T. C. Bateson Construction Co. v. United States

149 Ct. Cl. 514, 1960 U.S. Ct. Cl. LEXIS 88, 1960 WL 8472
CourtUnited States Court of Claims
DecidedApril 6, 1960
DocketNo. 432-57
StatusPublished
Cited by18 cases

This text of 149 Ct. Cl. 514 (T. C. Bateson Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. C. Bateson Construction Co. v. United States, 149 Ct. Cl. 514, 1960 U.S. Ct. Cl. LEXIS 88, 1960 WL 8472 (cc 1960).

Opinion

MaddbN, Judge,

delivered the opinion of the court:

Tbe plaintiff had a contract with the Government to construct maintenance hangars and related facilities at the Ardmore Air Force Base at Ardmore, Oklahoma. The work included the construction of a number of reinforced steel and concrete caissons some 50 feet deep, as foundations for the hangars. The concrete in fifteen of the caissons did not have the compressive strength required by the contract, and the plaintiff was required by the Government to remedy this defective work by placing additional caissons adjacent to the defective ones. The cost of the remedial work was some $14,000. The plaintiff says that the weakness of the concrete was due to the fault of the Government in designing the concrete mis, and that the Government had no right to require the plaintiff to remedy the defect at the plaintiff’s own expense. The instant suit is for the recovery of the cost of the remedial work.

The plaintiff subcontracted the construction of the caissons to a partnership hereinafter called Saxet. Saxet obtained its concrete from a corporation hereinafter called Ardmore. The specifications of the plaintiff’s contract with the Government prescribed five and one-half bags of cement per cubic yard of concrete for the concrete mix for the caissons, but also provided that if the plaintiff should be directed by the contracting officer to use more or less than that amount of cement, the Government would pay extra for the larger amount and would receive credit for the smaller amount.

The specifications provided that the concrete in the caissons should be strong enough to bear a weight of 3,000 pounds per square inch (p.s.i.) when it had set for 28 days. Before the pouring of the concrete began, the Government concluded, from its experience with other concrete work at the same air base, under identical conditions, that concrete of the prescribed strength could be produced by using only five bags of cement per cubic yard. The contracting officer thereupon directed that only five bags be used in the plaintiff’s caisson work.

The contracting officer permitted the use of ready-mixed concrete for the caissons. It was brought to the site in [516]*516Ardmore’s trucks which, had revolving drums with fins inside them to mix the cement, crushed rock, sand and water. Before the concrete was dumped from the trucks into the caisson excavations, samples were taken from each truck load for testing purposes. There was a slump test, to determine the workability of the concrete, i.e., whether it would compact well around the reenforcing bars and at the outside of the caissons without leaving voids. The water content of the mix had a good deal to do with the slumping quality of the concrete. The result of the slump test could be determined immediately. But the test for compressive strength, made by placing sample cylinders of the concrete under pressure, after seven days for a preliminary test, and after 28 days for a final test, necessarily created the risk that caissons would be filled with concrete which had set beyond the possibility of removal, and the samples taken from that concrete at the time it was poured would show that the concrete was lacking in compressive strength.

The first concrete was placed in the caissons on July 2, 1954. The seven-day test of samples of that concrete showed that it had very little compressive strength. Concrete was placed in other caissons on July 6. The seven-day tests of this concrete showed that it was quite strong. Caissons poured on July 7 had an average compressive strength of 4,187 pounds p.s.i. after 28 days. Those poured on July 8 and 9 tested only some 1,500 pounds. The final 28-day tests of course came long after the pouring.

At a conference on August 11 of the Government’s representatives and representatives of the plaintiff, Saxet and Ardmore, it was agreed that the cement in the mix should be increased to five and one-half bags per cubic yard; that only two cubic yards instead of three should be mixed in the mixing trucks in each batch; that all the materials in each batch should be thoroughly mixed before the water was added; that the mixing drums on the trucks should be revolved 100 times, instead of not less than 50 nor more than 100, as the practice had been. In addition to these agreed measures, Ardmore was directed to spray the stockpile of crushed stone, which was to be used in the aggregate, every [517]*517day to keep it from being overdry and absorbing too much of the water in the mix.

The concrete work was resumed after August 11, and the new procedures were followed. None of the caissons poured after that time were rejected on the ground that they contained defective concrete.

Investigation continued as to how many of the caissons poured before August 11 were defective. Core borings taken from some of them showed the concrete, even within the same caisson, to have good concrete at one depth and weak concrete at another depth. In all, 15 caissons were found to be defective.

As we have seen, the plaintiff was required to remedy the defects. It says that the reason for the weak concrete was the Government’s reduction of the cement content from five and one-half bags to five bags per cubic yard. It points to the fact that there was no more weak concrete after August 11, when the use of the five and one-half bag mixture began. The Government says that the cement content in the mix was not the cause of the trouble; that other caissons at the same area and poured under the same conditions, with the five-bag mixture, were not defective; that ten of the 25 caissons poured by Ardmore before August 11, using the five-bag mixture, had the required compressive strength; that the Portland Cement Association, which would be interested in selling as much cement as possible, says in its manual that a five-bag mix will produce concrete having compressive strength of from 4,000 to 5,500 pounds per square inch.

After the remedial work had been done, the plaintiff submitted to the contracting officer a claim for the cost of that work. The contracting officer denied the claim on the ground that the defective concrete resulted from insufficient or improper mixing of the concrete by Ardmore. The plaintiff appealed to the Corps of Engineers’ Claims and Appeals Board which denied the claim on substantially the same grounds. The plaintiff appealed to the Armed Services Board of Contract Appeals. That Board adopted the findings and conclusions of the Engineers’ Board and denied the plaintiff’s appeal. This suit followed.

[518]*518The “Disputes Clause,” Article 6 of the plaintiff’s contract with the Government, provided that determination by the Board of Contract Appeals would,

* * * unless determined by a court of competent jurisdiction to have been fraudulent, arbitrary, capricious or so grossly erroneous as necessarily to imply bad faith, be final and conclusive upon the parties hereto.

The Act of May 11, 1954, 68 Stat. 81, 41 U.S.C. § 321, which is the so-called Wunderlich Act, says that in situations where the contract provides for finality of the decision by the head of the pertinent Government department or his duly authorized representative or board, such decision

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Titan Pacific Construction Corp. v. United States
35 Cont. Cas. Fed. 75,693 (Court of Claims, 1989)
Schnip Building Co. v. United States
645 F.2d 950 (Court of Claims, 1981)
Foster Wheeler Corp. v. United States
513 F.2d 588 (Court of Claims, 1975)
Kaminer Construction Corp. v. United States
488 F.2d 980 (Court of Claims, 1973)
H. N. Bailey & Associates v. The United States
449 F.2d 376 (Court of Claims, 1971)
Koppers Company, Inc. v. The United States
405 F.2d 554 (Court of Claims, 1968)
Dittmore-Freimuth Corp. v. The United States
390 F.2d 664 (Court of Claims, 1968)
Midwest Spray & Coating Co. v. United States
176 Ct. Cl. 1331 (Court of Claims, 1966)
National Concrete & Foundation Co. v. United States
170 Ct. Cl. 470 (Court of Claims, 1965)
Lee Hoffman v. The United States
340 F.2d 645 (Court of Claims, 1964)
Hoffman v. United States
166 Ct. Cl. 39 (Court of Claims, 1964)
River Construction Corp. v. United States
159 Ct. Cl. 254 (Court of Claims, 1962)
Keco Industries, Inc. v. United States
157 Ct. Cl. 691 (Court of Claims, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
149 Ct. Cl. 514, 1960 U.S. Ct. Cl. LEXIS 88, 1960 WL 8472, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-c-bateson-construction-co-v-united-states-cc-1960.