) extensions of the delivery schedules hereunder reducing the rate of deliveries of the supplies called for by this contract; or (e) accelerations of the delivery schedules hereunder by an increase or increases in the rate of deliveries hereunder. Unless consented to in writing by the Contractor, no change orders hereunder of the type mentioned in clause (d) of the preceding sentence shall cause decreases in the deliveries hereunder, and no change orders of the type mentioned in clause (e) of such sentence *977 shall cause increases in the deliveries called for hereunder, amounting respectively in the aggregate in any one month to more than 550 (Decrease) and/or 5,500 (Increase) the delivery of which is called for by this contract. If such changes cause an increase or decrease in the amount of work under this contract or in the cost of performance of this contract or in the time required for its performance an equitable adjustment shall be made * * *

The parachute (known as Parachute-Unit M6 with Arming Wire Assembly for Anti-Ricochet Device) was to be manufactured in accordance with military specifications BP-P-1607 which were incorporated into the contract. The design and specifications for the M-6 parachute had been developed by Ordnance Ammunition Command, Joliet, Illinois. It was intended to be attached to a 500-pound bomb which could be dropped from an aircraft flying at low altitude, and the purpose of the parachute was to cause the bomb to come to rest within 750 feet from the aircraft’s slipstream to final halt. No deviation from the specifications and drawings was permitted except by authority of the contracting officer.

All Rainier’s parachutes were inspected by Army inspectors during manufacture, and all satisfactorily complied with the contract specifications and drawings. After completion, however, it was required that they be subjected to ballistic tests conducted by Aberdeen Proving Ground, Maryland. Rainier tendered 59 lots for ballistic testing, varying in size from less than 600 to as high as 1500 units. From each lot, six parachutes were selected for testing at Aberdeen. If the test sample passed, the entire lot was accepted; if it failed, a retest was made using new samples from the lot which may or may not have been reworked. Pertinent contract provisions with respect to these ballistic test procedures follow:

b. Investigation of failures. Whenever the rejection of complete rounds or loaded components, containing parts or materials supplied to the contractor by the Government is based upon the failure to meet the requirements of a proving ground test, the Government shall investigate with a view to determining the cause of failure. If such an investigation discloses that the contractor is responsible for the failure, he shall remedy the condition at his own expense, and after so doing, the test in the phase or phases under which the failure occurred shall be repeated. If this investigation does not disclose that the contractor is responsible for the failures, the material shall be accepted for payment and disposition of the lot shall be determined by the Chief of Ordnance. ******
E-5a. Not more than one parachute shall fail to limit the travel of the bomb, from slipstream to final rest, as follows:
******
M6, 750 feet maximum
****** F-6b. MS units. Assemble 6 units to inert loaded 500-pounds G.P. bombs equipped with inert fuzes. Insert the arming wires through the latches and vane shaft. Release the bombs individually, for impact on normal soil, from a plane flying at a calibrated indicated air speed of 350 miles per hour in level flight and at an altitude of approximately 100 feet. Observe to determine if the fuze arms.
F-6c. Retest. A retest, using the same number of samples used in the original test will be permitted if requested by the contractor provided not more than 2 units fail to meet the requirements of paragraph E-5a.

Rainier’s first lot was tested and rejected on January 4, 1954. After Rainier had reworked the lot, it was retested on January 19, and was accepted. The next eight lots were accepted on their first tests. The tenth lot was tested and rejected on March 18, but the following day was retested and accepted. *978 There were no more test failures until the fifteenth lot which failed its test on April 15, and 5 days later again failed on retest. The seventeenth and eighteenth lots were rejected April 30 and May 4, respectively, and failed their retests on May 4. Rainier’s officers were very concerned about the rejection of these three lots that had failed on retesting which comprised 3075 parachutes and represented more than $200,000 for which Rainier could not be paid. They feared that future lots might also fail the ballistic tests and be rejected. To them, the ballistic tests were unfair because admittedly Rainier was manufacturing the parachutes strictly in accordance with the specifications and drawings, yet some lots were failing the tests, and no one in the New York Ordnance District (which was administering the contract) was able to tell them the reason for the failures.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Energy Northwest v. United States
641 F.3d 1300 (Federal Circuit, 2011)
Energy Northwest v. United States
91 Fed. Cl. 531 (Federal Claims, 2010)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Environmental Tectonics Corp. v. United States
72 Fed. Cl. 290 (Federal Claims, 2006)
Bluebonnet Savings Bank FSB v. United States
67 Fed. Cl. 231 (Federal Claims, 2005)
Bluebonnet Sayings Bank v. United States
47 Fed. Cl. 156 (Federal Claims, 2000)
Detroit International Bridge Co. v. United States
39 Cont. Cas. Fed. 76,711 (Federal Claims, 1994)
American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
Gulf Contracting, Inc. v. United States
37 Cont. Cas. Fed. 76,128 (Court of Claims, 1991)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
District of Columbia v. C.J. Langenfelder & Son, Inc.
558 A.2d 1155 (District of Columbia Court of Appeals, 1989)
Gevyn Construction Corp. v. The United States
827 F.2d 752 (Federal Circuit, 1987)
Gevyn Construction Corp. v. United States
33 Cont. Cas. Fed. 74,851 (Court of Claims, 1986)
Hoffman Construction Co. v. United States
32 Cont. Cas. Fed. 73,279 (Court of Claims, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
404 F.2d 975, 186 Ct. Cl. 189, 1968 U.S. Ct. Cl. LEXIS 189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-bell-sophie-karp-hyman-m-oberman-lena-smith-the-rainier-cc-1968.